HTC711-16-R-R029_Amd_0006.pdf
PDF 222 KB Posted
- Attached to
- Busan, Korea S&RTS Federal contract opportunity
- Solicitation number
- HTC711-16-R-R029
About this file
Amendment 0006 revised Addendum 52.212-1 & 52.212-2
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Blank_SOR_837th_Korea_SRTS_FINAL_170321_G3.xlsx | XLSX spreadsheet | |
| HTC711-16-R-R029_Amd_0010.pdf | ||
| HTC711-16-R-R029_Amd_0009.pdf | ||
| HTC711-16-R-R029_Amd_0008.pdf | ||
| HTC711-16-R-R029_Amd_0007.pdf | ||
| Solicitation_Questions_Korea_Round_4.pdf | ||
| Solicitation_Questions_Korea_Round_3.pdf | ||
| Solicitation_Questions_Korea_Round_1_170105v1.pdf | ||
| 837th_Korea_SRTS-_SOR_FINAL_Blank.xlsx | XLSX spreadsheet | |
| TAB_B3_Korea_SRTS-PWS_170131Final.pdf | ||
| HTC711-16-R-R029_Amd_0005.pdf | ||
| HTC711-16-R-R029_Amd_0003.pdf | ||
| HTC711-16-R-R029_Amd_0001.pdf | ||
| ATTCH_3_Invoicing_Instruction.pdf | ||
| ATTCH_2_837th_Korea_SRTS-_SOR_Blank.xlsx | XLSX spreadsheet | |
| ATTCH_1_Korea_SRTS-PWS_161013_FINAL_FE.pdf | ||
| HTC711-16-R-R029.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to make changes to SOR, PWS, Addendum 52.212-1, 52.212-2 and post solicitation Q&A. All changes made to the PWS, Addendum 52.212-1 & 52.212-2 have been highlighted on those documents.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 8
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Feb-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X HTC711-16-R-R029
X 9B. DATED (SEE ITEM 11)
07-Dec-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-Feb-2017
CODE
USTRANSCOM-AQ - HTC711
508 SCOTT DR
SCOTT AFB IL 62225-5357
HTC711 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
HTC711-16-R-R029
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been modified:
ADDENDUM 52.212-1
ADDENDUM TO 52.212-1, INSTRUCTIONS TO OFFERORS – COMMERCIAL ITEMS (FEB 2012)
Paragraph (b) entitled “Submission of Offers” is deleted in its entirety and replaced with paragraph“(b) Proposal
Preparation Instructions” below:
(b) PROPOSAL PREPARATION INSTRUCTIONS
General Information
To assure timely and equitable evaluation of proposals, offerors must follow the instructions contained herein.
Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements. Failure to meet a requirement may result in an offer being ineligible for award.
The contracting officer has determined there is a high probability of adequate price competition in this acquisition.
Upon examination of the initial offers, the contracting officer will review this determination and if, in the contracting officer’s opinion, adequate price competition exists no additional cost information will be requested and certification under FAR 15.406-2 will not be required. However, if at any time during this competition the contracting officer determines that adequate price competition no longer exists offerors may be required to submit information to the extent necessary for the contracting officer to determine the reasonableness of the price.
1. Offerors are required to submit an electronic version of the proposal via electronic mail (email) with the
Request for Proposal (RFP) number and Offeror’s business name in the subject line, by the due date specified.
All documents provided by email shall be Adobe PDF files except Part II, pricing proposal, which shall be in
Microsoft Excel format with an .xlsx file extension.
2. Proposals shall be submitted via email using Times New Roman, 12 point font except for figures, tables, and diagrams where smaller is acceptable as long as it is legible. The maximum page limit for each part includes all text pages, tables, graphs, and other types of illustrative material. Cover Page or Table of Contents does not count against the page limits for the respective parts. Excess pages exceeding the maximum limits will not be read or considered in the evaluation.
3. Proposals shall be submitted in English. Any Contract Documentation written in a language other than English must be accompanied by an English translation of the document.
4. Proposals shall include the following parts:
A. Part I - Contract Documentation (1 of 3)
B. Part II – Technical Proposal (2 of 3)
C. Part III – Price Proposal (3 of 3)
Proposals shall be submitted in three separate emails, labelled 1 of 3 (Contract Documentation), 2 of 3
(Technical) and 3 of 3 (Price). The Technical proposal shall be separate from Pricing Proposal.
5. Instructions for submitting Contract Documentation (Part I), Technical Proposal (Part II) and Price Proposal (Part
III) are as follows:
A. Part I - Contract Documentation
(1) This part shall consist of a cover page which contains (i) the company name and address as registered in the System for Award Management (SAM) database; (ii) DUNS code; (iii) CAGE code;
and (iv) and the solicitation number.
(2) The name, title, telephone number and email address of the company/division point of contact of the individual(s) authorized to make decisions with respect to your proposal and who can obligate your company contractually and any other individual authorized to negotiate with the Government on your behalf.
(3) Complete blocks 12 (must be completed even if no discount is offered), 17a, 30a, b and c of the
SF 1449, Solicitation. In doing so, the offeror accedes to the contract terms and conditions as written in the RFP, with attachments. Signature by the offeror on the SF 1449 constitutes an offer, which the Government may accept. Block 17b – if remittance address is different, such address must be registered in the System for Award Management (SAM) database.
(4) Complete blocks 8, 15A and 15B on each SF30, Amendment of Solicitation to acknowledge all solicitation amendments (if any).
(5) Representations and Certifications should be submitted online using SAM at https://www.sam.gov or may be submitted with contract documentation.
(6) Offerors shall submit appropriate documentary evidence – Licensure or other written authorization from the Port Authority and any other documentation that the offeror or its intended subcontractor(s) is authorized to perform the required services at the specified location(s), and:
a. Proof of current certification of at least two (2) proposed personnel trained and tested in handling
Hazardous Materials per the requirements of the Code of Federal Regulation (CFR) Title 49, Section 172.702 or Host Nation equivalent.
b. Proof of capability to perform customs clearance through a licensed customs broker or clearing agency.
(7) Corporate Experience Information
A list of relevant contractual experience performing Stevedoring and Related Terminal Services in a similar or greater scope, magnitude and complexity as that required by this solicitation, completed during the past three (3) years. The list shall be limited to three (3) efforts or contracts and shall include:
a. Name and address of the contracting activity and point of contact;
b. Total contract value; and
c. Description of work performed, including experience performing Managerial, Planning, Safety and Security functions and Loading, Discharging, Receipt and Disposition of International
Maritime Dangerous Goods (IMDG) cargo.
B. Part II – Technical Proposal. Technical Proposals shall be clear, concise, and include sufficient detail for effective evaluation against factors defined in the addendum to 52.212-2 of this solicitation. The proposal should not simply rephrase or restate the Government’s requirements, but rather shall provide convincing rationale to address how the offeror intends to meet the requirements of the PWS. Statements that the https://www.sam.gov/ offeror understands, can, or will comply with the PWS; statements paraphrasing the PWS or parts thereof;
and phrases such as “standard procedures will be employed’ or “well known techniques will be used,” etc., will be considered unacceptable. Offerors shall assume the Government has no prior knowledge of their experience, and the Government will base its evaluation solely on the information presented in the proposal. The technical proposal shall address the following subfactors:
(1) Technical Subfactor 1 – Stevedore Business License. Offerors shall submit appropriate documentary evidence – Licensure or other written authorization from the Port Authority and any other documentation that the offeror or its intended subcontractor(s) is authorized to perform the required services at the specified location(s), and:
a. Proof of current certification of at least two (2) proposed personnel trained and tested in handling Hazardous Materials per the requirements of the Code of Federal Regulation (CFR) Title 49, Section 172.702 or Host Nation equivalent.
b. Proof of capability to perform customs clearance through a licensed customs broker or clearing agency.
(2) Technical Subfactor 2 – Mission Capability. Offeror proposal shall describe its approach for achieving the objectives of PWS paragraphs 3.0. - Safety, 5.0. - Contractor General Requirements and
6.0. - Terminal Specific Requirements. Responses to this subfactor shall be limited to no more than 25 pages (Table of Contents will not be included in page count).
C. Part III – Price Proposal
(1) Schedule of Rates. The offeror shall input unit pricing rates for all cells highlighted in yellow within
Atch 2, Pricing Schedule. If offeror intends to offer a service at no charge or escalation, the offeror shall insert 0 in the applicable cell. There should be no blank cells on the pricing schedule. The
Excel (.xlsx) spreadsheet (pricing schedule) will auto-populate total prices for (i) the base period, (ii) each option period and the six month extension of services to establish the Total Evaluated Price
(TEP).
(2) All unit pricing rates shall be submitted in US Dollars ($).
NOTE: Contract award and payment shall be made in US Dollars ($).
(3) All prices submitted shall be entered to the nearest cent, not to exceed two (2) decimal places.
Paragraph (c) entitled “Period of acceptance of offers” is tailored to read: The Government requires a minimum of
150 calendar days for acceptance of offers submitted in response to this solicitation.”
Paragraph (e) entitled “Multiple Offers” is tailored to read: “The government will not consider multiple offers presenting alternate terms and conditions for satisfying the requirements of this solicitation.”
Paragraph (g) entitled “Contract award (not applicable to Invitation for Bids).” Is tailored to read: “The
Government intends to evaluate offers and award a single contract without discussions with offerors. Therefore, the offeror’s initial offer should contain the offeror’s best terms from a price and technical standpoint. However, the
Government reserves the right to conduct discussions if later determined by the Contracting Officer to be necessary.
The Government may reject any or all offers if such action is in the public interest; accept other than the lowest offer; and waive informalities and minor irregularities in offers received.”
Paragraph (h) entitled “Multiple awards” is tailored to read: “The Government intends to award one contract as a result of this solicitation. Unless otherwise provided in the Schedule, offers may not be submitted for quantities less than those specified. The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit prices offered, unless the offeror specifies otherwise in the offer.”
Formal communications, such as requests for clarification, questions and/or written information concerning this solicitation should be submitted via email to:
William Henderson, Contracting Officer at william.r.henderson12.civ@mail.mil and
Brita Dorsey, Contract Specialist at brita.m.dorsey.civ@mail.mil.
The request should be in the following format:
Reference: Section ___, Page ____, Paragraph ____
Question: ____________________________________.
Written questions will be answered in writing and provided to all offerors via an Amendment posting to
FedBizOpps. However, due to the time required to research a question and provide an answer, questions received less than 10 calendar days prior to the due date of offers specified in this solicitation may not be answered.
Solicitation changes resulting from any provided answers will be made via amendment and posted to FedBizOpps.
A preproposal teleconference is tentatively scheduled for 15 December 2016 at 4:00 p.m. Central Standard Time.
Participants must request teleconference information via email to Brita Dorsey, brita.m.dorsey.civ@mail.mil or
William Henderson, william.r.henderson12.civ@mail.mil , 14 December 2016 by 1:00 p.m. Central Standard
Time.
ADDENDUM 52.212-2
ADDENDUM TO 52.212-2 EVALUATION – COMMERCIAL ITEMS (OCT 2014):
Paragraphs (d) and (e) are added to read as follows:
(d) Basis for contract award - This acquisition is being conducted under FAR Part’s 12, Acquisition of
Commercial Items, Subpart 12.6 and Part 15, Contracting by Negotiation of the Federal Acquisition
Regulation (FAR). Offers will be evaluated using the factors identified in FAR 52.212-2, Evaluation –
Commercial items and this addendum. Noncompliance may be grounds to eliminate the proposal from consideration for contract award. Award will be made on the basis of Lowest Price Technically
Acceptable Source Selection Process, IAW FAR 15.101-2. By submission of its offer in accordance with the instructions provided in clause FAR 52.212-1, Instructions to Offerors, and the Addendum to FAR
52.212-1, the offeror agrees to the terms of this solicitation.
Specifically, the evaluation process shall proceed as follows: First, the proposals will be ranked in price order from lowest to highest based on the Total Evaluated Price (TEP). The lowest ranked TEP offeror’s technical proposal will then be evaluated to receive a rating of Acceptable or Unacceptable. In order to be rated as Acceptable, the Technical proposal must meet the Government's minimum requirements as stated in paragraph A, below. Proposals deemed Unacceptable are those that fail to meet the
Government's minimum requirements.
If the lowest ranked TEP offeror’s technical proposal is rated acceptable, the Government will then evaluate that offeror’s pricing proposal to determine fair and reasonableness using one or more techniques set forth in FAR 15.404-1(b)(2). Additionally, IAW FAR 15.404-1(g), the Government will review the proposed prices to determine if unbalanced pricing exists.
If proposed prices are unbalanced, this will be noted and the risk to the Government will be considered in making the source selection decision. IAW FAR 15.404-1(g) (3), if the lack of balance poses an unacceptable risk to the Government, the offer may be rejected and not considered further for award. If the lowest ranked TEP offeror’s technical proposal is rated acceptable and it is determined that the offer mailto:william.r.henderson12.civ@mail.mil mailto:brita.m.dorsey.civ@mail.mil.
mailto:brita.m.dorsey.civ@mail.mil mailto:william.r.henderson12.civ@mail.mil has fair and reasonable pricing and balanced pricing (or if unbalanced pricing exists that it does not pose an unacceptable risk), the Government will complete a responsibility determination IAW the criteria specified in FAR 9.104-1.
The offeror’s Corporate Experience Information will be considered in the Government’s responsibility determination IAW the standards specified in FAR 9.104-1. If found responsible, the evaluation process stops at this point as that offer represents the best value to the Government. Award shall be made to that offeror without further consideration of any other offers.
If due to unbalanced pricing the lowest ranked TEP offeror poses an unacceptable risk, or if that offeror’s technical proposal is assigned an unacceptable rating, or if the offeror’s pricing is not fair and reasonable, or if the offeror is found to be non-responsible, the offer with the next lowest ranked TEP will be evaluated in accordance with the paragraphs above. This process will continue in order of ascending TEP until an offeror’s proposal is judged to have an acceptable technical rating, fair and reasonable prices, balanced pricing (or if unbalanced pricing exists that it does not pose an unacceptable risk) and the offeror is deemed responsible; or until all offers have been evaluated.
The Source Selection Authority (SSA) will determine whether it is in the Government's best interest to award without discussions or enter into discussions. If the SSA determines to enter into discussions, a competitive range will be established IAW FAR 15.306(c). The source selection team will complete the discussion process, request final proposal revisions, and document final evaluation results IAW DOD
Source selection procedures for those offerors determined to be within the competitive range. After the evaluation of the final proposal revisions, the SSA will make a selection of the best-value proposal consistent with the stated evaluation criteria.
The following factors shall be used to evaluate offers:
A. Factor I: Technical Approach. Each offeror’s written Technical Proposal will be evaluated to determine if the offeror’s technical approach is Acceptable or Unacceptable at the subfactor level, as defined below.
RATING DESCRIPTION
Acceptable Proposal meets the minimum requirements of the solicitation.
Unacceptable Proposal does not meet the minimum requirements of the solicitation.
If any technical subfactor is rated as Unacceptable, the overall Technical Proposal will be Unacceptable.
If all technical subfactors are rated as Acceptable, then the overall Technical Proposal will be Acceptable.
Offeror’s proposals must receive a rating of Acceptable for all of the following technical subfactors in order to be considered for award:
(1) Subfactor 1 – Stevedoring Business License. To be rated Acceptable, The Offeror shall provide a copy of the appropriate documentary evidence – Licensure or other written authorization from the Port Authority and any other documentation that the offeror or its intended subcontractor(s) is authorized to perform the required services at the specified location(s), and:
a) Proof of current certification of at least two (2) proposed personnel trained and tested in handling Hazardous Materials per the requirements of the Code of Federal
Regulation (CFR) Title 49, Section 172.702 and 172.704; Chapter 1.3, International Maritime Dangerous Goods Code (IMDGC) and/or Host Nation equivalent. Training must be current within the time limits specified in section
172.704(c), CFR49."
b) Proof of capability to perform customs clearance through a licensed customs broker or clearing agency.
(2) Subfactor 2 – Mission Capability. To be rated Acceptable, the offeror’s technical approach must clearly describe the concept of operations in the following objectives of the PWS. When evaluating the Offeror’s Technical Approach, the Government will determine if:
a) The approach demonstrates the offeror’s ability to conduct operations in accordance with applicable safety standards and regulations.
b) The approach demonstrates the offeror’s ability and knowledge of ocean terminal operations to include:
Discharge and Loading vessels, rail and trucks, drayage of containers, vehicles and other equipment
Timely receipt/disposition of cargo
Stuffing/Unstuffing-Stripping containers
Cargo Preparation/Intra-Terminal Transfer
Proper handling and stowage of ammunition and hazardous cargo
Cargo onward Movement
Cargo Yard Management, Staging and Yard Management
c) The approach demonstrates the offeror’s capability to maintain accountability and tracking of all DTS cargo (import/export) offered for shipment
d) The approach demonstrates the offerors ability to plan and schedule all operational activities for cargo load/discharge of multiple vessel types to include
Proper stow location, pay, nested, linked, secondary loads and condition of loaded cargo
Offerors should limit their technical proposal to addressing the specific minimum requirements listed above. Sections of the submitted technical proposal addressing elements of the PWS not listed above will not be considered in the overall rating. If any of the above is rated as Unacceptable, the entire
Technical Proposal will be rated as Unacceptable.
B. Factor II: Price.
(1) Completion of the pricing schedule will require the user to have good working knowledge of the Microsoft Excel program. The Offeror shall complete and submit the Pricing Schedule, Attachment 2. The pricing schedule shall be submitted as an attachment to an email and contain no hidden formulas or external links. The Government will utilize the Pricing Schedule to capture pricing and to calculate the Total Evaluated Price (TEP) for evaluation and award purposes. Thus, the TEP is calculated using the rates proposed in all cells where proposed unit pricing is required, for the base and all option periods, with any proposed escalation, to include a 6 month extension of services. The summation of the base, all option years, and the six month extension of services will constitute the TEP. Offeror will be considered ineligible for award if all required pricing is not inserted and included in the Pricing
Schedule.
This information shall be utilized by the Government to analyze offeror’s rates. Upon contract award, this data will form the basis for any price adjustments pursuant to the Revision of Prices clause, DFARS 252.247-7002, and, as such, must provide the means of determining the application of any requested adjustments and calculating the revised unit prices.
(2) In order to be considered for award, price must be determined fair and reasonable and balanced (or if unbalanced pricing exists that it does not pose an unacceptable risk to the Government) using one or more techniques set forth in FAR 15.404-1(b)(2).
(e) The Government reserves the right to award no contract at all depending on the quality of the proposals submitted and availability of funds for the requirement. The Government intends to evaluate proposals and award a single IDIQ contract without discussions. Therefore, the offerors will be advised that their initial offer should contain the most favorable terms and reflect its best possible performance potential. The Government does reserve the right to clarify aspects of the proposals and hold discussions, as allowable under FAR Part 15 procedures.
(End of Summary of Changes)