IFB_25-075-RM_Bid_Tabulation.pdf

PDF 142 KB Posted

Attached to
A New Exit Stairway and Exit Door in the Lackey Service Center Substation Area
Solicitation number
IFB 25-075-RM
Issued by
Polk County, Lake Harbor CDP, Florida

About this file

This is a bid tabulation document from the Kissimmee Utility Authority (KUA) for Invitation for Bid (IFB) 25-075-RM, concerning the installation of a new exit stairway and exit door in the Lackey Service Center Substation Area located in Kissimmee, Florida. The solicitation was opened on November 18, 2025, at 2:00 PM. KUA seeks a qualified, competent, and State of Florida licensed/certified contractor to install an exit door and stairway per the Engineer's drawings (Exhibit B), with the winning bidder responsible for obtaining all required permits. The project scope includes fixed-price work in accordance with KUA's specifications and service protocols, with potential additions or deletions during the contract term as dictated by operational needs.

Four vendors submitted timely bids for this project: Grove Construction Corporation at $89,500.00 (apparent low bidder), High Standard Construction at $93,450.15, MVB & Associates, Inc. at $109,936.00, and Urban Enterprise/Main Enterprise LLC at $92,800.00. All bids are subject to KUA's terms and conditions, and any additional terms submitted by bidders are rejected unless previously approved by the Authority through addenda. The bid tabulation was opened by Ramandeep Mann and verified by Jennifer Grieves. Any offers not received by the solicitation opening date and time are rejected as late.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Kissimmee Utility Authority

Finance & Administration Solicitation Number: IFB 25-075-RM

1701 W. Carroll Street Solicitation Title

A New Exit Stairway and Exit Door in the Lackey

Service Center Substation Area

Kissimmee, Florida 34741 Solicitation Opening Date: 11/18/25

Phone: (407) 933-9809 Solicitation Opening Time 2:00 PM

Fax: (407) 932-3286

VENDOR NAME→ Grove Construction Corporation High Standard

Construction MVB & Associates, Inc Urban Enterprise/Main Enterprise LLC

A New Exit Stairway and Exit

Door in the Lackey Service

Center Substation Area $89,500.00 $93,450.15 $109,936.00 $92,800.00

TOTAL BID PRICE AS SUBMITTED $89,500.00 $93,450.15 $109,936.00 $92,800.00

OPENED BY:Ramandeep Mann VERIFIED BY: Jennifer Grieves

Solicitation Tabulation

Remarks: Offers from the vendors listed herein are the only offers received timely as of the above opening date and time. All other offers submitted in response to this solicitation, if any, are hereby rejected as late. Shaded or circled total price indicates apparent low bidder subject to evaluation and review before an intent to award is made.

Rules: All bids accepted by Kissimmee Utility Authority are subject to the Agencies terms and conditions and any and all additional terms and conditions submitted by the bidders are rejected and shall have no force and effect unless receiving prior consideration and approval of the Authority in the form of Addenda to this bid.

Copy of IFB 25-075-RM Bid Tabulation.xls page 1 of 1

File details come from the government source that posted it. Updated .