ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
HSFLCS-15-R-00001/000001
Period of Performance: 04/01/2015 to 03/31/2020
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
QUESTIONS AND ANSWERS – 1
HSFLAR-15-R-00001
20 Jan 2015
1. Is there a format or specific form to submit questions?
ANSWER: No, an email is sufficient to submit questions regarding this solicitation.
2. Is there an existing contract for this service currently at FLETC? Is there a Freedom of Information Department?
ANSWER: The incumbent contractor is Northcon Inc. The contract number is HSFLCS-10-D-00001. For information regarding Freedom of Information Act (FOIA), please go to the FLETC webpage at www.fletc.gov. FOIA information can be found under “Freedom of Information”.
3. Pg. 106, Para L.2, FAR Clause 52.215-1(c)(2) discusses information that should be on the first page. Is this the same page mentioned on page 114, Para L.12(c)(2)? Need Clarification.
ANSWER: The requirements in Para L.12(c)(2) are in addition to the requirements of FAR Clause 52.215-1(c)(2). FAR Clause 52.215-1(c)(2) is required for the first page of the submitted proposal. The requirements of Para L.12 shall be provided as stated in the specific sections. The information may contain some duplicate information, but compliance with both sections is required.
4. Pg 114, Section L, Paragraph L.12 d (2) Management Approach states that proposal must include an evaluation of using e-verify to ensure compliance with these requirement. Please clarify as to what e-verify has to do with Management Approach other than employment of new employees.
ANSWER: Proposal must indicate if the company utilizes e-verify system within their company as part of their proposal per the terms of the solicitation.
5. Section L, Paragraph L.12.e, Section III, Past Performance, Page 114 of 123, – the RFP requires that a maximum of
3 contracts be submitted for past performance. However, the RFP does not clearly state what type of projects that would be relevant to task order projects. Is it new construction, renovation, just demolition, or what?
Please clarify.
ANSWER: It is the offeror’s discretion as to what types of contracts are submitted for this requirement. Page 120, Section M, Factor C: Past Performance provides some information regarding relevancy.
6. The referenced solicitation states that there will be ONLY one IDIQ awarded, but it has been our experience that sometimes IDIQs are awarded to a pool of contractors like under a MATOC or MACC. Please confirm that the solicitation language is correct and ONLY one IDIQ will be awarded under it.
ANSWER: This solicitation is for a single award IDIQ contract. This is not a solicitation for a multiple award IDIQ contract.