Round_3_Q&A.pdf

PDF 39 KB Posted

Attached to
S&RTS All Ports, Belgium Federal contract opportunity
Solicitation number
HTC711-19-R-R002
Issued by
Department of Defense United States Transportation Command

About this file

Q&A Round 3

View the file

Other files for this federal contract opportunity

Other files attached to S&RTS All Ports, Belgium, newest first.
File Type Posted
Round_4_Q&A.pdf PDF
Amendment_2_-_Attachment_2_SOR.xlsx XLSX spreadsheet
HTC711-19-R-R002_Amendment_2_RFP_APB.pdf PDF
Round_2_MTON_Conversion_-_Cheat_Sheet.xlsx XLSX spreadsheet
Round_2_Q&A.pdf PDF
Round_1_Q&A.pdf PDF
Amend_1_-_Solicitation.pdf PDF
Amend_1_-_Attachment_1_PWS_APB.pdf PDF
Attachment_2_SOR.xlsx XLSX spreadsheet
Attachment_1_PWS_APB.pdf PDF
Attachment_5_-_Addendums_to_52.212-1_&_52.212-2.docx DOCX document
Attachment_4_-_Corporate_Experience.docx DOCX document
HTC711-19-R-R002_APB_Solicitation.pdf PDF
Attachment_6_-_Technical_Worksheet.docx DOCX document
Attachment_3_-_RFP_Information_Sheet_.docx DOCX document
RFP_letter.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ALL PORTS BELGIUM S&RTS

RFP HTC711‐19‐R‐R002

QUESTION AND ANSWER ROUND 3

Question 3: Please clarify on the Schedule of Rates for Line items 270 through 291 where there is an estimated duration. The Extended Price only calculates the Unit Price times the Unit Quantity. Should the Extended Price also calculate by the Estimated Duration or should the Unit Price include the

Estimate Duration?

For Example for Open Staging Area, the Estimated Duration is 10 days. Should the unit price be a Daily

Rate or a Rate for the entire 10 days?

Answer Question 3: The Extended Price should include the Estimated Duration. The Amended Schedule of Rates calculates correctly therefore, all Proposals shall submit the Amendment 2 Schedule of Rates.