REVISED SECTION B: SUPPLIES OR SERVICES AND PRICES
SEE AMENDMENT 0003
NOTICE TO OFFERORS: Offeror(s) must complete and submit all applicable items of this Solicitation, with particular emphasis on Sections A, B, I and K. This is a Total Small Business Set-Aside
Provide all labor, materials and equipment, except as specified, to perform INDUSTRIAL SUPPORT FOR INSTALLATION OF THE SECURE COMMUNICATIONS INFORMATION FACILITY (SCIF) ON USCGC WAESCHE (WMSL 751) DURING MAINTENANCE & REPAIR PERIOD 1 (M&R-1), at cutter’s home moorage in Alameda, California, during the period of 2 March 2010 to 29 May 2010. ** IMPORTANT NOTE** CGC WAESCHE IS SCHEDULED TO BE COMMISSIONED AT COAST GUARD ISLAND ON FRIDAY 7 MAY 2010. THEREFORE NO CONTRACTOR WORK ON OR NEAR THE SHIP WILL BE ALLOWED BEGINNING 0700 ON MONDAY 3 MAY 2010 UNTIL 0700 ON SATURDAY 8 MAY 2010. THERE WILL BE SPECIFIC LIMITATIONS ON THE EQUIPMENT THAT THE CONTRACTOR MAY HAVE ON THE SHIP AND ON THE PIER ADJACENT TO THE SHIPS LOCATION, ALL AS MORE FULLY SET FORTH IN THE GENERAL REQUIREMENTS’ SECTION OF THE SPECIFICATIONS ACCOMPANYING THIS REQUEST FOR PROPOSALS. BIDDERS MUST TAKE INTO ACCOUNT THESE LIMITATIONS IN PREPARING THEIR RESPONSE TO THIS RFP.
B.1 DEFINITE ITEMS – If there is an award, these items will be awarded. The bid shall be evaluated to include the bid price for each definite item.
| ITEM |
| DESCRIPTION |
| BID PRICE |
| D-1 |
| PRODUCTION CONTROL GANTT BAR CHART, PROVIDE |
| $ |
| D-2 |
| TANK CLEANING SAFE FOR PERSONNEL – SAFE FOR HOTWORK |
| $ |
| D-3 |
| AFT DAMAGE CONTROL REPAIR LOCKER ESCAPE SCUTTLE |
| $ |
| D-4 |
| FWD DAMAGE CONTROL REPAIR LOCKER ESCAPE SCUTTLE |
| $ |
| D-5 |
| PILOT HOUSE TOP STRUCTURAL MODIFICATIONS |
| $ |
| D-6 |
| AFFF POWER & MCMS WIRING |
| D-7 |
| MULTI CABLE TRANSIT INSTALL AND CABLEWAY SUPPORT, FINAL |
| $ |
| D-8 |
| FUEL VALVE MOTOR ACTUATOR AND CONTROLLS INSTALL |
| $ |
| D-9 |
| OVERHEAD LIGHTING FIXTURE MODS |
DELETED FROM SPEC. DO NOT BID
| D-10 |
| TOILET/SHOWER AND STATEROOM COMPARTMENT STEP LIGHTS |
| $ |
| D-11 |
| SCIF & EXTERIOR COMMS POWER DISTRIBUTION INSTALL |
| $ |
| D-12 |
| HYDRA FREQUENCY REPROGRAMMING |
| D-13 |
| MPC ANNEXVENTILATION DUCT AND ELECTRICAL MODS |
| $ |
| D-14 |
| DEIONIZATION HELO WATER WASH INSTALL |
| D-15 |
| FUEL OIL TRANSFER PIPING AND MANIFOLD MODS |
| $ |
| D-16 |
| AFFF TO CMWD CROSS CONNECT PIPING INSTALL |
| $ |
| D-19 |
| STARBOARD BOAT DAVIT MODS |
| D-20 |
| FORWARD ASIST STOP MODS |
| D-22 |
| 03 LEVEL HANDRAIL/LIFE RAFT MODS |
| D-23 |
| DECK COVERING (INTERIOR POLYMERIC) RENEW |
| $ |
| D-24 |
| TWO-HIGH BERTH UNIT ADDITION TO STATEROOM 3-28-2-L |
| $ |
| D-25 |
| MISSION MODULE TO STATEROOM CONVERSION |
| $ |
| D-26 |
| CPO STATEROOM RIPOUT |
| D-27 |
| HF TRANSMITTER MECHANICAL & ELECTRICAL OUTFIT INSTALL |
| $ |
| D-28 |
| TEMPORARY SERVICES, DOCKSIDE, HOME PIER |
| $ |
TOTAL PRICE
B.2 OPTIONAL ITEMS – Optional Item (IF ANY) O-xx THROUGH O-xx may be awarded concurrent with Definite Items or when funds become available, but not later than 14 calendar days after commencement of the Definite Items, to maintain performance schedule. See Section H “Optional Items”.
| ITEM |
| DESCRIPTION |
| BID PRICE |
O-xx
B.2A COMPOSITE LABOR HOUR RATE APPLICABLE TO CONTRACT CHANGES (NON-FIRE WATCH)
The following labor hour rate shall be used in pricing all contract changes (except for the fire watch portion) in accordance with the clause of Section H entitled "COMPOSITE LABOR HOUR RATE FOR CONTRACT CHANGES."
Labor Hour Rate
Estimated Quantity**
Extended Amount
**NOTE: The estimated quantity and extended amount indicated above are for evaluation of bids only. The quoted rate will apply to all changes involving additional work under this contract regardless of the actual total hours required.
B.2B COMPOSITE LABOR HOUR RATE APPLICABLE TO CONTRACT CHANGES FOR FIRE WATCHES
The following labor hour rate shall be used in pricing the fire watch portion of all contract changes in accordance with the clause of Section H entitled "COMPOSITE LABOR HOUR RATE FOR CONTRACT CHANGES."
Labor Hour Rate
Estimated Quantity**
Extended Amount
**NOTE: The estimated quantity and extended amount indicated above are for evaluation of bids only. The quoted rate will apply to all changes involving additional work under this contract regardless of the actual total hours required.