I-Sheets.pdf

PDF 2 MB Posted

Attached to
Y1PC--Dallas National Cemetery
Solicitation number
36C10F20R0056
Issued by

About this file

This is a pre-solicitation notice for a design-bid-build construction project. The Department of Veterans Affairs seeks to expand the Dallas Fort Worth National Cemetery in Dallas, Texas through construction of additional gravesites, cemetery improvements including a new administration building and maintenance building renovation, and development of approximately 56 acres of land. The project scope includes construction of over 12,000 pre-placed crypt full casket gravesites, over 600 traditional gravesites, nearly 3,000 in-ground cremains sites, and a 300-grave hybrid natural burial section. Additional requirements comprise earthwork, drainage, fencing, roads, parking, utilities, signage, site furnishings, and a new irrigation system. The solicitation will be set aside for a 100% service-disabled veteran-owned small business as a general contractor. The pre-proposal conference will be detailed in the solicitation to post on June 19, 2020. Proposals are due approximately 30 days later. The magnitude of construction cost is estimated between $20-50 million. The contractor must provide performance and payment bonds and a bid guarantee. Award will be determined using best value tradeoff evaluation.

View the file

Other files

File Type Posted
ATTACHMENT 2_PAST PERF QUEST 02.docx DOCX document
P-Sheets.pdf PDF
LI-Sheets.pdf PDF
CS-Sheets 3 of 3.pdf PDF
G-Sheets.pdf PDF
CD-Sheets.pdf PDF
A-Sheets.pdf PDF
E-Sheets.pdf PDF
CG-Sheets 1 of 2.pdf PDF
S-Sheets.pdf PDF
ATTACHMENT 3 - Dallas Pre-Proposal Inquiry (PPI) Form.docx DOCX document
B-Sheets.pdf PDF
DALLAS WAGE RATES.pdf PDF
36C10F20R0056_3.docx DOCX document
F-Sheets.pdf PDF
Base Bid Specification Package.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. THE CONTRACTOR SHALL BECOME FAMILIAR WITH THE CONSTRUCTION DOCUMENTS AND NOTIFY THE INTERIOR DESIGNER OF ANY

DISCREPANCIES BEFORE PROCEEDING WITH THE WORK.

2. THE CONTRACTOR SHALL FIELD VERIFY EXISTING CONDITIONS AND NOTIFY THE INTERIOR DESIGNER OF ANY DISCREPANCIES BEFORE

PROCEEDING WITH THE WORK.

3. THE CONTRACTOR SHALL FIELD VERIFY EXISTING CONDITIONS AND DIMENSIONS PRIOR TO ORDERING OR INSTALLING MATERIALS OR

EQUIPMENT.

4. THE CONTRACTOR SHALL PROTECT NEW AND EXISTING WORK FROM DAMAGE DURING CONSTRUCTION ACTIVITIES. DAMAGED AREAS CAUSED DURING CONSTRUCTION SHALL BE REPAIRED OR REPLACED AT THE CONTRACTOR'S EXPENSE. REPAIRS SHALL MATCH

EXISTING CONDITIONS AND FINISHES.

5. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REMOVAL AND DISPOSAL OF DEMOLITION AND/OR CONSTRUCTION DEBRIS ASSOCIATED WITH THE WORK. DISPOSAL SHALL BE IN COMPLIANCE WITH FEDERAL, STATE, AND LOCAL REGULATIONS. THE PROJECT

SITE SHALL BE KEPT CLEAN AND FREE FROM WASTE MATERIALS.

6. THE OWNER SHALL RESERVE THE RIGHT TO SALVAGE ANY REMOVED MATERIALS.

7. EXISTING MATERIALS SHALL NOT BE RE-USED UNLESS OTHERWISE NOTED OR AS AUTHORIZED BY THE INTERIOR DESIGNER.

8. THE CONTRACTOR SHALL MAINTAIN EXISTING BUILDING EGRESS DURING DEMOLITION AND/OR CONSTRUCTION ACTIVITIES.

9. ALL PENETRATIONS THROUGH FIRE-RESISTIVE CONSTRUCTION SHALL BE SEALED WITH FIRE STOPPING/SAFING MATERIAL AND FIRE-RESISTIVE SEALANT AS REQUIRED TO ACHIEVE THE RESPECTIVE FIRE/SMOKE RESISTANCE RATING.

10. ALL JOINTS AND TERMINATIONS AT FIRE-RESISTIVE CONSTRUCTION SHALL BE SEALED WITH FIRE-RESISTIVE JOINT SYSTEMS REQUIRED TO ACHIEVE THE RESPECTIVE FIRE/SMOKE RESISTIVE RATINGS. SCRIBE GYPSUM BOARD AT THE TOP-OF-WALL TO MATCH

IRREGULARITIES OF DECK ABOVE.

11. FIRE-RESISTIVE WALL CONSTRUCTION SHALL BE PERMANENTLY IDENTIFIED AS SUCH BY STENCILING THE RATING LEVEL IN THE CONCEALED SPACE BELOW THE FLOOR AND/OR ABOVE THE CEILING. LETTERING SHALL BE A MINIMUM OF THREE INCHES IN HEIGHT AND SHALL BE LOCATED NOT LESS THAN 15 FEET FROM THE END OF EACH WALL AND AT INTERVALS NOT EXCEEDING 30 FEET.

12. INSTALL CONTROL JOINTS IN GYPSUM BOARD SURFACES AS SHOWN ON DRAWINGS AND AS DESCRIBED IN THE SPECIFICATIONS.

ISOLATE GYPSUM BOARD SURFACES WITH CONTROL JOINTS FOR RUNS THAT EXCEED 30 FEET IN LENGTH.

13. COORDINATE LOCATION, SIZE, AND WALL THICKNESS REQUIRED FOR RECESSED ITEMS. MAINTAIN FIRE-RESISTIVE AND ACOUSTICAL

RATINGS OF THE WALL BEING PENETRATED.

14. ALL NEW CEILING GRID SHALL BE CENTERED WITHIN THE ROOM AS INDICATED. AVOID ACOUSTIC CEILING TILES LESS THAN 3 INCHES

IN WIDTH AT LOCATIONS ADJACENT TO ROOM WALLS.

15. ALL PENETRATIONS WITHIN 24" x 48" ACOUSTIC CEILING TILES, INCLUDING SPRINKLER HEADS, SHALL BE CENTERED IN THE SHORT DIMENSION AND BE CENTERED AT QUARTER POINTS IN THE LONG DIMENSION OF THE TILE. PENETRATIONS WITHIN 24" x 24" ACOUSTIC

CEILING TILES SHALL BE CENTERED WITHIN THE TILE.

16. COORDINATE LOCATION, SIZE, AND DEPTH OF RECESSED AREAS IN CONCRETE FLOOR SLABS. MAINTAIN STRUCTURAL INTEGRITY AND

FIRE-RESISTANCE RATINGS OF THE FLOOR.

17. PREPARE EXISTING SUB-FLOOR TO MEET MANUFACTURER'S REQUIREMENTS FOR INSTALLATION OF NEW FLOORING MATERIAL. FLOAT SUB-FLOOR AS NECESSARY TO ALIGN FINISHED SURFACE BETWEEN NEW AND EXISTING FLOORING.

18. EXAMINE FLOOR SUBSTRATE AND CONDITIONS, WITH THE INSTALLER PRESENT, FOR COMPLIANCE WITH FLOORING MANUFACTURER'S RECOMMENDATIONS FOR MAXIMUM MOISTURE CONTENT, ALKALINITY RANGE, INSTALLATION TOLERANCES, AND OTHER CONDITIONS

PRIOR TO PROCEEDING WITH FLOORING INSTALLATION.

19. ALL FLOOR TRANSITIONS BETWEEN DIFFERENT FLOORING MATERIALS SHALL BE SMOOTH AND FLUSH WITH NO MORE THAN 1/4-INCH

VARIATION IN HEIGHT.

20. WHERE TWO DISSIMILAR HEIGHT FLOOR FINISHES ABUT, PROVIDE AND INSTALL TRANSITION STRIP.

21. WHERE TWO DISSIMILAR HEIGHT FLOOR FINISHES ABUT WITHIN A DOORWAY, POSITION TRANSITION STRIP AT CENTER OF DOOR WHEN

FULLY CLOSED.

22. WHERE FLOOR FINISH CHANGES FROM ONE ROOM TO ANOTHER, SET JOINT OF THE MATERIALS AT THE CENTER OF THE

COMMUNICATING DOOR OR OPENING.

23. WHERE SHEET RESILIENT FLOORING IS INDICATED, HEAT-WELD AND SEAL ALL SEAMS WITH WELD RODS IN COLORS MATCHING EACH SHEET RESILIENT FLOORING MATERIAL INDICATED. PROVIDE INTEGRAL COVE BASE WITH STAINLESS STEEL CAP AND

MECHANICALLY-FASTENED CORNERS.

24. FURNISH AND INSTALL RESILIENT WALL BASE IN CONTINUOUS COIL RUNS AT MAXIMUM LENGTHS POSSIBLE. JOB-FORM BOTH INSIDE

AND OUTSIDE CORNERS.

25. FURNISH AND INSTALL RESILIENT WALL BASE IN ALL OFFSETS, TOEKICKS, ALCOVES, AND OTHER RECESSES, TO INCLUDE AREAS NOT

TYPICALLY VISIBLE BEHIND EQUIPMENT, WITHIN THE AREA OF WORK INDICATED.

26. FURNISH AND INSTALL RESILIENT WALL BASE ON ALL CASEWORK / MILLWORK UNLESS OTHERWISE INDICATED.

27. WHERE WALL TILE IS INDICATED, PROVIDE NECESSARY TRIM PIECES, SUCH AS EDGE AND CORNER TILES, FOR A COMPLETE FINISHED

INSTALLATION.

28. PAINTING STANDARDS SHALL BE BASED UPON THE MPI ARCHITECTURAL PAINTING SPECIFICATION MANUAL FOR NEW WORK AND THE

MPI MAINTENANCE REPAINTING MANUAL FOR RENOVATION OR REPAINTING WORK.

29. ON PAINTED WALL SURFACES, PROVIDE A MINIMUM OF THREE COATS WITH THE FIRST COAT BEING PRIMER APPROPRIATE FOR SUBSTRATE MATERIAL. PAINT WALL SURFACES NOT TYPICALLY VISIBLE BEHIND EQUIPMENT, WITHIN THE AREA OF WORK INDICATED.

30. DO NOT PAINT OVER CODE-REQUIRED LABELS SUCH AS THOSE LOCATED ON RATED DOORS AND FRAMES.

31. THE CONTRACTOR IS RESPONSIBLE FOR FIELD VERIFICATION OF ALL DIMENSIONS AND FIELD CONDITIONS PRIOR TO FABRICATING

CASEWORK / MILLWORK.

32. WHERE ELECTRICAL DEVICES ARE LOCATED WITHIN CASEWORK, CASEWORK FABRICATOR SHALL PROVIDE FINISHED OPENINGS.

COORDINATE SIZES AND LOCATIONS WITH ELECTRICAL CONTRACTOR.

33. PROVIDE AND INSTALL PLASTIC LAMINATE ON ALL EXPOSED SURFACES WHEREVER PLASTIC LAMINATE IS INDICATED.

34. PROVIDE AND INSTALL JOINT SEALANT AT PERIMETER JOINTS OF CASEWORK WHERE COUNTERTOPS, BACK & SIDE SPLASHES, AND

EDGE JOINTS ABUT ADJACENT WALLS.

35. ALL FURNISHINGS, SUCH AS WINDOW TREATMENT, ARTWORK, AND SYSTEMS FURNITURE, SHALL BE NON-COMBUSTIBLE AND

ASSEMBLED OF FIRE-RESISTIVE MATERIALS.

INTERIOR GENERAL NOTES

STANDARD INTERIOR ABBREVIATIONS

STANDARD INTERIOR SYMBOLS

ROOM IDENTIFIER

FURNITURE IDENTIFIER

EQUIPMENT IDENTIFIER

ARTWORK IDENTIFIER

SIGN IDENTIFIER

WALL FINISH IDENTIFIER

FLOOR FINISH TRANSITION

IDENTIFIER

CARPET -

FIELD

XX-# XX-#

XX-#

KEY MATERIAL MANUFACTURER MODEL / SERIES COLOR SIZE COMMENTS

ACT-1 ACOUSTICAL CEILING

TILE

ARMSTRONG WORLD

INDUSTRIES, INC. ULTIMA TEGULAR WHITE 24" x 24"

CPT-1 CARPET TILE SHAW CONTRACT

GROUP POURED LAPIS 24" x 24"

FRP-1 FIBER REINFORCED

PANEL MARLITE STANDARD FRP P-100 WHITE -- PEBBLED SURFACE

GT-1 GROUT MAPEI SANDED 77 FROST -- WALL TILE

GT-2 GROUT MAPEI SANDED 104 TIMBERWOLF -- FLOOR TILE

LVT-1 LUXURY VINYL TILE SHAW CONTRACT

GROUP 0516V STRAND 16530 PEBBLE 18" x 36" HERRINGBONE

PATTERN

LVT-2 LUXURY VINYL TILE SHAW CONTRACT

GROUP 0648V SOLITUDE 48760

WOODLAND 6" x 48" STAGGERED PATTERN

LVT-3 LUXURY VINYL TILE SHAW CONTRACT

GROUP 0515V SURFACE 15500 PITCH 18" x 36"

PLAM-1 PLASTIC LAMINATE WILSONART, LLC HIGH PRESSURE

LAMINATE

D327

PEPPERDUST --

PORC-1 PORCELAIN FLOOR

TILE CROSSVILLE, INC. PORCELAIN STONE /

BASALT BEDROCK 12" x 12"

PORC-2 PORCELAIN WALL TILE CROSSVILLE, INC. RETRO ACTIVE SNOW BLIND 4" x 12" RUNNING BOND

PATTERN

PORC-3 PORCELAIN WALL TILE CROSSVILLE, INC. RETRO ACTIVE ROYAL NAVY 4" x 12" ACCENT BAND

PORC-4 PORCELAIN WALL TILE IRIS U.S. CARRARA SELECT ROMANO GREIGE

POLISHED

12" x 24", 4" x 12"

PT-1 INTERIOR PAINT SHERWIN WILLIAMS

COMPANY

INTERIOR LATEX,

SEMI-GLOSS

SW 7551 GREEK

VILLA -- INTERIOR WALLS

PT-2 INTERIOR PAINT SHERWIN WILLIAMS

COMPANY

INTERIOR LATEX,

SEMI-GLOSS

SW 7029

AGREEABLE

GREY

-- INTERIOR WALLS

PT-3 INTERIOR PAINT SHERWIN WILLIAMS

COMPANY

INTERIOR LATEX,

SEMI-GLOSS

SW 6227

MEDITATIVE -- INTERIOR WALLS

PT-4 INTERIOR PAINT SHERWIN WILLIAMS

COMPANY

INTERIOR LATEX,

SEMI-GLOSS

SW 7757 HIGH

REFLECTIVE

WHITE

-- CEILINGS

EP-05 EPOXY PAINT SHERWIN WILLIAMS

COMPANY -- LOCKER ROOM WALLS

PTB-1 PORCELAIN TILE BASE CROSSVILLE, INC. PORCELAIN STONE /

BASALT BEDROCK 6" x 12"

QTZ-1 QUARTZ COUNTERTOP DUPONT ZODIAQ SNOW FLURRY --

RB-1 RESILIENT BASE JOHNSONITE TRADITIONAL 18 NAVY BLUE 4" ROLL CARPET FLOORS

RB-2 RESILIENT BASE JOHNSONITE TRADITIONAL 20 CHARCOAL 4" ROLL RESILIENT TILE

FLOORS

RES-1 RESINOUS FLOORING SHERWIN WILLIAMS

COMPANY CERAMIC CARPET 337 OCEAN --

RS-1 ROLLER SHADE MECHOSHADE 1550 SERIES 1551 WHITE -- 3% OPEN

SLR-1 CONCRETE SEALER -- -- CLEAR --

SS-1 SOLID SURFACE DUPONT CORIAN ANTARCTICA --

VCT-1 VINYL COMPOSITION

TILE

ARMSTRONG WORLD

INDUSTRIES, INC. EXCELON SDT 51958 OCEAN AIR 12" x 12" STATIC DISSIPATIVE

WOM-1 WALK-OFF MAT FLEXCO

CORPORATION FLEXTUFT DELFT & GRAY 12" x 12"

INTERIOR FINISH MATERIAL SCHEDULE

NOTES:

1. FINISH MATERIALS SHALL BE END PRODUCTS THAT HAVE BEEN MINED, PRODUCED, AND / OR MANUFACTURED WITHIN THE UNITED STATES IN COMPLIANCE WITH THE BUY AMERICAN ACT, 41 USC 10a - 10d.

STONE

VCT

CORK

WALK OFF

MAT

CARPET -

ACCENT

CERAMIC TILE -

SQUARE

CERAMIC TILE -

RECTANGULAR

PLYWOOD

WOOD -

FINISH

QUARTZ

RESINOUS

FLOORING

PLASTIC

WOOD -

ROUGH

LUXURY

VINYL TILE

SOLID

SURFACE

RUBBER

FLOORING

SHEET VINYL

FLOORING

ALUMINUM

GYPSUM

ROOM NAME

ACT ACOUSTICAL CEILING TILE

ADO AUTOMATIC DOOR OPERATOR

AFF ABOVE FINISH FLOOR

ALT ALTERNATE

ALUM ALUMINUM

BB BULLETIN BOARD

BD BOARD

BLDG BUILDING

BLK BLOCK

CG CORNER GUARD

CJ CONTROL JOINT

CL CENTER LINE

CLG CEILING

CMU CONCRETE MASONRY UNIT

CONC CONCRETE

CONT CONTINUOUS

CORR CORRIDOR

CPT CARPET

CR CRASH RAIL

CRK CORK

CT CERAMIC TILE

CTB CERAMIC TILE BASE

DEPT DEPARTMENT

DETL DETAIL

DF DRINKING FOUNTAIN

DIA DIAMETER

DIM DIMENSION

DISP DISPENSER

DN DOWN

DR DOOR

DS DOWNSPOUT

EA EACH

EJ EXPANSION JOINT

ELEV ELEVATION

EP EPOXY PAINT

EQPM EQUIPMENT

EXT EXTERIOR

FAB FABRIC

FB FACE BRICK

FD FLOOR DRAIN

FE FIRE EXTINGUISHER

FEC FIRE EXTINGUISHER CABINET

FFE FINISH FLOOR ELEVATION

FIN FINISH

FND FOUNDATION

FLG FLOORING

FT FOOT/FEET

GALV GALVANIZED

GB GRAB BAR

GL GLASS

GLT GLASS TILE

GT GROUT

GWB GYPSUM WALL BOARD

HC HANDICAP

HD HAND DRYER

HDW HARDWARE

HM HOLLOW METAL

HMF HOLLOW METAL FRAME

HR HAND RAIL

HT HEIGHT

IN INCH

INSUL INSULATION

INT INTERIOR

JAN JANITOR

JT JOINT

KP KICK PLATE

LAM LAMINATED

LAV LAVATORY

LDR LADDER

LIN LINOLEUM

LKR LOCKER

LVR LOUVER

LVT LUXURY VINYL TILE

MB MARKER BOARD

MBH MOP AND BROOM HOLDER

MTL METAL

MFR MANUFACTURER

MO MASONRY OPENING

MR MIRROR

MTRL MATERIAL

NIC NOT IN CONTRACT

NTS NOT TO SCALE

OC ON CENTER

OFD OVERFLOW DRAIN

OFS OVERFLOW SCUPPER

OPP OPPOSITE

ORD OVERFLOW ROOF DRAIN

PLAM PLASTIC LAMINATE

PLYWD PLYWOOD

PORC PORCELAIN

PP POWER POLE

PS PROJECTION SCREEN

PT PAINT

PTD PAPER TOWEL DISPENSER

PTDR PAPER TOWEL DISPENSER &

RECEPTACLE

QTY QUANTITY

QTZ QUARTZ

RB RESILIENT BASE

RD ROOF DRAIN

REC RECESSED

REF REFRIGERATOR

REQD REQUIRED

RES RESINOUS FLOORING

RH ROBE HOOK

RM ROOM

RO ROUGH OPENING

RS ROLLER SHADE

RT RUBBER TILE

RV ROOF VENT

SB SHOWER BENCH

SD SOAP DISPENSER

SEC SECURITY

SECT SECTION

SF SQUARE FOOT/FEET

SH SHOWER HEAD

SHT SHEET

SIM SIMILAR

SLR SEALER

SND SANITARY NAPKIN DISPOSAL

SS SOLID SURFACE

STD STANDARD

STL STEEL

STN STAIN

STOR STORAGE

SV SHEET VINYL

TB TACK BOARD

TEMP TEMPORARY

TTD TOILET TISSUE DISPENSER

TYP TYPICAL

UR URINAL

US UTILITY SHELF

VCT VINYL COMPOSITE TILE

VIF VERIFY IN FIELD

VWC VINYL WALL COVERING

WC WATER CLOSET

WD WOOD

WOM WALK-OFF MAT

WMP WIRE MESH PARTITION

WWF WELDED WIRE FABRIC

FABRIC

STANDARD MOUNTING HEIGHTS

INSULATION-

BATT

FIRESTOPPING

STEEL

SIGN

DOOR SIGN

8" MAX.

INTERIOR GENERAL

NOTES & SYMBOLS I-001

APPROVED DRAWING TITLE

DATE

LOCATION

CHECKED PROJECT NUMBER

DRAWING NUMBER

DESCRIPTION DATE

DESIGN CONSULTANTS: ARCHITECT / ENGINEER OF RECORD:

C

Office of Construction and Facilities Management

1 3 4 5 6

B

A

D

E

C

B

A

D

E

BUILDING NUMBER

DRAWN

SEAL:

MARK

03-31-2020

DALLAS, TEXAS

916CM2012

DALLAS - FORT WORTH

NATIONAL CEMETERY

Calibre 9090 South Ridgeline Boulevard, Suite 105 Highlands Ranch, CO 80129 (303) 730-0434 www.calibre-engineering.com Construction Management Civil Engineering Surveying

Calibre Engineering, Inc.

Cemetery Expertise:

MKEC Engineering Ken Kallenbach

(316) 684-9600

Architect:

TK-Architecture, LLC Thomas J. Kapels

(719) 325-9303

Irrigation:

Aqua Engineering Bob Beccard

(970) 372-6104

Water Resources:

Leonard Rice Engineers Dave Colvin

(303) 867-7662

MEP:

Miller Remick MEP Tom Chapman

(856) 429-4000

Cost Estimating:

MOCA Cost Engineering Todd Waddle

(850) 389-8131

Surveying:

Fabre Engineering & Surveying Frank Fabre

(850) 433-6438

Geotechnical Engineering:

Terracon Consultants Jennifer Peters

(210) 907-7648

PHASE FOUR DEVELOPMENT

OF 246189

1001, 1301, & 3004

TJK

3-31-2020

VITREOUS CHINALAVATORYPINOIRK-2035-8

I-201

I-201

IN-21

I-201

IN-23A

I-201

I-201

I-201

I-201

IN-23B

IN

-2

IN

-1

IN-12IN-09

IN-16

IN-15

IN-06

IN-11

IN-13

IN-08

IN-05

IN-10

IN

-2

3F

IN-03

IN-04

MAINTENANCE FACILITY

FINISH & SIGNAGE PLAN

1. CORNER GUARD (CG-1); RE: DETL 2 / I-601

2. FIBER REINFORCED PANEL (FRP-1) UP TO HEIGHT OF 4'-0" AFF

KEY NOTES

I-101

SCALE: 1/8" = 1'-0"

FINISH & SIGNAGE PLAN - MAINTENANCE FACILITY1

PLAN

NORTH

0 4 8 16

APPROVED DRAWING TITLE

DATE

LOCATION

CHECKED PROJECT NUMBER

DRAWING NUMBER

DESCRIPTION DATE

DESIGN CONSULTANTS: ARCHITECT / ENGINEER OF RECORD:

C

Office of Construction and Facilities Management

1 3 4 5 6

B

A

D

E

C

B

A

D

E

BUILDING NUMBER

DRAWN

SEAL:

MARK

03-31-2020

DALLAS, TEXAS

916CM2012

DALLAS - FORT WORTH

NATIONAL CEMETERY

Calibre 9090 South Ridgeline Boulevard, Suite 105 Highlands Ranch, CO 80129 (303) 730-0434 www.calibre-engineering.com Construction Management Civil Engineering Surveying

Calibre Engineering, Inc.

Cemetery Expertise:

MKEC Engineering Ken Kallenbach

(316) 684-9600

Architect:

TK-Architecture, LLC Thomas J. Kapels

(719) 325-9303

Irrigation:

Aqua Engineering Bob Beccard

(970) 372-6104

Water Resources:

Leonard Rice Engineers Dave Colvin

(303) 867-7662

MEP:

Miller Remick MEP Tom Chapman

(856) 429-4000

Cost Estimating:

MOCA Cost Engineering Todd Waddle

(850) 389-8131

Surveying:

Fabre Engineering & Surveying Frank Fabre

(850) 433-6438

Geotechnical Engineering:

Terracon Consultants Jennifer Peters

(210) 907-7648

PHASE FOUR DEVELOPMENT

OF 246

TJKTJK

I-202

I-202

I-202

I-202

I-202

I-202

I-202

I-202

I-202

IN-03

IN-02

IN-22

IN

-2

IN

-1

IN

-1

IN-09

IN-08

IN-11

IN-12

IN-14 IN-15

IN-17

IN-16

IN-13

10'-0" 6'-0"6'-0"

IN-06

IN

-2

6'- 0"

5'- 7"

FOR R

EFERENCE O

NLY

NOT IN

C

ONTRACT

ADMINISTRATION FACILITY

FINISH & FURNITURE PLAN

KEY NOTES

I-102

SCALE: 1/8" = 1'-0"

FINISH & SIGNAGE PLAN - ADMINISTRATION FACILITY1

PLAN

NORTH

APPROVED DRAWING TITLE

DATE

LOCATION

CHECKED PROJECT NUMBER

DRAWING NUMBER

DESCRIPTION DATE

DESIGN CONSULTANTS: ARCHITECT / ENGINEER OF RECORD:

C

Office of Construction and Facilities Management

1 3 4 5 6

B

A

D

E

C

B

A

D

E

BUILDING NUMBER

DRAWN

SEAL:

MARK

03-31-2020

DALLAS, TEXAS

916CM2012

DALLAS - FORT WORTH

NATIONAL CEMETERY

Calibre 9090 South Ridgeline Boulevard, Suite 105 Highlands Ranch, CO 80129 (303) 730-0434 www.calibre-engineering.com Construction Management Civil Engineering Surveying

Calibre Engineering, Inc.

Cemetery Expertise:

MKEC Engineering Ken Kallenbach

(316) 684-9600

Architect:

TK-Architecture, LLC Thomas J. Kapels

(719) 325-9303

Irrigation:

Aqua Engineering Bob Beccard

(970) 372-6104

Water Resources:

Leonard Rice Engineers Dave Colvin

(303) 867-7662

MEP:

Miller Remick MEP Tom Chapman

(856) 429-4000

Cost Estimating:

MOCA Cost Engineering Todd Waddle

(850) 389-8131

Surveying:

Fabre Engineering & Surveying Frank Fabre

(850) 433-6438

Geotechnical Engineering:

Terracon Consultants Jennifer Peters

(210) 907-7648

PHASE FOUR DEVELOPMENT

OF 246

0 4 8 16

TJK

1. CORNER GUARD (CG-2); RE: DETL 4 / I-601

2. FIBER REINFORCED PANEL (FRP-1) UP TO HEIGHT OF 4'-0" AFF

3. TELEVISION (OWNER FURNISHED / OWNER INSTALLED)

4. REFRIGERATOR (CONTRACTOR FURNISHED / CONTRACTOR

INSTALLED)

5. MICROWAVE (CONTRACTOR FURNISHED / CONTRACTOR

INSTALLED)

6. GRAVESITE LOCATOR KIOSK (OWNER FURNISHED / OWNER

INSTALLED)

SCALE: 1/8" = 1'-0"

FURNITURE PLAN - ADMINISTRATION FACILITY2

PLAN

NORTH

0 4 8 16

VITREOUS CHINALAVATORYPINOIRK-2035-8

FOR R

EFERENCE O

NLY

NOT IN

C

ONTRACT

FOR R

EFERENCE O

NLY

NOT IN

C

ONTRACT

MAINTENANCE FACILITY

FURNITURE PLAN

1. TELEVISION (OWNER FURNISHED / OWNER INSTALLED)

2. REFRIGERATOR (CONTRACTOR FURNISHED / CONTRACTOR

INSTALLED)

3. MICROWAVE (CONTRACTOR FURNISHED / CONTRACTOR

INSTALLED)

4. ICE MAKER (OWNER FURNISHED / OWNER INSTALLED)

5. VENDING MACHINE (BY OTHERS)

KEY NOTES

I-111

SCALE: 1/8" = 1'-0"

FURNITURE PLAN - MAINTENANCE FACILITY1

PLAN

NORTH

0 4 8 16

APPROVED DRAWING TITLE

DATE

LOCATION

CHECKED PROJECT NUMBER

DRAWING NUMBER

DESCRIPTION DATE

DESIGN CONSULTANTS: ARCHITECT / ENGINEER OF RECORD:

C

Office of Construction and Facilities Management

1 3 4 5 6

B

A

D

E

C

B

A

D

E

BUILDING NUMBER

DRAWN

SEAL:

MARK

03-31-2020

DALLAS, TEXAS

916CM2012

DALLAS - FORT WORTH

NATIONAL CEMETERY

Calibre 9090 South Ridgeline Boulevard, Suite 105 Highlands Ranch, CO 80129 (303) 730-0434 www.calibre-engineering.com Construction Management Civil Engineering Surveying

Calibre Engineering, Inc.

Cemetery Expertise:

MKEC Engineering Ken Kallenbach

(316) 684-9600

Architect:

TK-Architecture, LLC Thomas J. Kapels

(719) 325-9303

Irrigation:

Aqua Engineering Bob Beccard

(970) 372-6104

Water Resources:

Leonard Rice Engineers Dave Colvin

(303) 867-7662

MEP:

Miller Remick MEP Tom Chapman

(856) 429-4000

Cost Estimating:

MOCA Cost Engineering Todd Waddle

(850) 389-8131

Surveying:

Fabre Engineering & Surveying Frank Fabre

(850) 433-6438

Geotechnical Engineering:

Terracon Consultants Jennifer Peters

(210) 907-7648

PHASE FOUR DEVELOPMENT

OF 246

TJKTJK

NORTH EAST SOUTH WESTNORTH WESTSOUTHEAST

VITREOUS CHINALAVATORYCAXTONK-2210 VITREOUS CHINALAVATORYCAXTONK-2210

REFRIG

REFRIG REFRIGREFRIG

3'-0"2'-6" 15"3'-3"

2'-

2'-

2" 2'-

0" 7'-

0"

2'-6" 3'-0" 15"

3'-0"

NORTH

3'-0"3'-0"1" 3'-0" 1'-6" 3'-3" 16'-10"

2'-

1'-

8" 2'-

6" 7'-

0"

3'-0"1" 3'-0" 3'-0" 3'-0" 1'-6" 3'-0"2'-6"2'-6" 2'-6" 2'-6"

3'-0"2'-6"2'-6"3'-3" 2'-6" 2'-6" 3'-3" 19'-6"

NORTH

2'-0" 2'-0" 2'-0" 2'-0" 2'-0" EQ.EQ.

2'-

2'-0" 2'-0" 2'-0" 2'-0"2'-0"5" 5"2'-0" 12'-10"

EAST

2'-

2'-0" 2'-0"2'-0"3" 3"2'-0" 8'-6"

SOUTH

2'-0" EQ.2'-0"2'-0"EQ.

2'-

5'- 6"

5'- 6"

5'- 6"

5'- 6"

5'- 6"

5'- 6"

5'- 6"

5'- 6"

444 4 4 4 4 4

10 10

10 10 10 10 10 10 10 10 10 10

5 5 667 7

WEST

1. PORCELAIN WALL TILE (PORC-2)

2. PORCELAIN WALL TILE (PORC-3)

3. PORCELAIN TILE BASE (PTB-1)

4. PAINT (AS SCHEDULED)

5. TOILET TISSUE DISPENSER

6. COMBINATION TOWEL DISPENSER / WASTE RECEPTACLE

7. 36" GRAB BAR (GB-1)

8. 42" GRAB BAR (GB-2)

9. 18" GRAB BAR (GB-3)

10. FRAMED MIRROR UNIT

11. PLASTIC LAMINATE (PLAM-1)

12. COUNTERTOP (SS-1)

13. COUNTERTOP (QTZ-1)

KEY NOTES

MAINTENANCE FACILITY

INTERIOR ELEVATIONS I-211

SCALE: 1/4" = 1'-0"

TOILET 111 INTERIOR ELEVATIONS1

TJK

SCALE: 1/4" = 1'-0"

TOILET 115 INTERIOR ELEVATIONS2

SCALE: 1/4" = 1'-0"

BREAK ROOM ELEVATIONS6SCALE: 1/4" = 1'-0"

HONOR GUARD ELEVATIONS3 SCALE: 1/4" = 1'-0"

MALE LOCKER ROOM ELEVATIONS4 SCALE: 1/4" = 1'-0"

FEMALE LOCKER ROOM ELEVATIONS5

APPROVED DRAWING TITLE

DATE

LOCATION

CHECKED PROJECT NUMBER

DRAWING NUMBER

DESCRIPTION DATE

DESIGN CONSULTANTS: ARCHITECT / ENGINEER OF RECORD:

C

Office of Construction and Facilities Management

1 3 4 5 6

B

A

D

E

C

B

A

D

E

BUILDING NUMBER

DRAWN

SEAL:

MARK

03-31-2020

DALLAS, TEXAS

916CM2012

DALLAS - FORT WORTH

NATIONAL CEMETERY

Calibre 9090 South Ridgeline Boulevard, Suite 105 Highlands Ranch, CO 80129 (303) 730-0434 www.calibre-engineering.com Construction Management Civil Engineering Surveying

Calibre Engineering, Inc.

Cemetery Expertise:

MKEC Engineering Ken Kallenbach

(316) 684-9600

Architect:

TK-Architecture, LLC Thomas J. Kapels

(719) 325-9303

Irrigation:

Aqua Engineering Bob Beccard

(970) 372-6104

Water Resources:

Leonard Rice Engineers Dave Colvin

(303) 867-7662

MEP:

Miller Remick MEP Tom Chapman

(856) 429-4000

Cost Estimating:

MOCA Cost Engineering Todd Waddle

(850) 389-8131

Surveying:

Fabre Engineering & Surveying Frank Fabre

(850) 433-6438

Geotechnical Engineering:

Terracon Consultants Jennifer Peters

(210) 907-7648

PHASE FOUR DEVELOPMENT

OF 246

SCALE: 1/4" = 1'-0"

BREAK ROOM ELEVATIONS8

NORTH EAST SOUTH WEST

NORTH EAST SOUTH WESTNORTH SOUTH WEST

VITREOUS CHINALAVATORYCAXTONK-2210

NORTH WESTSOUTHEAST

EAST

VITREOUS CHINALAVATORYCAXTONK-2210 VITREOUS CHINALAVATORYCAXTONK-2210VITREOUS CHINALAVATORYCAXTONK-2210 VITREOUS CHINALAVATORYCAXTONK-2210

VITREOUS CHINALAVATORYCAXTONK-2210 VITREOUS CHINALAVATORYCAXTONK-2210 VITREOUS CHINALAVATORYCAXTONK-2210

NORTH

REFRIG

SOUTHWEST SOUTH NORTH

TELEVISION

(NIC)

NORTHWEST EASTSOUTH SOUTH

2'- 6"

2'- 6"

2'- 6"

2'-

2'-

2" 2'-

0"

2'- 6"

2'- 6"

7'- 0"

3'-0"15" 15" 3'-3"3'-3"2'-4" 15" 12" 1" 3'-0" 3'-0"15"3'-5"2'-4" 15" 3'-5" 2'-4" 3'-0" 15" 3'-3" 2'-4" 3'-0" 2'-6"12"3'-3" 3'-0" 2'-0"1'-6" 3'-0" 1'-6" 1"1" 11'-2"

3'-0"3'-0"3'-0"3'-0"

3'-0" 2'-6"12"

1'-9" 1'-9"

2'- 6"

2'-

2'-

2'-

2'-

3'-0" 12" 3'-0"12"

3'-0"3'-0"

3'-8" 3'-8"

5'- 6"

5'- 6"

5'- 6"

5'- 6"

2'-

"5'- 6"

5'- 6"

5'- 6"

5'- 6"

5'- 6"

5'- 6"

5'- 6"

5'- 6"

5'- 6"

5'- 6"

5'- 6"

2'-

"5'- 6"

2'-

2'-

5 5 5 55555

5 5 5 5 5 5 5

6 6

7 7

8 8

9 9

10 10

11 11

12 12

2'- 6"3'-

8"

5'-6"3'-3" 3'-3"

2'- 6" 3'-

8"

2'-6" 3" 2'-6"3"

I-501

I-501

I-501

I-501

1. PORCELAIN WALL TILE (PORC-2)

2. PORCELAIN WALL TILE (PORC-3)

3. PORCELAIN WALL TILE (PORC-4)

4. PORCELAIN TILE BASE (PTB-1)

5. PAINT (AS SCHEDULED)

6. TOILET TISSUE DISPENSER

7. COMBINATION TOWEL DISPENSER / WASTE RECEPTACLE

8. 36" GRAB BAR (GB-1)

9. 42" GRAB BAR (GB-2)

10. 18" GRAB BAR (GB-3)

11. FRAMED MIRROR UNIT

12. CEILING-HUNG TOILET PARTITION

13. PLASTIC LAMINATE (PLAM-1)

14. COUNTERTOP (SS-1)

15. COUNTERTOP (QTZ-1)

KEY NOTES

ADMINISTRATION FACILITY

INTERIOR ELEVATIONS I-212

SCALE: 1/4" = 1'-0"

PUBLIC TOILET 102 INTERIOR ELEVATIONS1

APPROVED DRAWING TITLE

DATE

LOCATION

CHECKED PROJECT NUMBER

DRAWING NUMBER

DESCRIPTION DATE

DESIGN CONSULTANTS: ARCHITECT / ENGINEER OF RECORD:

C

Office of Construction and Facilities Management

1 3 4 5 6

B

A

D

E

C

B

A

D

E

BUILDING NUMBER

DRAWN

SEAL:

MARK

03-31-2020

DALLAS, TEXAS

916CM2012

DALLAS - FORT WORTH

NATIONAL CEMETERY

Calibre 9090 South Ridgeline Boulevard, Suite 105 Highlands Ranch, CO 80129 (303) 730-0434 www.calibre-engineering.com Construction Management Civil Engineering Surveying

Calibre Engineering, Inc.

Cemetery Expertise:

MKEC Engineering Ken Kallenbach

(316) 684-9600

Architect:

TK-Architecture, LLC Thomas J. Kapels

(719) 325-9303

Irrigation:

Aqua Engineering Bob Beccard

(970) 372-6104

Water Resources:

Leonard Rice Engineers Dave Colvin

(303) 867-7662

MEP:

Miller Remick MEP Tom Chapman

(856) 429-4000

Cost Estimating:

MOCA Cost Engineering Todd Waddle

(850) 389-8131

Surveying:

Fabre Engineering & Surveying Frank Fabre

(850) 433-6438

Geotechnical Engineering:

Terracon Consultants Jennifer Peters

(210) 907-7648

PHASE FOUR DEVELOPMENT

OF 246

TJK

SCALE: 1/4" = 1'-0"

PUBLIC TOILET 103 INTERIOR ELEVATIONS2

SCALE: 1/4" = 1'-0"

STAFF TOILET 108 INTERIOR ELEVATIONS3 SCALE: 1/4" = 1'-0"

STAFF TOILET 109 INTERIOR ELEVATIONS4

SCALE: 1/4" = 1'-0"

OPERATIONS CENTER INTERIOR ELEVATIONS5 SCALE: 1/4" = 1'-0"

BREAK ROOM INTERIOR ELEVATIONS6 SCALE: 1/4" = 1'-0"

CONFERENCE INTERIOR ELEVATIONS7

SCALE: 1/4" = 1'-0"

RECEPTION DESK INTERIOR ELEVATIONS8 SCALE: 1/4" = 1'-0"

RECEPTION INTERIOR ELEVATIONS9

2'-

2'-0"

2'- 41 2"

4"

3"

2'-1"

ADJUSTABLE

SHELF

11 2"

2'-

2'-0"

71 8" 1'-

93 8" 4"

3"

2'-1"

41 2"

ADJUSTABLE

SHELF

11 2"

MATERIALPRODUCTTRADENAMEMODELNUMBER

2'-1"

2'-

1'-3"

1'- 6"

9" 51 2"

7"

9" 2'-0"

4"

RE

M

O

VA

BL

E

PA

NE

L

11 2"

2'-1"

51 2" 11 2"

METAL SUPPORT

BRACKET @ 48" O.C.

AS

IN

DI

CA

TE

D

ON

E

LE

VA

TI

ON

1'-2"

1"

SOFFIT

ADJUSTABLE

SHELF

3 4"

3 4"

2'- 6"

2'-0"

2'- 01 2"

2'-1"

4"

3"

2'- 6"

2'-0"

61 8" 4"

3"

2'-1"

31 2"

1'- 63 8"

ADJUSTABLE

SHELF

ADJUSTABLE

SHELF

11 2"11 2"

2'- 6"

2'-0"

4" 1'-

01 4" 11 2"

3"

2'-1"

91 2" 31 2"

61 8"

31 2"

61 8"

2'- 6"

2'- 6"

2'-0"

4"

3"

2'-1"

ADJUSTABLE

SHELF

11 2"

2'-

2'-0"

71 8" 4"

71 8" 11 2"

3"

2'-1"

41 2" 41 2"

71 8"41 2" 41 2"

71 8"

51 2" 11 2"

METAL

SUPPORT

BRACKET

@ 48" O.C.

2'-8"

2'- 6"

1'-11"

4" 1'-

01 4" 11 2"

3"

91 2" 31 2"

61 8"

31 2"

61 8"

1'-2" 1'-10"

1'- 01 2"

11 2"

3'- 8"

CASEWORK DETAILS I-501

SCALE: 1-1/2" = 1'-0"

34" BASE w/ DOOR7 SCALE: 1-1/2" = 1'-0"

34" BASE w/ DOOR & DRAWER8 SCALE: 1-1/2" = 1'-0" 34" BASE w/ FOUR DRAWERS9 SCALE: 1-1/2" = 1'-0"

34" ACCESSIBLE BASE w/ SINK10

SCALE: 1-1/2" = 1'-0"

WALL CABINET w/ DOOR1 SCALE: 1-1/2" = 1'-0"

30" BASE w/ DOOR2 SCALE: 1-1/2" = 1'-0" 30" BASE w/ DOOR & DRAWER3 SCALE: 1-1/2" = 1'-0"

30" BASE w/ FILE & DRAWER4 SCALE: 1-1/2" = 1'-0" 30" BASE w/ OPEN SHELVES5 SCALE: 1-1/2" = 1'-0"

30" COUNTERTOP6

TJK

APPROVED DRAWING TITLE

DATE

LOCATION

CHECKED PROJECT NUMBER

DRAWING NUMBER

DESCRIPTION DATE

DESIGN CONSULTANTS: ARCHITECT / ENGINEER OF RECORD:

C

Office of Construction and Facilities Management

1 3 4 5 6

B

A

D

E

C

B

A

D

E

BUILDING NUMBER

DRAWN

SEAL:

MARK

03-31-2020

DALLAS, TEXAS

916CM2012

DALLAS - FORT WORTH

NATIONAL CEMETERY

Calibre 9090 South Ridgeline Boulevard, Suite 105 Highlands Ranch, CO 80129 (303) 730-0434 www.calibre-engineering.com Construction Management Civil Engineering Surveying

Calibre Engineering, Inc.

Cemetery Expertise:

MKEC Engineering Ken Kallenbach

(316) 684-9600

Architect:

TK-Architecture, LLC Thomas J. Kapels

(719) 325-9303

Irrigation:

Aqua Engineering Bob Beccard

(970) 372-6104

Water Resources:

Leonard Rice Engineers Dave Colvin

(303) 867-7662

MEP:

Miller Remick MEP Tom Chapman

(856) 429-4000

Cost Estimating:

MOCA Cost Engineering Todd Waddle

(850) 389-8131

Surveying:

Fabre Engineering & Surveying Frank Fabre

(850) 433-6438

Geotechnical Engineering:

Terracon Consultants Jennifer Peters

(210) 907-7648

PHASE FOUR DEVELOPMENT

OF 246195

1001 & 1301

SCALE: 1-1/2" = 1'-0"

RECEPTION DESK w/ TRANSACTION TOP11 SCALE: 1-1/2" = 1'-0"

RECEPTION DESK COUNTERTOP12

ROOM INFORMATION FLOORS WALLS

CEILING NOTES

NO. NAME FLOOR BASE NORTH EAST SOUTH WEST

101 ENTRY WOM-1 RB-2 PT-1 PT-1 PT-3 PT-1 ACT-1

102 PUBLIC TOILET PORC-1 PTB-1

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PT-4

103 PUBLIC TOILET PORC-1 PTB-1

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PT-4

104 LOBBY LVT-1/

LVT-3 RB-2 PT-2 PT-1 -- PT-1 ACT-1,

PT-1

105 RECEPTION LVT-1 RB-2 -- PT-1 PT-3 PT-1 ACT-1

106 CONFERENCE ROOM CPT-1 RB-1 PT-1 PT-1 PT-1 PT-3 ACT-1

107 OPEN OFFICE CPT-1 RB-1 PT-3 PT-3 PT-1 PT-1 ACT-1

108 STAFF TOILET PORC-1 PTB-1

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PT-4

109 STAFF TOILET PORC-1 PTB-1

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PT-4

110 CORRIDOR LVT-2 RB-2 PT-1 PT-1 PT-1 PT-1 ACT-1

111 OPERATIONS CENTER LVT-2 RB-2 PT-1 PT-2 PT-2 PT-1 ACT-1

112 STORAGE LVT-2 RB-2 PT-1 PT-1 PT-1 PT-1 ACT-1

113 TELECOMMUNICATIONS VCT-1 RB-2 PT-1 PT-1 PT-1 PT-1 PT-4

114 MECHANICAL SLR-1 RB-2 PT-1 PT-1 PT-1 PT-1 --

115 BREAK ROOM LVT-2 RB-2 PT-3 PT-3 PT-1 PT-1 ACT-1

116 ELECTRICAL SLR-1 RB-2 PT-1 PT-1 PT-1 PT-1 PT-4

117 CUSTODIAL SLR-1 RB-2 PT-1 PT-1,

FRP-1

PT-1,

FRP-1 PT-1 PT-4

118 BUDGET OFFICE CPT-1 RB-1 PT-2 PT-1 PT-1 PT-2 ACT-1

119 ADMINISTRATIVE OFFICER OFFICE CPT-1 RB-1 PT-2 PT-1 PT-1 PT-2 ACT-1

120 ASSISTANT DIRECTOR OFFICE CPT-1 RB-1 PT-2 PT-1 PT-1 PT-2 ACT-1

121 CEMETERY DIRECTOR OFFICE CPT-1 RB-1 PT-2 PT-1 PT-1 PT-2 ACT-1

122 ASSISTANT DIRECTOR OFFICE CPT-1 RB-1 PT-2 PT-1 PT-1 PT-2 ACT-1

ADMINISTRATION FACILITY ROOM FINISH SCHEDULE

NOTES:

1. INSTALL RESILIENT BASE WITHOUT TOE AT AREAS WITH CARPET. INSTALL RESILIENT BASE WITH TOE AT AREAS WITH VINYL AND

CONCRETE FLOORING.

ROOM INFORMATION FLOORS WALLS

CEILING NOTES

NO. NAME FLOOR BASE NORTH EAST SOUTH WEST

101 ENTRY WOM-1 RB-2 PT-3 -- PT-3 PT-3 PT-4

102 TRAINING ROOM LVT-2 RB-2 PT-2 PT-2 PT-1 PT-1 ACT-1

103 MULTI-USE TRAINING LVT-1 RB-2 PT-3 PT-1 PT-1 PT-1 ACT-1

104 COMPUTER TRAINING LVT-1 RB-2 PT-1 PT-1 PT-4 PT-1 ACT-1

105 STORAGE LVT-2 RB-2 PT-1 PT-1 PT-1 PT-1 PT-4

106 CUSTODIAL SLR-1 RB-2 PT-1,

FRP-1

PT-1,

FRP-1 PT-1 PT-1 PT-4

107 HALL LVT-2 RB-2 PT-1 PT-1 PT-1 PT-1 ACT-1

108 GROUNDS FOREMAN OFFICE LVT-2 RB-2 PT-3 PT-1 PT-1 PT-1 ACT-1

109 INTERMENT FOREMAN OFFICE LVT-2 RB-2 PT-3 PT-1 PT-1 PT-1 ACT-1

110 TELECOMMUNICATIONS VCT-1 RB-2 PT-1 PT-1 PT-1 PT-1 PT-4

111 STAFF TOILET PORC-1 PTB-1

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PT-4

112 GENERAL FOREMAN OFFICE LVT-2 RB-2 PT-3 PT-3 PT-1 PT-1 ACT-1

113 WORK LEADERS OFFICE LVT-2 RB-2 PT-1 PT-1 PT-1 PT-3 ACT-1

114 HONOR GUARD LVT-1 RB-2 PT-1 PT-1 PT-2 PT-2 ACT-1

115 HONOR GUARD TOILET PORC-1 PTB-1

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PORC-2,

PORC-3,

PT-2

PT-4

116 STORAGE LVT-1 RB-2 PT-1 PT-1 PT-1 PT-1 PT-4

117 ELECTRICAL EXISTING

118 CORRIDOR LVT-2 RB-2 PT-1 PT-1 PT-1 PT-1 ACT-1

119 MEN'S LOCKER ROOM RES-1 RES-1 EP-5 EP-5 EP-5 EP-5 PT-4

120 WOMEN'S LOCKER ROOM RES-1 RES-1 EP-5 EP-5 EP-5 EP-5 PT-4

121 CUSTODIAL SLR-1 RB-2 PT-1,

FRP-1

PT-1,

FRP-1 PT-1 PT-1 PT-4

122 UNIFORMS RES-1 RES-1 PT-1 PT-1 PT-1 PT-1 PT-4

123 BREAK ROOM LVT-2 RB-2 PORC-2,

PT-1 PT-1 PT-2 PT-1 ACT-1

MAINTENANCE FACILITY ROOM FINISH SCHEDULE

NOTES:

1. INSTALL RESILIENT BASE WITHOUT TOE AT AREAS WITH CARPET. INSTALL RESILIENT BASE WITH TOE AT AREAS WITH VINYL AND

CONCRETE FLOORING.

4" T

YP

4" T

YP

RESILIENT

BASE w/

COVE

TOE

RESILIENT

BASE w/

STRAIGHT

TOE

COVE

TILE

BASE

COVE

TILE

BASE w/

BULLNOSE

RESILIENT

BASE w/

BEVELED

TOP

STRAIGHT

TILE

BASE

STRAIGHT

TILE

BASE w/

BULLNOSE

SHEET

VINYL

COVE

BASE

4" T

YP

EPOXY

FLOORING

COVE

BASE

4" T

YP

ALUM.

TRIM

BACKER

MATERIAL

BACKER

MATERIAL

4" T

YP

BULLNOSE

EDGE

BULLNOSE

EDGE

41 2"

TY

P.

41 2"

TY

P.

41 2"

TY

P.

41 2"

TY

P.

NOTE: CORNER GUARDS

SHALL BE 60" HIGH UNLESS

NOTED OTHERWISE

STAINLESS STEEL

CORNER GUARD

MANUFACTURER'S

RECOMMENDED

ADHESIVE

METAL STUD WALL

FRAMING

GYPSUM BOARD

AS SCHEDULED

NOTE: CORNER GUARDS

SHALL BE 60" HIGH UNLESS

NOTED OTHERWISE

METAL STUD WALL

FRAMING

GYPSUM BOARD

AS SCHEDULED

ALUMINUM

RETAINER

SCREWS @

18" O.C. MAX

PLASTIC CORNER

GUARD COVER

RESILIENT FLOORING TO

FINISH FLOOR

DIRECT GLUE CARPET TO

RESILIENT FLOORING

CL CL

DIRECT GLUE CARPET TO

PORCELAIN TILE

CL

DIRECT GLUE CARPET TO

FINISH FLOOR

CL

RESILIENT

TRANSITION

STRIP

RESILIENT

TRANSITION

STRIP

RESILIENT

TRANSITION

STRIP

ALUMINUM

TILE EDGING

NOTE: MAXIMUM HEIGHT OF FLOOR

TRANSITIONS SHALL BE 1/4 INCH.

SCALE: 3" = 1'-0"

WALL BASE DETAILS - TYPICAL1

ROOM FINISHES I-601

SCALE: 12" = 1'-0"

FLOOR TRANSITION DETAILS - TYPICAL3 SCALE: 6" = 1'-0"

CORNER GUARD - PLASTIC4

SCALE: 6" = 1'-0"

CORNER GUARD - METAL2

APPROVED DRAWING TITLE

DATE

LOCATION

CHECKED PROJECT NUMBER

DRAWING NUMBER

DESCRIPTION DATE

DESIGN CONSULTANTS: ARCHITECT / ENGINEER OF RECORD:

C

Office of Construction and Facilities Management

1 3 4 5 6

B

A

D

E

C

B

A

D

E

BUILDING NUMBER

DRAWN

SEAL:

MARK

03-31-2020

DALLAS, TEXAS

916CM2012

DALLAS - FORT WORTH

NATIONAL CEMETERY

Calibre 9090 South Ridgeline Boulevard, Suite 105 Highlands Ranch, CO 80129 (303) 730-0434 www.calibre-engineering.com Construction Management Civil Engineering Surveying

Calibre Engineering, Inc.

Cemetery Expertise:

MKEC Engineering Ken Kallenbach

(316) 684-9600

Architect:

TK-Architecture, LLC Thomas J. Kapels

(719) 325-9303

Irrigation:

Aqua Engineering Bob Beccard

(970) 372-6104

Water Resources:

Leonard Rice Engineers Dave Colvin

(303) 867-7662

MEP:

Miller Remick MEP Tom Chapman

(856) 429-4000

Cost Estimating:

MOCA Cost Engineering Todd Waddle

(850) 389-8131

Surveying:

Fabre Engineering & Surveying Frank Fabre

(850) 433-6438

Geotechnical Engineering:

Terracon Consultants Jennifer Peters

(210) 907-7648

PHASE FOUR DEVELOPMENT

OF 246

TJK

1001 & 1301

NOTES:

1. INTERIOR SIGN SHALL COMPLY WITH ANSI 117.1 ACCESSIBILITY STANDARD.

2. TACTILE SIGN SHALL BE LOCATED ON THE LATCH SIDE OF SINGLE DOORS OR ON THE RIGHT SIDE OF THE RIGHT DOOR ON DOUBLE

DOORS.

3. MOUNTING HEIGHT SHALL BE MEASURED TO THE HORIZONTAL CENTER LINE OF EACH INTERIOR SIGN.

MAINTENANCE FACILITY INTERIOR SIGN SCHEDULE

SIGNS COLOR INSCRIPTION

NOTES

NO. TYPE MATERIAL FIELD FRAME TEXT FONT MESSAGE

IN-03 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA MULTI-USE TRAINING

IN-04 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA COMPUTER TRAINING

IN-05 DETL 4 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA STORAGE

IN-06 DETL 4 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA CUSTODIAL

IN-08 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA GROUNDS FOREMAN

IN-09 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA INTERMENT FOREMAN

IN-10 DETL 4 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA TELECOM

IN-11 DETL 7 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA RESTROOM

IN-12 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA FOREMAN

IN-13 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA WORK LEADERS

IN-13A DETL 2 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA WORK LEADER INSTALL ON OFFICE

FURNITURE

IN-13B DETL 2 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA WORK LEADER INSTALL ON OFFICE

FURNITURE

IN-15 DETL 7 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA RESTROOM

IN-16 DETL 4 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA STORAGE

IN-19 DETL 5 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA MEN

IN-20 DETL 6 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA WOMEN

IN-21 DETL 8 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA CUSTODIAL

IN-23A DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA BREAK ROOM

IN-23B DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA BREAK ROOM

IN-23F DETL 3 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HELVETICA MAXIMUM OCCUPANCY 86

ADMINISTRATION FACILITY INTERIOR SIGN SCHEDULE

NOTES:

1. INTERIOR SIGN SHALL COMPLY WITH ANSI 117.1 ACCESSIBILITY STANDARD.

2. TACTILE SIGN SHALL BE LOCATED ON THE LATCH SIDE OF SINGLE DOORS OR ON THE RIGHT SIDE OF THE RIGHT DOOR ON DOUBLE

DOORS.

3. MOUNTING HEIGHT SHALL BE MEASURED TO THE HORIZONTAL CENTER LINE OF EACH INTERIOR SIGN.

SIGNS COLOR INSCRIPTION

NOTES

NO. TYPE MATERIAL FIELD FRAME TEXT FONT MESSAGE

IN-02 DETL 5 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HELVETICA MEN

IN-03 DETL 6 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA WOMEN

IN-06 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA CONFERENCE ROOM

IN-07A DETL 2 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA CEMETERY REPRESENTATIVE INSTALL ON OFFICE

FURNITURE

IN-07B DETL 2 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA CEMETERY REPRESENTATIVE INSTALL ON OFFICE

FURNITURE

IN-07C DETL 2 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA CEMETERY REPRESENTATIVE INSTALL ON OFFICE

FURNITURE

IN-07D DETL 2 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA CEMETERY REPRESENTATIVE INSTALL ON OFFICE

FURNITURE

IN-07E DETL 2 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA CEMETERY REPRESENTATIVE INSTALL ON OFFICE

FURNITURE

IN-07F DETL 2 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA CEMETERY REPRESENTATIVE INSTALL ON OFFICE

FURNITURE

IN-07G DETL 2 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA CEMETERY REPRESENTATIVE INSTALL ON OFFICE

FURNITURE

IN-07H DETL 2 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA CEMETERY REPRESENTATIVE INSTALL ON OFFICE

FURNITURE

IN-08 DETL 6 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA MEN

IN-09 DETL 5 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA WOMEN

IN-11 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA OPERATIONS CENTER

IN-12 DETL 4 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA STORAGE

IN-13 DETL 4 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HELVETICA TELECOM

IN-14 DETL 4 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA MECHANICAL

IN-15 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA BREAK ROOM

IN-16 DETL 4 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA ELECTRICAL

IN-17 DETL 7 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA CUSTODIAL

IN-18 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA BUDGET OFFICER

IN-19 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA ADMINISTRATIVE OFFICER

IN-20 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA ASSISTANT DIRECTOR

IN-21 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHTE HEVLETICA CEMETERY DIRECTOR

IN-22 DETL 1 RIGID VINYL POINT

BLUE ALUM DESIGN

WHITE HEVLETICA ASSISTANT DIRECTOR

2"

21 4" 63 4"

9"

9"

REMOVABLE

END CAPS

1" TACTILE

ROOM

NUMBER w/

BRAILLE

2"

21 4" 21 4"

41 2"

9"

REMOVABLE

END CAPS

1" TACTILE

ROOM

NUMBER w/

BRAILLE

4" 1

4" 1 4" 1

4"

Name or TitleName or Title

2"

83 4"

9"

REMOVABLE

END CAPS

4" 1

4"

WOMEN

1" TACTILE

TEXT w/

BRAILLE21 4"

2"

83 4"

9"

REMOVABLE

END CAPS

4" 1

4"

1" TACTILE

TEXT w/

BRAILLE21 4"

2"

83 4"

9"

REMOVABLE

END CAPS

4" 1

4"

RESTROOM

3/4" TACTILE

TEXT w/

BRAILLE21 4"

MAXIMUM

OCCUPANCY

2"

41 2"

9"

REMOVABLE

END CAPS

3/4" TACTILE

TEXT

4" 1

4"

MEN

STORAGE

2"

21 4"

9"

3/4" TACTILE

TEXT w/

BRAILLE

4" 1

4"

REMOVABLE

END CAPS

#### 1" TACTILE

TEXT

PRINTED

PAPER INSERT

PRINTED

PAPER INSERT

INTERIOR SIGNAGE I-611

APPROVED DRAWING TITLE

DATE

LOCATION

CHECKED PROJECT NUMBER

DRAWING NUMBER

DESCRIPTION DATE

DESIGN CONSULTANTS: ARCHITECT / ENGINEER OF RECORD:

C

Office of Construction and Facilities Management

1 3 4 5 6

B

A

D

E

C

B

A

D

E

BUILDING NUMBER

DRAWN

SEAL:

MARK

03-31-2020

DALLAS, TEXAS

916CM2012

DALLAS - FORT WORTH

NATIONAL CEMETERY

Calibre 9090 South Ridgeline Boulevard, Suite 105 Highlands Ranch, CO 80129 (303) 730-0434 www.calibre-engineering.com Construction Management Civil Engineering Surveying

Calibre Engineering, Inc.

Cemetery Expertise:

MKEC Engineering Ken Kallenbach

(316) 684-9600

Architect:

TK-Architecture, LLC Thomas J. Kapels

(719) 325-9303

Irrigation:

Aqua Engineering Bob Beccard

(970) 372-6104

Water Resources:

Leonard Rice Engineers Dave Colvin

(303) 867-7662

MEP:

Miller Remick MEP Tom Chapman

(856) 429-4000

Cost Estimating:

MOCA Cost Engineering Todd Waddle

(850) 389-8131

Surveying:

Fabre Engineering & Surveying Frank Fabre

(850) 433-6438

Geotechnical Engineering:

Terracon Consultants Jennifer Peters

(210) 907-7648

PHASE FOUR DEVELOPMENT

OF 246

TJK

SCALE: 3" = 1'-0"

ROOM IDENTIFICATION SIGN1 SCALE: 3" = 1'-0"

WORKSTATION SIGN2

SCALE: 3" = 1'-0"

MAXIMUM OCCUPANCY SIGN3

SCALE: 3" = 1'-0"

MENS RESTROOM SIGN5 SCALE: 3" = 1'-0"

WOMENS RESTROOM SIGN6

SCALE: 3" = 1'-0"

RESTROOM SIGN7

SCALE: 3" = 1'-0"

UTILITY ROOM SIGN4

1001 & 1301

File details come from the government source that posted it. Updated .