About this file

Station Eatons Neck Final Report

View the file

Other files

File Type Posted
TMACC_Amendment_0008.pdf PDF
TMACC_Amendment_0007.pdf PDF
TMACC_Amendment_0006.pdf PDF
6_-_TMACC_Past_Performance_Questionnaire_Amdt_0006.pdf PDF
TMACC_Amendment_0005.pdf PDF
TMACC_Amendment_0004.pdf PDF
WD_FL153.pdf PDF
WD_NY12.pdf PDF
WD_NC69.pdf PDF
WD_AK1.pdf PDF
WD_HI1.pdf PDF
WD_ME8.pdf PDF
TMACC_Amendment_0003.pdf PDF
WD_CA29.pdf PDF
WD_MI33.pdf PDF
9723_CMD-CEN_Tower_Northport_FY15_Photo_21.bmp BMP image
9723_CMD-CEN_Tower_Northport_FY15_Photo_22.bmp BMP image
9723_CMD-CEN_Tower_Northport_FY15_Photo_23.bmp BMP image
TMACC_Amendment_0002.pdf PDF
10228_CMD-CEN_TOWER_Station_Hobucken_FY_15_Photo_7.bmp BMP image
2017_TMACC_SF1442_Amdt_0002.pdf PDF
10228_CMD-CEN_TOWER_Station_Hobucken_FY_15_Photo_8.bmp BMP image
10228_CMD-CEN_TOWER_Station_Hobucken_FY_15.pdf PDF
10228_Photo_1.PNG PNG image
10228_Photo_2.PNG PNG image
TMACC_Amendment_0001.pdf PDF
2017_TMACC_SF1442_Amdt_0001.pdf PDF
3_-_TMACC_Contractor_Responsibility.pdf PDF
TMACC_Solicitation.pdf PDF
7_-_Material_Approval_Submittal.pdf PDF
6_-_TMACC_Past_Performance_Questionnaire.pdf PDF
5_-_TMACC_Pre-proposal_Inquiry.pdf PDF
1_-_TMACC_Seed_Project_SOW.pdf PDF
2_-_Seed_Project_Wages.pdf PDF
8_-_Fed_Reg_for_FAR_52_222-23.pdf PDF
4_-_TMACC_Experience_&_Project_Information_Form.pdf PDF
2017_TMACC_SF1442.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Site Master Inc. Proprietary & Confidential

Page | 2

II – Table of Contents

Section Page Title Page

I Title Page 1

II Table of Contents 2

III Executive Summary 3

IV Recommended Maintenance 6

V Chronological Narrative 6

Appendices Page

A Tower Inspection Photographs 7

B Tower Height Verification Form 21

C Tower Condition Assessment Form 22

D Repair Estimate(s) Sheet 23

Site Master Inc. Proprietary & Confidential

Page | 3

III - Executive Summary

i. Inspection Summary

The 80’ self-supporting communications tower at the U.S. Coast Guard Station Eaton’s Neck in Northport N.Y. was inspected on 13-14 July 2015 by SiteMaster, Inc. of Tulsa, Oklahoma. The lacing of the four tower sections consisted of bolted, x-braced angles from 0-20’, bolted solid diagonals from 20-60’ and welded, solid round diagonals from 60-80’.

ii. Structural Members

The inspectors found no loose anchor bolts on any of the tower legs. All anchor bolts are equipped with pal nuts.

The inspectors did not find any loose structural connection bolts on any of the three tower legs from 0-80’. Inspectors noted that all connection bolts are equipped with pal nuts.

Inspectors found no loose connection bolts on any of the diagonal members or gusset plates. All bolts are equipped with a locking device such as pal nuts.

A variable amount of rust and corrosion is visible on all three tower legs from 20-80’. All surfaces are rusted or corroded.

A large percentage of the connection bolts on the tower flanges and diagonals are also rusted or corroded.

The tower foundation is in satisfactory condition.

There are three bent diagonal members at 61’, 62’, and 79’6”.

iii. Alignment and Twist

A visual inspection of the tower’s alignment showed that the structure appeared plumb.

iv. FAA Obstruction Lighting System

Not applicable to this tower.

v. Guy System and Guy Hardware

Not applicable to this tower.

vi. Guy Anchors and Foundation

Not applicable to this tower.

Site Master Inc. Proprietary & Confidential

Page | 4

vii. Insulator Systems

Not applicable to this tower.

viii. Grounding Systems

The tower appears to be satisfactorily grounded. All three tower legs have clamped grounding leads. Each ground lead is running underground to a presumed tower ground ring.

The coaxial cable on the tower is not grounded although grounds are cut in to the coax.

The leads have been removed and no buss bars are installed.

The inspectors suggest the ground leads on the tower legs be exothermically welded to the tower legs to conform to industry standards. It is also suggested that the coax be properly grounded and the ground leads be connected to a buss bar that is connected directly to the ground ring at the bottom of the tower. The coax should also be grounded on the tower before the connection to the antenna and the buss bar should be directly connected to the tower allowing the tower legs to act as the connection to the grounding ring.

There is no lightning rod on the tower. It is suggested a lightning rod be installed at the top of the tower and that it is attached to its own ground lead. The ground lead should run the length of the tower and be exothermically welded to the ground ring at the bottom of the tower.

ix. OSHA Standards

The tower is equipped with a climbing ladder and safety climb rail. The climbing ladder extends from 20-80’ and is mounted directly to the face of the tower. The climbing ladder mounting U-bolts are stainless steel and in good condition. The ladder flanges are rusted and corroded. 100% of the climbing ladder and connections were wire brushed and application of zinc-rich cold galvanizing paint was applied.

The safety climb rail extends from 20-80’. The rail and mounting hardware shows signs of rust and corrosion. 100% of the safety rail and hardware was wire brushed by the inspectors and an application of zinc rich cold galvanizing paint was applied.

It is suggested the climb ladder and the safety rail be extended to the bottom of the tower.

It is also necessary to mount the ladder on standoffs allowing for the 7” OSHA requirement of clearance between the ladder rungs and the tower face.

It is also recommended that the safety climb rail be replaced with a 3/8” safety climb cable device to conform to industry standards.

Site Master Inc. Proprietary & Confidential

Page | 5

x. Miscellaneous

The inspectors found two antennas on the tower at separate heights. The first was mounted at 57’6”. The antenna appears to be in good condition, although the mounting hardware shows significant signs of rust and corrosion. The second antenna is mounted at 63’8” and 80’. The antenna shows some signs of aging and requires attention to avoid more costly repairs. The antenna mounting hardware shows signs of corrosion and rust.

All areas of rust and corrosion were wire brushed by the inspectors and an application of cold galvanization was applied.

xi. Maintenance Accomplished

The inspectors used a wire brush and cleaned heavily rusted or corroded components of the tower. 100% of the tower received an application of zinc-rich cold galvanization compound. 100% of bolts were checked for torque and tightened where needed.

Site Master Inc. Proprietary & Confidential

Page | 6

IV – Recommendations

Within 1 Year:

1. A six foot lightning rod should be installed at the top of the tower.

2. Coax needs to be properly grounded and the ground leads be connected to a buss bar that is connected directly to the ground ring at the bottom of the tower.

3. It is suggested the climb ladder and the safety rail be extended to the bottom of the tower. It is also necessary to mount the ladder on standoffs allowing for the 7”

OSHA required clearance between the ladder rungs and the tower face.

4. It is recommended that the safety climb rail be replaced with a 3/8” safety climb cable device to conform to industry standards.

5. Tower leg ground leads need to be exothermically welded to the tower legs to comply with industry standards.

6. Replace the three bent diagonal members at 61’, 62’, and 79’6”.

V – Chronological Narrative

Date: 7/13/15

Weather Conditions: Sunny Wind: 5-10MPH

Time Work Performed

1430-1445 Arrived on site; safety meeting

1445-1730 Performed ground and tower inspection

1730 Left site

Date: 7/14/15

Weather Conditions: Sunny Wind: 5-10MPH

Time Work Performed

0800-0815 Arrived on site; safety meeting

0815-1100 Applied cold galvanization paint to 100% of tower

1100-1130 Cleaned up

1130 Left site

Site Master Inc. Proprietary & Confidential

Page | 7

Appendix A Tower Inspection Photographs

Overall View of Tower

Site Master Inc. Proprietary & Confidential

Page | 8

No. Description Photograph

1 Site ID

2 Tower leg A

3 Tower leg B

Site Master Inc. Proprietary & Confidential

Page | 9

4 Tower leg C

5 Looking up tower – face AB

6 Looking up tower – face BC

Site Master Inc. Proprietary & Confidential

Page | 10

7 Looking up tower – face CA

8 Tower foundation

9 View up tower – leg A

Site Master Inc. Proprietary & Confidential

Page | 11

10 View up tower – leg B

11 View up tower – leg C

12 Climbing ladder

Site Master Inc. Proprietary & Confidential

Page | 12

13 Safety climb tower clamp

14 Tower ladder U-bolt clamp

15 Cross members - rusted

Site Master Inc. Proprietary & Confidential

Page | 13

16 Cross members - repaired

17 Cross members - repaired

18 Leg flange – rusted

Site Master Inc. Proprietary & Confidential

Page | 14

19 Cross members - rusted

20 Cross members - repaired

21 Bent diagonal at 61’

Site Master Inc. Proprietary & Confidential

Page | 15

22 Bent diagonal at 62’

23 Bent diagonal at 79’6”

24 Antenna coax ground at 54’

Site Master Inc. Proprietary & Confidential

Page | 16

25 Antenna at 57’6”

26 Antenna at 57’6”

27 Antenna at 57’6” – mount rusted

Site Master Inc. Proprietary & Confidential

Page | 17

28 Antenna at 57’6” – mount rusted

29 Antenna at 63’8”

30 Antenna at 63’8” – mount rusted

Site Master Inc. Proprietary & Confidential

Page | 18

31 Antenna at 63’8” – mount rusted

32 Antenna at 63’8” – mount rusted

33 Antenna at 63’8” – coax grounding

Site Master Inc. Proprietary & Confidential

Page | 19

34 Unused mount at 76’ - rusted

35 Unused mount at 80’ - rusted

36 Tower mount at 83’ - rusted

Site Master Inc. Proprietary & Confidential

Page | 20

Appendix B

Site Master Inc. Proprietary & Confidential

Page | 21

Appendix C

PROJECT:

NO. OF

UNITS

UNIT UNIT COST COST UNIT COST COST

30 MHRS $ 400.00 $ 400.00 $ 85.00 $ 2,550.00

20 MHRS $ 25.00 $ 500.00 $ 95.00 $ 1,900.00

16 MHRS $ 45.00 $ 720.00 $ 95.00 $ 1,520.00

10 MHRS $ 25.00 $ 250.00 $ 95.00 $ 950.00

5 MHRS $ 50.00 $ 250.00 $ 95.00 $ 475.00

10 MHRS $ 20.00 $ 200.00 $ 95.00 $ 950.00

APPROVED BY: DATE

TITLE: 28-Jul-15

ITEM (OR FEATURE) DESCRIPTION

QUANTITIES MATERIAL COST LABOR COST

LOCATION:

Northport, NY

ACTIVITY:

Tower Inspection, Maintenance

Replace (3) bent diagonals

Extend climbing ladder to bottom of tower

Install new safety climb system

Install tower lightning rod

Ground antenna coax

Ground tower legs at base

$ 3,000.00

Equipment $ 500.00

COST ESTIMATING WORKSHEET

LABOR COST $ 8,345.00

MATERIAL COST $ 2,320.00

Kenneth Groth

Corporate Estimator

Project Management $ 1,000.00

Mobilization

6914 S. Yorktown, Suite 210 • Tulsa, OK 74136 • 918.663.2232 • 888.494.7483 • Fax: 918.663.2291 • www.sitemaster.com

TOWER HEIGHT & DESIGNATION

80' SST - 0004C Sta Eatons Neck

Task Order Number:

HSCG1-15-J-PMV070

DHS - U.S. COAST GUARD

To Be Completed Within One Year

$ 15,165.00

Tower Inspection, Maintenance and Repairs of USCG District 1 Towers

TOTAL COST (EST.)