Site Master Inc. Proprietary & Confidential
Page | 2
II – Table of Contents
Section Page Title Page
I Title Page 1
II Table of Contents 2
III Executive Summary 3
IV Recommended Maintenance 6
V Chronological Narrative 6
Appendices Page
A Tower Inspection Photographs 7
B Tower Height Verification Form 21
C Tower Condition Assessment Form 22
D Repair Estimate(s) Sheet 23
Site Master Inc. Proprietary & Confidential
Page | 3
III - Executive Summary
i. Inspection Summary
The 80’ self-supporting communications tower at the U.S. Coast Guard Station Eaton’s Neck in Northport N.Y. was inspected on 13-14 July 2015 by SiteMaster, Inc. of Tulsa, Oklahoma. The lacing of the four tower sections consisted of bolted, x-braced angles from 0-20’, bolted solid diagonals from 20-60’ and welded, solid round diagonals from 60-80’.
ii. Structural Members
The inspectors found no loose anchor bolts on any of the tower legs. All anchor bolts are equipped with pal nuts.
The inspectors did not find any loose structural connection bolts on any of the three tower legs from 0-80’. Inspectors noted that all connection bolts are equipped with pal nuts.
Inspectors found no loose connection bolts on any of the diagonal members or gusset plates. All bolts are equipped with a locking device such as pal nuts.
A variable amount of rust and corrosion is visible on all three tower legs from 20-80’. All surfaces are rusted or corroded.
A large percentage of the connection bolts on the tower flanges and diagonals are also rusted or corroded.
The tower foundation is in satisfactory condition.
There are three bent diagonal members at 61’, 62’, and 79’6”.
iii. Alignment and Twist
A visual inspection of the tower’s alignment showed that the structure appeared plumb.
iv. FAA Obstruction Lighting System
Not applicable to this tower.
v. Guy System and Guy Hardware
Not applicable to this tower.
vi. Guy Anchors and Foundation
Not applicable to this tower.
Site Master Inc. Proprietary & Confidential
Page | 4
vii. Insulator Systems
Not applicable to this tower.
viii. Grounding Systems
The tower appears to be satisfactorily grounded. All three tower legs have clamped grounding leads. Each ground lead is running underground to a presumed tower ground ring.
The coaxial cable on the tower is not grounded although grounds are cut in to the coax.
The leads have been removed and no buss bars are installed.
The inspectors suggest the ground leads on the tower legs be exothermically welded to the tower legs to conform to industry standards. It is also suggested that the coax be properly grounded and the ground leads be connected to a buss bar that is connected directly to the ground ring at the bottom of the tower. The coax should also be grounded on the tower before the connection to the antenna and the buss bar should be directly connected to the tower allowing the tower legs to act as the connection to the grounding ring.
There is no lightning rod on the tower. It is suggested a lightning rod be installed at the top of the tower and that it is attached to its own ground lead. The ground lead should run the length of the tower and be exothermically welded to the ground ring at the bottom of the tower.
ix. OSHA Standards
The tower is equipped with a climbing ladder and safety climb rail. The climbing ladder extends from 20-80’ and is mounted directly to the face of the tower. The climbing ladder mounting U-bolts are stainless steel and in good condition. The ladder flanges are rusted and corroded. 100% of the climbing ladder and connections were wire brushed and application of zinc-rich cold galvanizing paint was applied.
The safety climb rail extends from 20-80’. The rail and mounting hardware shows signs of rust and corrosion. 100% of the safety rail and hardware was wire brushed by the inspectors and an application of zinc rich cold galvanizing paint was applied.
It is suggested the climb ladder and the safety rail be extended to the bottom of the tower.
It is also necessary to mount the ladder on standoffs allowing for the 7” OSHA requirement of clearance between the ladder rungs and the tower face.
It is also recommended that the safety climb rail be replaced with a 3/8” safety climb cable device to conform to industry standards.
Site Master Inc. Proprietary & Confidential
Page | 5
x. Miscellaneous
The inspectors found two antennas on the tower at separate heights. The first was mounted at 57’6”. The antenna appears to be in good condition, although the mounting hardware shows significant signs of rust and corrosion. The second antenna is mounted at 63’8” and 80’. The antenna shows some signs of aging and requires attention to avoid more costly repairs. The antenna mounting hardware shows signs of corrosion and rust.
All areas of rust and corrosion were wire brushed by the inspectors and an application of cold galvanization was applied.
xi. Maintenance Accomplished
The inspectors used a wire brush and cleaned heavily rusted or corroded components of the tower. 100% of the tower received an application of zinc-rich cold galvanization compound. 100% of bolts were checked for torque and tightened where needed.
Site Master Inc. Proprietary & Confidential
Page | 6
IV – Recommendations
Within 1 Year:
1. A six foot lightning rod should be installed at the top of the tower.
2. Coax needs to be properly grounded and the ground leads be connected to a buss bar that is connected directly to the ground ring at the bottom of the tower.
3. It is suggested the climb ladder and the safety rail be extended to the bottom of the tower. It is also necessary to mount the ladder on standoffs allowing for the 7”
OSHA required clearance between the ladder rungs and the tower face.
4. It is recommended that the safety climb rail be replaced with a 3/8” safety climb cable device to conform to industry standards.
5. Tower leg ground leads need to be exothermically welded to the tower legs to comply with industry standards.
6. Replace the three bent diagonal members at 61’, 62’, and 79’6”.
V – Chronological Narrative
Date: 7/13/15
Weather Conditions: Sunny Wind: 5-10MPH
Time Work Performed
1430-1445 Arrived on site; safety meeting
1445-1730 Performed ground and tower inspection
1730 Left site
Date: 7/14/15
Weather Conditions: Sunny Wind: 5-10MPH
Time Work Performed
0800-0815 Arrived on site; safety meeting
0815-1100 Applied cold galvanization paint to 100% of tower
1100-1130 Cleaned up
1130 Left site
Site Master Inc. Proprietary & Confidential
Page | 7
Appendix A Tower Inspection Photographs
Overall View of Tower
Site Master Inc. Proprietary & Confidential
Page | 8
No. Description Photograph
1 Site ID
2 Tower leg A
3 Tower leg B
Site Master Inc. Proprietary & Confidential
Page | 9
4 Tower leg C
5 Looking up tower – face AB
6 Looking up tower – face BC
Site Master Inc. Proprietary & Confidential
Page | 10
7 Looking up tower – face CA
8 Tower foundation
9 View up tower – leg A
Site Master Inc. Proprietary & Confidential
Page | 11
10 View up tower – leg B
11 View up tower – leg C
12 Climbing ladder
Site Master Inc. Proprietary & Confidential
Page | 12
13 Safety climb tower clamp
14 Tower ladder U-bolt clamp
15 Cross members - rusted
Site Master Inc. Proprietary & Confidential
Page | 13
16 Cross members - repaired
17 Cross members - repaired
18 Leg flange – rusted
Site Master Inc. Proprietary & Confidential
Page | 14
19 Cross members - rusted
20 Cross members - repaired
21 Bent diagonal at 61’
Site Master Inc. Proprietary & Confidential
Page | 15
22 Bent diagonal at 62’
23 Bent diagonal at 79’6”
24 Antenna coax ground at 54’
Site Master Inc. Proprietary & Confidential
Page | 16
25 Antenna at 57’6”
26 Antenna at 57’6”
27 Antenna at 57’6” – mount rusted
Site Master Inc. Proprietary & Confidential
Page | 17
28 Antenna at 57’6” – mount rusted
29 Antenna at 63’8”
30 Antenna at 63’8” – mount rusted
Site Master Inc. Proprietary & Confidential
Page | 18
31 Antenna at 63’8” – mount rusted
32 Antenna at 63’8” – mount rusted
33 Antenna at 63’8” – coax grounding
Site Master Inc. Proprietary & Confidential
Page | 19
34 Unused mount at 76’ - rusted
35 Unused mount at 80’ - rusted
36 Tower mount at 83’ - rusted
Site Master Inc. Proprietary & Confidential
Page | 20
Appendix B
Site Master Inc. Proprietary & Confidential
Page | 21
Appendix C
PROJECT:
NO. OF
UNITS
UNIT UNIT COST COST UNIT COST COST
30 MHRS $ 400.00 $ 400.00 $ 85.00 $ 2,550.00
20 MHRS $ 25.00 $ 500.00 $ 95.00 $ 1,900.00
16 MHRS $ 45.00 $ 720.00 $ 95.00 $ 1,520.00
10 MHRS $ 25.00 $ 250.00 $ 95.00 $ 950.00
5 MHRS $ 50.00 $ 250.00 $ 95.00 $ 475.00
10 MHRS $ 20.00 $ 200.00 $ 95.00 $ 950.00
APPROVED BY: DATE
TITLE: 28-Jul-15
ITEM (OR FEATURE) DESCRIPTION
QUANTITIES MATERIAL COST LABOR COST
LOCATION:
Northport, NY
ACTIVITY:
Tower Inspection, Maintenance
Replace (3) bent diagonals
Extend climbing ladder to bottom of tower
Install new safety climb system
Install tower lightning rod
Ground antenna coax
Ground tower legs at base
$ 3,000.00
Equipment $ 500.00
COST ESTIMATING WORKSHEET
LABOR COST $ 8,345.00
MATERIAL COST $ 2,320.00
Kenneth Groth
Corporate Estimator
Project Management $ 1,000.00
Mobilization
6914 S. Yorktown, Suite 210 • Tulsa, OK 74136 • 918.663.2232 • 888.494.7483 • Fax: 918.663.2291 • www.sitemaster.com
TOWER HEIGHT & DESIGNATION
80' SST - 0004C Sta Eatons Neck
Task Order Number:
HSCG1-15-J-PMV070
DHS - U.S. COAST GUARD
To Be Completed Within One Year
$ 15,165.00
Tower Inspection, Maintenance and Repairs of USCG District 1 Towers
TOTAL COST (EST.)