1. CONTRACT ID CODE PAGE OF PAGES
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
0002 19 May 2017 2117857***B29
6. ISSUED BY CODE HSCG85 7. ADMINISTERED BY (If other than Item 6) CODE
USCG COMMAND
Surface Forces Logistics Centers, C&PD2-LREPL 1301 Clay Street, Suite 800N, Oakland, CA 94612
SAME AS BLOCK #6
8. NAME AND ADRESS OF CONTRACTOR (no., street, county, State and ZIP Code) √ 9.A AMENDMENT OF SOLICITATION NO.
TO ALL PROSPECTIVE OFFERORS
HSCG85-17-R-P45B29
9B. DATE (SEE ITEM 11)
25 April 2017
10A. MODIFICATION OF CONTRACT/ORDER
NO. ?
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the Offer submitted: or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/.ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority).
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
SUBJECT: RFP No. HSCG85-17-R-P45B29 USCGC BERTHOLF (WMSL 750), Dockside Repairs FQ4 FY17
The purpose of this amendment is to:
1. Extend the solicitation end date from May 30, 2017 to June 6, 2017, 1:00 p.m. Pacific time.
2. Extend the deadline for Requests for Clarification from May 19, 2017 to May 26, 2017 at 1:00 p.m. Pacific time.
SEE PAGE 2 FOR ADDITIONAL DESCRIPTION
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Wilma L. Estrada, Contracting Officer 15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)PREVIOUS
EDITION UNUSABLE Prescribed by GSA, FAR (48 CFR) 53.243
3. Change the anticipated award date from June 30, 2017 to July 7, 2017.
HSCG85-17-R-P45B29
USCGC BERTHOLF (WMSL 750) Dockside Repairs FQ4 FY17 Amendment No. 0002
4. Reply to the following Requests for Clarification:
Question 1: This is in reference to Work Item D-25; Flex Hose Assemblies, Renew;
Paragraph 2: Reference 750-WMSL-505-006 Rev. D, List of Hoses (ASC505006) was not on the reference CD. Is this reference available?
Answer to Question 1: No. This drawing is still going through revision and is not available.
Question 2: This is in reference to Work Item D-02; Main Propulsion Diesel Engine, Exhaust Piping, Commercial Cleaning; Paragraph 3.5.1: The drawings show the expansion joints as being welded at one end and flange bolted at the other, thus they could not be removed without cutting them at the weld, is that correct?
Answer to Question 2: Elevation 3-B of Sheet 3 of CG Dwg 750 WMSL 259-11 shows a clean-out connection just up from the expansion joint. If the expansion joint is welded into place and cannot be removed, it is acceptable to the Coast Guard to break the piping at the upstream flange on the expansion joint and blank it to prevent contamination, then clean out the pipe through the clean out connection. It is not the intent to break any welded joints in this specification item.
Question 3: This is in reference to Work Item D-02; Main Propulsion Diesel Engine, Exhaust Piping, Commercial Cleaning; Paragraph 3.5.1: In order to clarify the Start and or End pending which direction the cleaning starts. For our purpose The MDE exhaust cleaning starts at the first Expansion Joint PC 16 on page 3 of 7 750-WMSL-259-011 which is bolted to the forward MDE Exhaust Manifold, terminating up through to the top of the stack?
Is That Correct?
Answer to Question 3: Yes. Starting at the expansion joint and cleaning up to the stack is satisfactory.
Question 4: This is in reference to Work Item D-17; Cofferdam, Install; Paragraph 1.1:
A: How many Sea Chest Cofferdams are to be installed?
B: Please identify the size of each intended Cofferdam?
C: Confirm the Cofferdams are contractor supplied?
Answer to Question 4:
A. Contractor to count the number of required cofferdams based on other work in the spec package.
B. Cofferdams are related to the work being done in the separate work items. Ship check may be required.
C. Cofferdams are contractor supplied.
Question 5: This is in reference to Work Item D-23; Deck Covering (Slip Resistant), Renew; Figure 1: Figure 1 CIWS Deck shows the Ammo and Flare Boxes, are these to be removed as interference’s for preservation underneath?
Answer to Question 5: Boxes that are bolted to their foundation shall be temporarily moved and reinstalled after completion. Boxes that are welded in place shall not be disconnected from the foundations but the Contractor shall work around them.