This document is a comprehensive set of Special Provisions for a roadway improvement project issued by the City of Tucson Department of Transportation and Mobility in Pima County, Arizona. The project involves reconstructing and widening Valencia Road from Kolb Road to Houghton Road, spanning approximately 4.27 miles, to create a six-lane divided roadway. The construction will include new asphaltic concrete pavement, aggregate base course, cement treated subgrade, raised medians, concrete curbs and sidewalks, asphaltic concrete paths, concrete curb access ramps, drainage facilities, storm drain systems, pavement markings, signage, pedestrian handrails, landscaping, and utility adjustments. The contract has a total duration of 550 calendar days for the construction phase, followed by a 24-month landscape establishment period.
The project is funded through local transportation infrastructure resources, with provisions for potential market price adjustments to account for material cost fluctuations. The total project budget is not explicitly stated, but the contract includes detailed specifications for various bid items with unit pricing. Bidders are required to submit comprehensive documentation, including mix designs, material certifications, and traffic control plans. The project incorporates specific requirements for environmental compliance, including stormwater management, dust control, and native plant preservation. Contractors must also coordinate with multiple utility providers and adhere to strict traffic maintenance protocols, ensuring minimal disruption to local businesses and residents during construction.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Special Provisions Valencia Road, Kolb Rd to Houghton Rd
Plan I-2020-021
SP-1
VALENCIA ROAD
KOLB ROAD TO HOUGHTON ROAD
ROADWAY IMPROVEMENTS
SPECIAL PROVISIONS
COT Job No. SR14
COT Plan No. I-2020-021
PCRWRD No. UPC-2020-130
Psomas Project No. 7TUS160201
May 2024
SP-3
TABLE OF CONTENTS
TABLE OF CONTENTS
SPECIFICATIONS AND DETAILS
PROJECT LOCATION AND SCOPE OF WORK
GENERAL PROVISIONS
SECTION 101 - ABBREVIATIONS AND TERMS
SECTION 102 - BIDDING REQUIREMENTS AND CONDITIONS
SECTION 103 - AWARD AND EXECUTION OF CONTRACT
SECTION 104 - SCOPE OF WORK
ITEM 1040001 - PARTNERING
SECTION 105 - CONTROL OF WORK
SECTION 106 - CONTROL OF MATERIAL
SECTION 107 - LEGAL RELATIONS AND RESPONSIBILITY TO PUBLIC
SECTION 108 - PROSECUTION AND PROGRESS
SECTION 109 - MEASUREMENT AND PAYMENT
ITEM 1091301 - MARKET PRICE ADJUSTMENT
SECTION 201 - CLEARING & GRUBBING
ITEM 2010004 - PRESERVATION FENCING
SECTION 202 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS
ITEM 2020012 - REMOVAL OF ENCROACHMENTS ALLOWANCE
SECTION 203 - EARTHWORK
SECTION 206 - FURNISH WATER SUPPLY
SECTION 302 - CEMENT TREATED SUBGRADE
SECTION 404 - BITUMINOUS TREATMENTS
SECTION 406 - ASPHALTIC CONCRETE
ITEM 4060011 - PAVEMENT PATCH (STD DTL 216) (TYPE I)
SECTION 501 - DRAINAGE PIPE
SECTION 503 - CONCRETE STORM DRAIN CATCHMENTS
SECTION 509 - SANITARY SEWER MANHOLES
ITEM 5090500 - MANHOLE REHABILITATION AND CORROSION
PROTECTIVE COATING:
SP-4
SECTION 510 - POTABLE WATER SYSTEMS
ITEM 5102414 - TEMPORARY LINE STOP, 8”
ITEM 5102415 - TEMPORARY LINE STOP, 16”
ITEM 5103101 - POTABLE WATER, ADJUST EXISTING VALVE BOX AND
COVER
ITEM 5103205 - POTABLE WATER, FIRE HYDRANT
ITEM 5105010 - POTABLE WATER PIPE, NON-CA, REMOVE & DISPOSE, 10” &
SMALLER
ITEM 5105012 - POTABLE WATER PIPE, NON-CA, REMOVE & DISPOSE, 12” &
LARGER
ITEM 5105110 - POTABLE WATER PIPE, CA, REMOVE & DISPOSE, 10” &
SMALLER
ITEM 5105112 - POTABLE WATER PIPE, CA, REMOVE & DISPOSE, 12” &
LARGER
ITEM 5105310 - POTABLE WATER, REMOVE & SALVAGE FIRE HYDRANT
ITEM 5108124 - METER RELOCATION, SERVICE LINE ADJUSTMENT, (M/A)
1”
SECTION 515 - UTILITY IMPACTS
ITEM 5150005 - UTILITY POTHOLING, DEPTH LESS THAN TWELVE FEET
(12’)
SECTION 601 - CONCRETE STRUCTURES
ITEM 6010101 - BOX CULVERT 1 (2 - 10’ x 4’)
ITEM 6010102 - BOX CULVERT 2 (7 - 10’ x 4’)
ITEM 6016086 - PIPE CULVERT HEADWALL (ADOT STD. DWG. SD-6.30)
SECTION 607 - SIGN SUPPORTS
ITEM 6070010 - SIGN POST (PERFORATED) (SINGLE)
ITEM 6070110 - FOUNDATION FOR SIGN POST (PERFORATED)
ITEM 6072001 - SIGN MOUNT ASSEMBLIES (POLE MOUNTED) (METRO
SIGNS)
SECTION 608 - SIGN PANELS
ITEM 9080021 - STREET NAME SIGN PANEL (POLE MOUNTED)
ITEM 6080302 - RADAR SPEED SIGN (SOLAR) (SPEED MANAGEMENT)
SECTION 701 - MAINTENANCE AND PROTECTION OF TRAFFIC
SP-5
SECTION 704 - THERMOPLASTIC STRIPES AND MARKINGS
SECTION 705 - PREFORMED PLASTIC PAVEMENT MARKING
SECTION 706 - RAISED PAVEMENT MARKERS
SECTION 707 – TUBULAR MARKER (FLEXIBLE)
SECTION 708 - PAINTED PAVEMENT MARKINGS
SECTION 730 - GENERAL REQUIREMENTS FOR TRAFFIC SIGNAL AND
STREET LIGHTING SYSTEMS
SECTION 732 - ELECTRICAL MATERIAL AND SERVICE
ITEM 7320415 - PULL BOX (SPECIAL) (CONCRETE-POLYMER)
ITEM 7320455 - PULL BOX (ITS)
ITEM 7320459 - VAULT (FIBER OPTIC)
ITEM 7320460 - FIBER OPTIC SPLICE CLOSURE
ITEM 7320670 - SINGLE MODE FIBER OPTIC CABLE (12 FIBER)
ITEM 7320677 - SINGLE MODE FIBER OPTIC CABLE (144 FIBER)
ITEM 7320800 - METER SERVICE PEDESTAL CABINET
ITEM 7320888 - ELECTRICAL SERVICE INSTALLATION FEES ALLOWANCE
SECTION 733 - SIGNAL INDICATIONS AND MOUNTING ASSEMBLIES
ITEM 7330250 - TATTLETALE LIGHT (LED) (BLUE)
SECTION 734 - TRAFFIC SIGNAL CONTROLLER ASSEMBLY
ITEM 7340060 - FIBER OPTIC NETWORK INTERFACE (LIU)
ITEM 7340065 – FIBER OPTIC MANAGED SWITCH (CISCO)
SECTION 735 - DETECTORS
ITEM 7350011 - VIDEO DETECTION SYSTEM (AGENCY SUPPLIED /
CONTRACTOR INSTALLED) (4-CAMERA)
SECTION 736 - STREET AND SIGN LIGHTING
SECTION 737 - INCIDENTAL ELECTRICAL WORK
ITEM 7370100 - TEMPORARY TRAFFIC SIGNALS
ITEM 7370200 - REMOVE AND SALVAGE EXISTING ELECTRICAL
EQUIPMENT
ITEM 7370220 - INCIDENTAL ELECTRICAL WORK
SECTION 802 - LANDSCAPE GRADING
SP-6
SECTION 803 - LANDSCAPE BORROW AND PLATING MATERIAL
SECTION 805 - SEEDING
SECTION 806 - TREES, SHRUBS AND PLANTS
ITEM 8061700 - LANDSCAPE PRUNING
SECTION 807 - LANDSCAPE ESTABLISHMENT
ITEM 8070012 - MISCELLANEOUS LANDSCAPE WORK ALLOWANCE
(LANDSCAPE ESTABLISHMENT MAINTENANCE)
SECTION 808 - LANDSCAPE IRRIGATION SYSTEM
SECTION 809 - NATIVE PLANT SALVAGE
SECTION 810 - EROSION CONTROL AND POLLUTION PREVENTION
SECTION 908 - CONCRETE CURBS, GUTTERS, SIDEWALKS AND
DRIVEWAYS
SECTION 924 - CONTRACTOR QUALITY CONTROL
ITEM 9240170 - CONTRACTOR QUALITY CONTROL
SECTION 926 - ENGINEER’S FIELD OFFICE
SECTION 930 - INCIDENTAL ITEMS
ITEM 9300109 - MISCELLANEOUS WORK (MINOR ALTERATIONS IN
DETAILS OF CONSTRUCTION)
ITEM 9300114 - MISCELLANEOUS WORK (PUBLIC ART LOCATION)
SECTION 932 - PAVERS
ITEM 9320010 - BRICK PAVERS
SECTION 975 - TELECOMMUNICATIONS INFRASTRUCTURE DOT FORMAT ...300
SECTION 1005 - BITUMINOUS MATERIALS FOR SURFACING
SECTION 1007 - RETROREFLECTIVE SHEETING
SP-7
LIST OF APPENDICES
APPENDIX A - SUBGRADE ACCEPTANCE CHART
APPENDIX B - US ARMY CORP OF ENGINEERS
NATIONWIDE PERMIT NUMBER 14 – LINEAR TRANSPORTATION PROJECTS
APPENDIX C - PUBLIC ART FOUNDATION
SP-8
SPECIFICATIONS AND DETAILS
The work embraced herein shall be performed in accordance with the requirements of the following documents:
Specifications
Pima Association of Governments (PAG), Standard Specifications for Public Improvements, 2015 Edition.
http://apps.pagnet.org/standardspecifications/
Arizona Department of Transportation, Highways Division, Standard Specifications for Road and Bridge Construction, 2021 Edition.
https://azdot.gov/sites/default/files/media/2021/04/2021_Standard_Specifications_for_Road_and _Bridge_Construction_PC.pdf
Details
Pima Association of Governments (PAG), Standard Details for Public Improvements, 2015 Edition, except as modified on the plans.
http://apps.pagnet.org/standardspecifications/
City of Tucson Department of Transportation, Access Ramp Details, April 2007. See Appendix A of these Special Provisions (Attachment C, Sheets 1 through 7).
City of Tucson Department of Transportation, Street Name Sign Layouts for Signalized and Unsignalized Intersections.
https://www.tucsonaz.gov/files/transportation/Signalized_07-30-10.pdf https://www.tucsonaz.gov/files/transportation/Unsignalized_07-30-10.pdf
Arizona Department of Transportation, Highways Division, Construction Standard Drawings, (C-Drawings), May 2012 and current revisions.
http://www.azdot.gov/docs/default-source/roadway-engineering-library/2012constructionstandarddrawings.pdf
Arizona Department of Transportation, Highways Division, Bridge Group Structure Detail Drawings (SD series), current edition.
http://www.azdot.gov/business/engineering-and-construction/bridge/structure-detail-drawings/overview
SP-9
Arizona Department of Transportation, Highways Division, Signing and Marking Standard Drawings, June 2014 and current revisions.
http://azdot.gov/business/engineering-and-construction/traffic/signing-and-marking-standard-drawings/current-test
Manuals
U.S. Department of Transportation, Federal Highway Administration, Manual on Uniform Traffic Control Devices for Streets and Highways, December 2009 and amendments.
http://mutcd.fhwa.dot.gov/pdfs/2009/pdf_index.htm
Arizona Supplement to the Manual on Uniform Traffic Control Devices (MUTCD), 2009 edition (January 2012).
http://www.azdot.gov/Highways/Traffic/Standards.asp
2015 Edition of the Additions by the City of Tucson to the Manual on Uniform Traffic Control
Devices, for Temporary Traffic Control.
http://www.tucsonaz.gov/tdot/traffic-engineering-resources
City of Tucson Department of Transportation, Traffic Signal Design Manual, May 2003 and current revisions.
https://www.tucsonaz.gov/files/transportation/Design_Manual.pdf
Pima County/City of Tucson, Signing and Pavement Marking Manual, 2020, First Edition.
https://webcms.pima.gov/UserFiles/Servers/Server_6/File/Government/Transportation/Roadway %20Design/FINAL-Pima-County_City-of-Tucson-Signing-and-Pavement-Marking-Manual- 2020-First-Edition_linking_nocomments-12_21.pdf
City of Tucson Department of Information Technology / Infrastructure Engineering Division Telecommunication Requirements for New and Existing City Facilities, 2019 (Contact DTM for manual).
Pima County Department of Transportation, Street Lighting and ITS Conduit Design Manual, August 2006 and current revisions.
https://webcms.pima.gov/UserFiles/Servers/Server_6/File/Government/Wastewater%20Reclama tion/Energy%20Management/Biogas/StreetLight-Conduit-Manual.pdf
Other Specifications and Details
Tucson Water Standard Specifications and Details Manual, 2017 Edition and current revisions.
https://www.tucsonaz.gov/water/spec-book
SP-10
Pima County Regional Wastewater Reclamation Department Standard Specifications and Details for Construction, 2022.
www.pima.gov/wastewaterreclamation/standards
SP-11
PROJECT LOCATION AND SCOPE OF WORK
The proposed work is located within Sections 8, 14, 15, 16, 17, 21, 22 and 23 of Township 15 South, Range 15 East, Gila and Salt River Meridian, Pima County, Arizona.
This project consists of furnishing all labor, materials, and equipment necessary to reconstruct and widen the existing Valencia Road to a six-lane divided roadway between Kolb Road and Houghton Road. The project limits along Valencia Road will extend from east of the Valencia Road and Kolb Road intersection to west of the Valencia Road and Houghton Road intersection for a total length of 4.27 miles. The project also includes the reconstruction of side streets and driveways.
The work includes, but is not limited to, the construction of new asphaltic concrete pavement, aggregate base course, cement treated subgrade, raised medians, concrete curb, concrete sidewalk, asphaltic concrete path, concrete curb access ramps, cross drainage facilities, storm drain facilities, pavement markings, signing, pedestrian handrails, landscaping and native re-vegetation, utility adjustments, and other related incidental work as shown on the City of Tucson Plan No. I-2020-021.
SP-12
GENERAL PROVISIONS
For these Special Provisions, the terms Agency, Department, City, City of Tucson, and Engineer are synonymous.
1. Project Objectives
The objective of this contract is to complete construction as quickly as possible while minimizing the impact to the Stakeholders. The Stakeholders are, but not limited to, the adjacent businesses, schools, commuters, buses, emergency services, pedestrians, bicyclists, and adjoining neighborhoods. As such, this work will be accomplished in an orderly manner as defined herein.
Driver and pedestrian/access shall be maintained during the construction of improvements.
Temporary paved access shall always be provided by the contractor to meet the Americans with Disabilities Act (ADA) requirements. The contractor is advised that an approved construction sequencing scheme meeting the intent of the project objectives will need to be followed. Once approved, the contractor shall follow the phasing plan unless modified by the Engineer in writing.
2. Project Limits and Restrictions
The contractor shall perform all work within the public right-of-way, legally obtained easements including temporary construction easements (TCEs), legally obtained rights-of-entry (ROE), and legally acquired property by the City of Tucson. The contractor shall assume all responsibility and liability for any encroachment upon private property. The use of private property for construction yards will be allowed only if zoning requirements allows its use for this purpose – see Section 106-9 of the Standard Specifications for further details regarding temporary construction yards. The cost of the construction yard is considered incidental to the project.
Under no circumstances shall any equipment, vehicles or other construction items, not specifically required or needed for the immediate construction at hand, be stored or left on private property without the express written permission of the property owner.
The contractor shall field verify all existing conditions shown on plans and specified herein prior to beginning construction. Any significant deviations to the conditions that may affect the timely construction of improvements shall be brought to the attention of the Engineer within 24 hours of discovery. Prior to delivery of any equipment, materials or supplies to the site of any work, or the beginning of any construction work, it is strongly recommended that the contractor take pre-construction photos or videos as deemed appropriate for establishing the conditions existing in all the areas that may be affected by the construction.
SP-13
3. Contract Time
Once the contract has been awarded and signed, the contractor shall be issued a Notice to Proceed (NTP). This will begin Phase 1 of the project, the construction phase, and the contractor shall have 550 calendar days to complete this work as shown on the project plans and as specified herein.
Phase 2 of the contract shall encompass the 24-month (730 consecutive calendar days) Landscape Establishment period as detailed in Section 807. All other items of work shall be completed and accepted (via acceptance of the roadway and/or drainage phase of the work) by the Engineering Representative prior to the commencement of Phase 2. The contractor shall obtain the acceptance of the previous phase(s) following a Final Inspection of that phase.
If the Final Inspection should reveal work that is not completed or is unacceptable to the Engineer for any reason, a "punch list" of these items shall be generated and provided to the contractor. Substantial completion (for the purpose of stopping the contract time) will be granted in accordance with Section 105-21 of the Standard Specifications.
Once substantial completion is granted, the contractor shall actively work to achieve final acceptance of the construction phase of the contract within 15-calendar days from the substantial completion date of that phase. Failure to prosecute the remaining work within this time period will result in the resumption of time charges and the application of liquidated damages from the date scheduled for final acceptance.
When the work on this list has been satisfactorily completed, final acceptance of the phase(s) shall be given for all items of work other than Landscape Establishment. At this time the Landscape Establishment period shall begin, and the monies retained for all items of work other than Landscape Establishment (ITEM 8070001) shall be released.
Through the duration of the Landscape Establishment period, the Agency shall retain 10% of the cost of the aforementioned items of work or a minimum of $2,000.00, whichever is greater. (The amount retained for ITEM 8070001 shall not exceed 5% of the total contract bid amount).
Upon completion of the Landscape Establishment period, a final inspection will be held with Engineering and Streets Division staff to ensure that all plants are healthy and acceptable.
Prior to delivery of any equipment, materials or supplies to the site of any work, or the beginning of any construction work, it is strongly recommended that the Contractor take pre-construction photos or videos as deemed appropriate for the purpose of establishing the conditions existing in all the areas that may be affected by the construction.
SP-14
4. Construction Scheduling
Various activities within the community must be considered in the project scheduling to provide the most effective and least impacting effort. The following dates are provided for information and shall be referred to when planning work and lane restrictions:
Christmas Retail Season .......................................................................... Nov. 1st to Jan. 2nd Gem and Mineral Show ........................................................................ Jan. 27th to Feb. 11th Pima County Fair .............................................................................. April 18th to April 28th Tucson Water Department Restrictions ............................................... April 1st to Sept. 30th SWG Construction Restrictions .................................................... October 1st to March 30th TEP Construction Restrictions ........................................................... May 1st to August 30th School Session ..................................................................................... July 17th to May 24th
The contractor shall factor these events into his construction schedule. The contractor may do incidental work during these restrictions to complete areas that are not specifically described herein if no additional impacts to commuters, businesses, and residents are imposed and the work is previously approved by the Engineer.
Work requiring lane restrictions beyond the minimum stated herein shall be done at night unless approved by the Engineer.
The intent of this project is to complete the work as quickly as possible to minimize any inconvenience to the traveling public, or adjacent stakeholders. To that end, the contractor is strongly encouraged to consider working weekends, double shifts, or as often as necessary to complete the work by the specific milestones. Lost time due to little or no work being performed shall not be considered when applying for a contract time extension.
5. Maintenance & Protection of Traffic
The contractor shall be responsible for all construction zone traffic control and shall provide a traffic control plan in accordance with Section 701 of the Standard Specifications, these Special Provisions and shall be approved by the Engineer prior to construction.
The traffic control plans shall meet the conditions and requirements described in Subsection 104- 5 of these Special Provisions.
The contractor shall not allow any work to commence unless the conditions and requirements of Subsection 104-5 Maintenance of Traffic are adhered to. If the contractor fails to abide by the conditions and requirements of this specification section, it shall be considered sufficient grounds for the City to suspend the contractor’s work.
SP-15
The existing traffic signal operations at the Old Vail Road and the Nexus Road intersections shall be operational and continuous twenty-four (24) hours per day seven (7) days a week. Any periods of time for which the signals are temporarily out of service shall be controlled by uniformed law enforcement agency personnel.
6. Construction Sequencing
Unless otherwise approved by the Engineer, it is anticipated that the contractor will construct the project in two major phases as follows:
Phase 1 – The contactor shall maintain traffic on the existing roadway while constructing the north half of the roadway.
Phase 2 – The contractor shall move traffic to the newly constructed travel lanes and construct the south half of the roadway.
7. Disposal of Material
All construction debris, rubble, excess, surplus and unsuitable materials structures and obstructions, except as hereafter specified, shall be removed from the job site and disposed of by the contractor at a site previously secured by the contractor, and done in a manner approved by the Engineer.
Disposal shall be the responsibility of the contractor. However, the contractor shall, with each and every disposal site arranged for (other than commercial waste sites), provide the Engineer with a copy of the written approval of the property owner indicating that the property owner is fully aware of what the material consists. The contractor shall also provide a letter to the Engineer from the City or County (whichever has jurisdiction), giving site approval for materials disposal at each site to be used. The approval letter shall be received and approved by the Engineer prior to the disposal of any materials at any site.
Costs associated with the disposal of these materials shall be incidental to the related items of work. Fees associated with the disposal of these materials shall be paid by the contractor.
All material removals shall be transported and legally disposed of from the project site the same day they are removed. Stockpiling of removed materials within the public rights-of-way shall not be allowed unless previously approved and directed by the Engineer. The location of the disposal site shall be the responsibility of the contractor and the contractor shall identify in writing the quantity of materials removed and disposed of to that location.
Upon removal, existing material, including existing guardrail, anchors, breakaway cable terminals, posts, and hardware, shall become the property of the contractor unless otherwise specified in the project plans, or in these Special Provisions, or by the Engineer.
SP-16
Upon removal, disposal of the existing asphaltic concrete shall be the responsibility of the contractor. When approved by the Engineer, the contractor may stockpile and use it as recycled asphaltic concrete or dispose of it at an approved site. No measurement or direct payment will be made for disposal. The cost of disposing the removed AC pavement shall be incidental and considered as included in the cost of contract items.
If in good condition as determined and approved by the Engineer, removal of existing fence and gate material along the project limits may be salvaged and used for reconstruction of fence and gates at necessary locations.
8. Permits
Before undertaking any of this contract work at any location covered by this project, the contractor shall obtain all applicable business licenses and permits, including but not limited to:
water quality permits, air quality permits, traffic control and street closure permits, excavation/construction in the public rights-of-way permits, storm water pollution prevention plan, and any other permits required by ordinance and/or state and federal law.
The contractor shall be pay for all necessary fees, taxes and other costs associated with obtaining and securing all permits, including plan review. The costs associated with obtaining permits shall be considered incidental and inclusive with the associated items of work. No additional compensation will be provided.
Excavation permits for excavation/construction in the public rights-of-way will not be required when the work is administered by the Agency.
No separate payment shall be made for preparation of the traffic control plans, and the costs shall be included in the overall cost of the project. The overall cost shall also include applicable plan review and permit fees.
The City of Tucson is operating under a 404 Nationwide Permit for this project. A copy of the permit may be found in the Appendix. The contractor shall comply with all permit conditions.
The contractor shall file a Notice of Intent to use the statewide Construction General Permit for Discharge to Waters of the United States and a Notice of Termination when the site is stabilized with the Arizona Department of Environmental Quality (ADEQ). The contractor shall maintain and implement Pima County’s Stormwater Pollution Prevention Plan under the Construction General Permit. The contractor is directed to Section 810 of these Special Provisions and the Stormwater Pollution Prevention Plan for the project.
SP-17
Prior to any ground disturbing activity, the contractor shall obtain an Activity Permit from the Pima County Department of Environmental Quality. The contractor shall implement the standard specifications for dust suppression.
The contractor will be required to relocate certain water distribution facilities owned by Tucson Water and modify certain sanitary sewer system facilities owned by Pima County Regional Wastewater Reclamation Department (PCRWRD) as shown on the plans and hereinafter specified. The contractor shall obtain all construction permits required for this work. During construction operations, all contact between the contractor and Tucson Water or PCRWRD personnel will be through the Engineer. The contractor shall give all notices to the Engineer two (2) working days in advance of the notice periods required by Tucson Water and
PCRWRD.
9. Material Sources
No Agency designated materials source has of yet been identified for use on this project.
Contractor material sources shall be as specified in Section 1001 of the Standard Specifications.
10. Public Relations
Public relation services required for this project above and beyond what is specified in the Standard Specifications will be provided by the City of Tucson. The contractor shall work with the City of Tucson and/or its Public Relations firm for the duration of the contract to provide accurate and specific project schedule information needed to be communicated to the public.
This includes details of, but not limited to: lane restrictions, driveway and access closures, lane travel switches, detours, emergency closures, temporary closures, mail box locations, postal delivery, trash collection, newspaper delivery, and for all other services.
Communication to the stakeholders will be conducted in several ways. Contractor resident notifications shall advise of temporary work affecting access and/or utility service with start and end dates. The Tucson Department of Transportation and Mobility (DTM) will create a web page providing a general project overview and periodic project updates and contact information.
Message boards shall be used by the contractor to advise the traveling public of changes to the work zone. The contractor shall provide variable message boards at each entrance of the project work zone a minimum of seven (7) working days prior to starting work indicating the start of a different construction phase where travel times are affected or as directed by the Engineer.
The contractor shall participate in a “Construction Public Meeting” prior to the start of construction. Meeting date is to be set by the City of Tucson. The contractor shall, no later than seven (7) days, distribute to all residents and businesses abutting the project rights-of-way notices informing them of the intent by the City of Tucson to begin construction of this project.
Such notices shall be furnished to the contractor by the office of the City Engineer. Notices are not to be placed in mailboxes. Where there is no response or there is no answer at the door, the
SP-18
notice is to be left in the door/screen door. There shall be no separate pay item for the cost of the construction public meeting or notification letters. Cost shall be included as part of the overall job.
11. Construction Survey and Layout
Construction survey and layout, with the exception of pavement marking layout, will be provided by the City of Tucson.
12. Record Drawings
The contractor is responsible for keeping a set of record project pans on site for the annotation of changes in detail, location, and depth of all items constructed which vary from the contract documents that are made during the construction. LOCATION OF UTILITY POTHOLES (BID ITEM 5150005) SHALL BE IDENTIFIED ON THE RECORD DRAWINGS. The record project plans shall include any revised or added plan sheets. The cost of furnishing record drawings shall be considered as included in the overall cost of the project.
Upon completion of the work, the contractor shall transfer the annotated information to a clean set of the project plans. The dimensions and notations provided on the record project plans shall be complete, clear, and legible. No later than 60 calendar days after acceptance of the project or as directed by the Engineer, the contractor shall submit the dated record set of project plans along with a transmittal letter to the Engineer for review and acceptance. Final retention shall not be released until the record project plans are accepted by the Engineer. The contractor’s failure to furnish this item may delay the contract close-out.
13. Saw Cutting
The contractor’s work shall consist of saw cutting and/or wheel cutting the existing pavement where new asphaltic concrete (AC) and Portland cement concrete pavement (PCCP) is to match existing pavement surfaces. The contractor’s work shall also include saw cutting and/or wheel cutting existing Portland cement driveways, sidewalks, and curbs where new construction shall match the grade of these existing surfaces. Saw cuts shall be made to a minimum depth of 1½ inches and in all cases, deep enough to insure a neat vertical joint. Portland cement concrete that is damaged by the contractor’s saw cutting shall be replaced in kind at the contractor’s expense.
No measurement or direct payment will be made for saw cutting and/or wheel cutting, the cost being considered as included in the price of other contract items.
14. Existing Vegetation
Clearing limits must be approved in advance by the Engineer. Grading and construction near and around vegetation that is to be preserved-in-place may be required. The Engineer may require that specific vegetation remain within the construction limits in addition to what is shown in the
SP-19
project plans. The contractor and the Engineer shall tour the project site prior to any construction beginning and together verify what specific vegetation shall be preserved in place.
The contractor shall preserve in place some existing plant material in the Right-of-Way as shown on the project plans. The contractor shall prune exiting trees to remain in place and provide fencing as described in Sections 201 and 806 of these Special Provisions or as directed by the City Landscape Architect.
The contractor’s work to remove, salvage, or protect vegetation shall be in accordance with the Native Plant Preservation Plan. Existing project vegetation on this project shall not be disturbed by the contractor beyond those limits actually needed for the contractor’s construction purposes.
Those items unnecessarily damaged by the contractor shall be repaired or replaced at the contractor’s expense.
15. Contractor’s Environmental Requirements and Mitigation Measures
The contractor’s attention is directed to Section 107-14 of the Standard Specifications that requires conformance to all State and local air quality requirements.
To prevent the introduction of invasive species seeds, all earthmoving and hauling equipment shall be washed prior to entering the construction site and the contractor shall inspect all construction equipment and remove all attached debris, including plant parts, soil, and mud, prior to the equipment entering the construction site.
To prevent invasive species seeds from leaving the site, the contractor shall inspect all construction and hauling equipment and remove all debris, including plant parts, soil, and mud, prior to leaving the construction site.
Prior to the start of construction and before ground disturbing or earthmoving activities occur, the contractor shall treat noxious and invasive vegetation, particularly buffelgrass, in accordance with Section 201-3.04. Invasive species eradication shall continue throughout the entire project from clearing and grubbing through final project acceptance.
In compliance with Executive Order 13112 regarding invasive species, all disturbed soils that will not be landscaped or otherwise permanently stabilized by construction will be seeded using species native to the project vicinity.
In compliance with Executive Order 13112 regarding invasive species, all earth-moving and hauling equipment shall be washed prior to leaving the construction site to prevent invasive species seeds from leaving the site.
The contractor shall comply with all terms and conditions of the attached Section 404 Nationwide Permit 14 as established by the US Army Corps of Engineers.
SP-20
The contractor shall comply with all terms and conditions of the Conditional Section 401 Water Quality Certification certified by the Arizona Department of Environmental Quality.
If obliteration of yellow traffic paint is required, the contractor shall test the paint prior to obliteration. If the paint tests positive for lead, the contractor shall notify its employees that lead is present in the paint; therefore, the contractor shall notify their employees prior to any disturbance where lead is present in the paint below the 0.5 percent US Department of Housing and Urban Development/US Environmental Protection Agency action levels, but above the U5 Department of Labor Occupational Safety and Health Administration detection level. As part of the notification, the contractor shall make the US Department of Labor Occupational Safety and Health Administration pubIication_number_3142- 12R_2004_Lead_in_Construction (http://www.osha.gov/Publications/osha3142.pdf) available to workers.
The contractor shall prepare and implement a Stormwater Pollution Prevention Plan that meets the requirements of the construction general permit, including sampling and analysis plan, as necessary.
The contractor shall prepare and submit a notice of intent (NOI) for the project and shall provide the Stormwater pollution prevention plan and sampling and analysis plan, as necessary, to the Arizona Department of Environmental Quality.
The contractor shall prepare and submit a notice of termination (NOT) upon approval from the Engineer for the project to the Arizona Department of Environmental Quality.
The contractor shall not conduct any clearing, grubbing, or tree/limb removal from March 1 to August 31 unless a qualified biologist approved by the City of Tucson Department of Transportation has conducted a bird nest search of the affected vegetation and has determined that no active bird nests are present. Vegetation removal may occur if the area has been surveyed within 10 calendar days prior to removal as long as only inactive bird nests, if any, are present.
16. Archeological Features
If human remains, including human skeletal remains, cremations, and/or ceremonial objects and funerary objects are found during excavation or any activity related to construction in any part of the project area, ground disturbing activities must cease in the immediate vicinity of the discovery. Should artifacts or human remains be uncovered, the area will be taped off and the City of Tucson Engineer notified. The City of Tucson Engineer will immediately contact the City of Tucson Historic Preservation Department (520.837.6968) and arrange for the proper treatment of those resources. State laws ARS 41-865 and ARS 41-844 require that the Arizona State Museum (520-621-4795) be notified of the discovery by the contractor so that cultural groups who claim cultural or religious affinity to them can make appropriate arrangements for the repatriation and reburial of the remains. The human remains will be removed from the site by
SP-21
a professional archaeologist pending consultation and review by the Arizona State Museum and the concerned cultural groups.
The work is subject to delay in that location pursuant to ARS 41-844 while an examination takes place.
17. Hazardous Materials
If suspected hazardous materials are encountered during construction, work shall cease at the location and the Engineer shall be notified immediately to arrange for proper assessment, treatment, or disposal of those materials. The area will be taped off, and further investigation and clean up by the City of Tucson will follow. No adjustments will made due to work shut down. If potentially hazardous or contaminated materials are encountered, the contractor shall stop work and remove all workers within the contaminated area. For life threatening situations, follow the procedures in the Safety Plan, as specified in Subsection 107-7.02.
18. Utilities
Utility relocation work both shown and not shown on the project plans or noted in these Special Provisions will be the responsibility of the appropriate utility. All efforts have been made to avoid utility conflicts and assure as much of the utility work as possible was completed prior to the start of this project. If any relocation work is necessary due to additional conflicts, the utility companies will perform the relocation work during the project construction phases unless otherwise noted on the project plans. The contractor is hereby notified that the utility companies, in conjunction with the contract work, will perform their own utility relocation work. The contractor shall make every effort to cooperate fully with each utility company and acknowledges and agrees that delays to his operations may necessarily occur. Due to these delays that are anticipated by the utility companies, the Engineer will consider requests by the contractor for contract time extensions if necessary. The contractor will also acknowledge and agree that no monetary compensation will be given to the contractor by the Agency as a result of the impacts on the construction operations that are caused by the utility companies due to their anticipated work or delay. The contractor is also referred to Section 105-6 of the Standard Specifications, Cooperation With Utility Companies.
The contractor shall consider the extent of utility work in preparing the contract bid and project schedule. It will be the contractor’s responsibility, prior to bidding, to contact the appropriate utilities to obtain additional information such as relocation record drawings and/or as-builts, relocation sequencing, utility windows, construction time frames, and identification of areas requiring subgrade preparation by the contractor prior to the start of utility work.
At least two (2) working days prior to commencing excavation, the contractor shall call the Blue Stake Center, between the hours of 7:00 a.m. and 4:30 p.m., Monday through Friday for
SP-22
information relative to the location of buried utilities. The number to call is: Tucson and Pima County 1-800-STAKE-IT.
It shall be the responsibility of the contractor to contact the utility companies in order for them to determine if there is a need for any overhead protection, bracing or shoring necessary during the construction of this project. If overhead protection, bracing or shoring is necessary, the contractor shall conduct this work to the satisfaction of the utility. No measurement or direct payment will be made for overhead protection, bracing or shoring, the cost being considered as incidental.
It shall be the responsibility of the contractor to verify and locate all existing overhead and underground utilities whether shown on the plans or not. The contractor is advised that the placement of a utility on the project plans is in no way meant to indicate its exact location.
Utility locations shown on the plans are approximate, and all utilities located within the project limits may not necessarily be shown. The absence of a utility from the plans does not necessarily indicate that it is not present.
The possibility of conflicts with existing utilities-in-service always exists. If conflicting utilities interfere with the normal progress of the contractor towards completion of this project, the Engineer may, with the prior written approval of the owner of the utility to be relocated, authorize the contractor to relocate said conflicting utilities by Force Account (see Section 515 of these Special Provisions).
The contractor shall take full responsibility of costs incurred due to damage to utilities as a result of construction, grading or excavation operations. If any utilities are damaged, the contractor shall repair or replace the damaged utility at his sole expense.
The contractor shall coordinate with affected utilities, so the utilities can notify affected customers of service interruptions. All utility relocations that were deemed necessary and were already known to have been in conflict with the project improvements have been completed. The contractor is also referred to Section 107-21 of these special provisions for more specific details.
All discarded matter (including but not limited to trash, garbage, oil drums, fuel, ashes, equipment, concrete, and chemicals) that is generated by contractor construction activities shall be removed or disposed on a daily basis according to state and federal regulations. Contractor’s construction areas shall be maintained in a sanitary condition at all times.
Storage areas for petroleum products and other chemicals used by the contractor shall be located or protected in such a manner that any spills will not enter stream channels or impact groundwater.
SP-23
19. Storm Water/Ground Water Management
It shall be the responsibility of the contractor to allow for any subsurface groundwater and storm water runoff during the time of project construction. The contractor shall not divert or impound water in such a manner as to flood adjacent homes, facilities, or roadways. No additional compensation shall be provided for dewatering or diversion structures required for constructing or protecting the work, the cost being considered incidental to the project.
Dewatering may be done by the contractor by permit only. No measurement or direct payment will be made for dewatering groundwater or channelizing surface water required during the course of construction, including all permits. A contractor’s licensed well driller is required for conducting any dewatering operation, and all costs for dewatering shall be considered incidental to the contract unit cost of the bid items requiring dewatering. The contractor shall apply to the Arizona Department of Water Resources for the Dewatering Permit in a timely manner. The contractor shall note that up to approximately 90 days may be required for the approval of the Dewatering Permit.
The contractor’s attention is also directed to Section 810 of these Special Provisions and the Stormwater Pollution Prevention Plan for the project regarding the requirements for temporary and permanent erosion control.
20. Shoring and Bracing
All contractor construction shall be conducted in conformance with the details shown on the project plans and these Special Provisions, with appropriate soil stabilization and bracing measures as previously approved by the Engineer. No measurement or direct payment will be made for shoring and/or bracing, unless shown as a line item(s) in the bidding schedule.
Contractor shoring and/or bracing is considered incidental to the cost of the other bid items.
Appropriate soil stabilization and bracing measures as previously approved by the Engineer for the protection of utilities and private facilities shall be implemented by the contractor. No measurement or direct payment will be made for contractor soil stabilization and bracing measures, it will be considered incidental to the cost of the project.
21. Contractor’s Staging or Storage Yard
A contractor’s staging area has been identified and cleared for the project. The location of the staging area is located on a City of Tucson owned parcel (Parcel ID 14102013C) and is approximately 9 acres in size including a Tucson Water well site. The contractor shall provide access to the well site at all times. Contractor staging shall not take place within the well site.
Staging areas and vehicle storage yards are not permitted in the washes within the project area.
The contractor will need to provide a SWPPP addendum to cover their offsite staging area and include the offsite staging area acreage of disturbance on their NOI. Refer to Section 106-9 of
SP-24
the Standard Specifications for offsite staging outside of the right-of-way. Contractor staging areas shall be stabilized at the expense of the contractor and approved by the Engineer.
The contractor’s cost of the construction yard is considered incidental to the project. The contractor shall provide and maintain temporary fencing around the equipment yard and field office for the duration of the contract; the cost being incidental and considered as included in the cost of contract items.
22. Erosion Control Measures
The contractor’s attention is directed to the requirements of Section 810 of the specifications for detailed discussion of erosion control measures.
The contractor shall phase or sequence construction activities to minimize the area of disturbance at any one time. Sediment and erosion control measures shall be installed before upgradient land is disturbed. Once an area of the project has been cleared, the contractor is responsible for documenting in the SWPPP book all erosion control measure activities by the contractor or others in the area that has been cleared.
Once the project reaches final stabilization, the contractor shall remove, dispose or realign temporary erosion control measures as directed by the Engineer. Subsequent removal, disposal or realignment of temporary erosion control measures will be incidental to the respective work item and no additional payment will be made.
23. Regional Transportation Authority (RTA) Construction Signs
The Regional Transportation Authority has contracted with a Sign Contractor to provide and install signs at all RTA funded construction projects location. Signs will indicate to the traveling public the type of project being constructed, the jurisdiction in which the project is located, and that RTA funding is being utilized for the project. The Sign Contractor will work with the City representative to ensure that signs are installed a minimum of 7 days prior to construction start and will remain in place a minimum of 30 days after construction ends. The Sign Contractor will be responsible for Blue Staking for the sign installation and the contractor. Signs will be 4 feet by 8 feet for this larger corridor projects and will be placed at all logical approaches to the project. The contractor will work with the City representative and the Sign Contractor to ensure that locations selected for signs are visible to the traveling public, do not violate sight distance requirements, and do not block other signs, business lines of sight or construction access.
24. Miscellaneous Removal, Relocation, and/or Salvage Work
The contractor shall remove, relocate and/or salvage, as directed by the Engineer, all mailboxes, fences, gates, signs, posts, pipes, etc., within the right-of-way and construction easement areas.
The cost of this work shall be considered as incidental to ITEM 2020001 - REMOVAL OF
SP-25
STRUCTURES & OBSTRUCTIONS, except when the bidding schedule contains specific items on a unit basis.
All materials identified on the plans to be salvaged as part of this project shall be delivered to a location as directed by the Engineer.
Signs and posts shall be removed and salvaged by the contractor in accordance with the signing plans and these Special Provisions. Signs and posts shall be delivered by the contractor to the Sign Shop, 4004 S. Park Avenue, Building 6 (west end). The contractor shall coordinate the delivery of signs and posts with April Ormsby, 520-373-3641.
The contractor shall be responsible for loading and unloading all salvaged materials at the location specified. No measurement of direct payment will be made for this work, the cost being considered as included in the price of contract items.
25. Fencing and Gates
Portions of the project limits along Valencia Road are adjacent to utility owned and undeveloped private parcels. Unless otherwise approved by the Engineer, the contractor shall construct new fencing adjacent to new right-of-way prior to removing existing fence. If pertinent, applicable and/or necessary, the contractor shall maintain a reasonable barrier to accessing the Valencia Road right-of-way. The contractor shall be responsible for placing “temporary fence” and gates where construction operations require that the existing fence and gates are to be removed, reconstructed, and/or relocated. The contractor shall coordinate with the Engineer when removing existing fence and placing temporary fence along the necessary linear footage. No measurement or direct payment will be made for this work, the cost being considered as incidental to the project.
26. Survey Monuments
Prior to removing any existing survey monuments, the contractor shall obtain approval from the Engineer. The decision whether to preserve or replace a monument will be based on the condition of the monument and whether it is in direct conflict with construction. If a monument is removed or damaged by the contractor without authorization from the Engineer, the contractor shall be responsible for the cost to replace the monument. There will be no measurement or direct payment made for this coordination effort, the cost being incidental to the project cost.
27. Work Hours/Noise Abatement Ordinance
Construction noise abatement and start/stop times shall be in accordance with the Arizona Department of Transportation Standard Specifications for Road and Bridge Construction, Section 104.08 (2008 Edition), and the City of Tucson Code 16-31(b)(5) which
SP-26
prohibits construction noise between the hours of 8:00 p.m. through sunrise, Mondays through Saturdays, and at any time on Sundays and legal holidays.
28. Construction Water/Dust Control
The contractor shall provide potable water for use in construction, compaction and dust control.
Reclaimed water may only be used if there is no discharge of this water to surface waters of the U.S. and the reclaimed water remains on-site. The contractor shall notify the Arizona Department of Environmental Quality (ADEQ) for all discharges of reclaimed water to surface waters of the U.S. or off-site.
Fugitive dust generated from construction activities will be controlled in accordance with the Pima County Department of Environmental Quality (PCDEQ) requirements.
For milling activities, the roadway surface preceding the milling machine shall be kept sufficiently wet so as to prevent the generation of any visible fugitive dust particles, but not so wet as to cause excess runoff from the roadway surface onto the roadway shoulder.
29. Verification of Pipe Lengths
The contractor shall verify all pipe lengths shown on the project plans and submit the information to the Engineer for approval before ordering the pipe.
30. Nearby or Adjacent Construction
The contractor shall be aware of any other significant construction activities in the area, near or adjacent to this project’s 4.27-mile long construction work zone.