This document is a Questions and Answers file for Solicitation HT940626QE005, a water sample collection and analysis services contract issued by the Defense Health Agency. The solicitation covers water sample testing at three locations (Shaw AFB, Poinsett Range, and Wateree Air Force Recreational area) with a base year and four 12-month option years, starting April 1, 2026. Key clarifications include laboratory certification requirements, acceptable analytical methods (such as EPA Method 200.8 for Lead and Copper), and confirmation that the contract scope is limited to sampling, analysis, reporting, and treatment recommendations without physical remediation.

The solicitation is a small business set-aside Request for Quotation (RFQ) requiring electronic quote submission. The Q&A document addresses technical details such as sample collection frequencies, quality control requirements, sampling point access, and pricing considerations. Contractors must include travel costs within line item pricing and comply with specific EPA method requirements for water sample testing, including PFAS testing via method 533. The government emphasizes that prospective contractors should rely solely on the current solicitation requirements and that all line items, including emergency or special event testing quantities, will be evaluated before award.

View the file

Other files for this federal contract opportunity

Other files attached to Water Sample Collection and Analysis Services - Amendment 6, newest first.
File Type Posted
Amendment 6 - Solicitation HT940626QE005.pdf PDF
Pricing Template - HT940626QE005 - Amend 6.xlsx XLSX spreadsheet
Questions and Answers - HT940626QE005 16JAN26.docx DOCX document
Questions and Answers - HT940626QE005 15JAN26.docx DOCX document
Amendment 5 - Solicitation HT940626QE005.pdf PDF
Amendment 4 - Solicitation HT940626QE0050004.pdf PDF
Amendment 3 - Solicitation HT940626QE005.pdf PDF
Pricing Template - HT940626QE005.xlsx XLSX spreadsheet
Amendment 2 - Solicitation HT940626QE005.pdf PDF
Questions and Answers - HT940626QE005.docx DOCX document
Amendment 1 - Solicitation HT940626QE005.pdf PDF
Solicitation - HT940626QE005.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and answers - Solicitation HT940626QE005

#
Section
Question
Answer
1
PWS 1.4.3 and 3.1.1
Does the sampler need to follow Method 4500-H+B and Method 4500-Cl and test while onsite, or does a laboratory need to be accredited and complete the analysis?
The laboratory must be certified by the state of South Carolina.
2
PWS 1.4.3 and 1.4.5.1
They run the parameters with Potable Water accreditations. (I didn't see any RLs or MDLs on the SOW.)
The RLs and MDLs are based on the method.
3
PWS 1.4.3
Is Lead and Copper w/ EPA 200.8 method acceptable?
Yes. The customer has stated that the required method is actually 200.8. Therefore, the PWS has been modified to reflect EPA Method 200.8”. See bullet 1.4.3 and 1.4.5.1.
4
PWS 1.4.3
Clarification regarding Line Item 3001 AW. Could you please confirm how many metals/elements are required under Method 200.7?
Bullet 1.4.3 of the PWS included in the solicitation contains the parameters per method. There is no 3001AW SLIN in this solicitation.
5
PWS 1.3
We reviewed the historical contract information and noted that the prior award did not appear to exercise the full anticipated period of performance and included a funding only de-obligation. Without discussing prior contractor performance, can you please confirm whether the current solicitation reflects any changes to scope, quantities, or performance expectations, or whether offerors should rely solely on the requirements stated in the current PWS?
Prospective contractors must rely solely on the requirements stated in solicitation HT940626QE005.
6
PWS bullets1.4.5 and 1.4.6; Quote Instructions bullet g
The solicitation references emergency or 'special event' testing quantities. Can you please confirm these are not included in the evaluated base price and would only be exercised via future contract modification, if required?
solicitation HT940626QE005/SF1449 Contains SLINs that must be filled out by contractors submitting quotes. Some of those SLINs reflect emergencies or special events requirements. Refer to the quote instruction Section in the solicitation document for more information.

All SLINs and pricing will be evaluated before award.

7
PWS 1.4
Can you please confirm that contractor responsibilities are limited to sampling, analysis, reporting, and recommendations of treatment, and that physical remediation or treatment activities are not within scope?
The requirements on this solicitation do not include physical remediation or treatment activities.

PWS 1.4

Would it bring value to a contractors’ bid if they had the capability to purify water through building systems or maintaining ones on site?
The Government appreciates detailed and thoughtful quotes. We recognize the potential of additional capabilities. However, the additional capabilities fall outside the scope of the current requirements. The suggestion is for proposals to align with the requirements stated in the solicitation.
9
PWS 1.6.7 & 2.1.7
The PWS references well and system sampling. Can you please confirm that existing sampling points or access locations will be made available by the Government, and that the contractor is not responsible for installing or modifying sampling infrastructure?
The contractor shall coordinate a sampling schedule with the BE POC for each and all analysis at the three (3) location areas for the contract period of performance. And must coordinate with the COR and BE POC to obtain a visitor's

pass and escort while on base property. The contractor is not responsible for installing or modifying sampling infrastructure.

10
PWS 1.4
I don’t see a separate line item for the travel.
The price per line item must include the price for travel. Refer to the quote instruction Section in the solicitation document for more information.
11
PWS 1.4. and 2.1.2
Can you tell me whether the quantity of 48 PFAS testing via method 533 samples include field blanks?
The contractor shall comply with the quality control requirements

per method (e.g., matrix spikes, reagent blanks), handling requirements (e.g., any preservation requirements, sample container requirements, etc.), storage, and holding time per analytical method specifications. Contractors must account for quality control requirements per method when preparing their proposals. The quantities stated in the solicitation are per required method. Contractors must include the quality controls as stipulated for each EPA method.

12
PWS 1.4
How many times per year will we be required to collect samples from the three facilities?
See PWS update in solicitation amendment 3. The update provides the frequency per required EPA methods (See bullet 1.4.3 and sub-bullets).