1. CONTRACT ID CODE PAGE OF PAGES
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1 3
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
0001 08/18/2011 4086757
6. ISSUED BY CODE 51290 7. ADMINISTERED BY (If other than Item 6)
CODE
Commanding Officer
CG CEU OAKLAND (PCD)
2000 Embarcadero
Oakland, CA 94606-5337
Moffett Field, CA. 94035-1000
Commanding Officer
CG CEU OAKLAND (PCD)
2000 Embarcadero
Oakland, CA 94606-5337
8. NAME AND ADDRESS OF CONTRACTOR (No. Street, county, State and ZIP: Code) () 9A. AMENDMENT OF SOLICITATION NO.
ISC BioExpress
X HSCG88-11-R-TMACC
9B. DATED (SEE ITEM 11)
To All Prospective Offerors
Kaysville, UT. 84037
08 August 2011
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning one (1) copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATA SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and data specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
() A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET
FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER: Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copy to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
IDIQ NATIONAL TOWER/ANTENNA MULTIPLE AWARD CONSTRUCTION CONTRACT (TMACC) AT VARIOUS COAST GUARD
FACILITIES THROUGHOUT THE UNITED STATES AND TERRITORIES.
The purpose of this amendment is to provide answers to the request for information:
Cont’d on Page 2
Except at provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
JEFFREY A. CROSS
Contracting Officer
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
(Signature of person authorized to sign)
BY ___________________________________________
(Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE COMPUTER GENERATED Prescribed by GSA
HSCG88-11-R-TMACC
Amendment 0001 page 2 of 3
Questions:
1. How are these services currently performed (in house, contractor)?
Answer: These services were provided by contractors.
2. If by a contractor,
a. What is the Contractor Name?
Answer: Communication Services Inc. HSCG88-06-D-623108; Seacomm Erectors Inc. HSCG88-06-D-
623109; Swager Communications Inc. HSCG88-06-D-623011; and Tower Inspection Inc. HSCG88-06-D-
623111.
b. What is the Contract Number?
Answer: Please refer to 2.a. above.
c. When was the contract awarded?
Answer: Communication Services Inc. March 27, 2006; Seacomm Erectors Inc. March 28, 2006; Swager
Communications Inc. March 14, 2006; and Tower Inspection Inc. March 28, 2006.
d. When does the contract expire?
Answer: Communication Services Inc. HSCG88-06-D-623108 expired March 26, 2011; Seacomm
Erectors Inc. HSCG88-06-D-623109 expired March 27, 2011; Swager Communications Inc. HSCG88-06-
D-623011 expired March 13, 2011; and Tower Inspection Inc. HSCG88-06-D-623111 expired March 27, 2011.
e. What are the contract period of performance terms? (i.e. base and 4 one-year options, etc.)
Answer: Base and 4 one-year options.
f. What type of Contract was awarded (Firm Fixed Price, ID/IQ, etc.)
Answer: IDIQ
g. How was the contract awarded (Full & Open, HubZone set-aside, Small Business Set-aside, Sole Source, etc.)
Answer: Total Small Business
h. What is the current contract value or ceiling?
Answer: Individual delivery orders may range between estimated $2,000 - $2 million. The program value is not-to-exceed $5 million per year over a five-year period.
3. Regarding HSCG88-11-R-TMACC, would you be willing to share incumbent information (contractor names and contract numbers)? Or is this a new requirement – or a combination of several previous requirements?
4. Is the specification titled “Tower Inspection and Minor Maintenance” the sample project? If so, will you be providing information on the towers to be inspected – locations, heights and types, the minor work to be performed, etc.?
Answer: Appendix A lists the site name, city, State, tower height, Tower use, Tower type, Tower material type, year constructed, and exact LAT & Longitude. The Scope for inspection requirements are provided within pages 1-17.
HSCG88-11-R-TMACC
Amendment 0001 page 3 of 3
5. I located the RFP, but the SF1449 did not have a responses due date. It just had TBD for the date. When are proposals due?
Answer: Attached is the new SF1449 showing block 13.A to state: Sealed offers in original and 1 copy to perform the work required are due at the place specified in Item 8 by 4:00 p.m. (hour) local time October 3, 2011 (date).
6. Would you please verify the due date for proposals for the TMACC solicitation? The FBO notice states Oct.
3, but the SF-1442 states TBD.
Answer: Attached is the new SF1449 showing block 13.A to state: Sealed offers in original and 1 copy to perform the work required are due at the place specified in Item 8 by 4:00 p.m. (hour) local time October 3, 2011 (date).
7. Please provide incumbent’s contract number:
8. For the seed project:
a. List of the towers in each state
Answer: Please refer to attached Appendix A.
b. The tower heights
Answer: Please refer to attached Appendix A.
c. Whether the towers have lighting kits
Answer: Yes for all tower heights that are 150 feet and higher.
d. Prevailing wage rate schedule
Answer: General Decision Number: CA100029 08/12/2011 CA29 for San Francisco General Decision Number: MT100089 08/12/2011 MT89 for Polson, MT
General Decision Number: OR100085 05/27/2011 OR85 for Klamath Falls, OR
General Decision Number: WA100087 07/01/2011 WA87 for Oak Harbor, WA
General Decision Number: CA100019 08/05/2011 CA19 for Bria, CA
9. Is the IDIQ Coast Guard Tower/Antenna RFP still going to be a Hubzone set aside?
Answer: Yes, it is a Hubzone set aside.
10. I was just wondering if we need to respond to “IDIQ National Tower/Antenna Multiple Award Construction
Contract (TMACC) at various Coast Guard Facilities throughout the United States and Territories” even though there is not funding at the present time. Will you please let us know?
Answer: For your firm to be considered, you will need to respond to this solicitation. 2012 funds are not presently available for this project. No award will be made under this solicitation until 2012 funds are available.
11. Is there a site visit?
Answer: There is no scheduled site visit.