REV 1 Summary of Changes.pdf

PDF 44 KB Posted

Attached to
Maintenance & Repair Period 1 on USCGC WAESCHE
Solicitation number
HSCG8510R610940
Issued by

About this file

REV 1 SUMMARY OF CHANGES

View the file

Other files

File Type Posted
AMEND 0004 TO SOL.doc DOC document
AMEND 0003 TO SOL.doc DOC document
W24193-006_RecC.pdf PDF
750-WMSL-582-501 Rev C.pdf PDF
REVISED SCHEDULE B FOR AMEND 0003.doc DOC document
USCGC WAESCHE_Maintenance and Repair 1_March_2010_Rev 1.pdf PDF
CAPTURE NET MODS.jpg JPG image
AMEND 0002 TO SOL.doc DOC document
AMEND 0001 TO SOL.doc DOC document
USCGC WAESCHE_Maintenance and Repair 1_March_2010_Rev 0.pdf PDF
FINAL WASCHE MR 1 SOLICITATION.doc DOC document
PRESOLICITATION NOTICE.doc DOC document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REV 1 Summary of Changes

General Requirements, Section 4.7: Updated Title of section and added Para 4.71.1 through Para 4.7.1.2.6

HOTWORK, (All Items Pertaining): Updated “Conduct all hotwork in accordance with MLCPAC Std Spec 074. All welds shall be continuous, 100% efficient welds.”

Item D-1: Entire Spec has been revised.

Item D-2, SCOPE: Deleted “AMR EMERGENCY EGRESS SCUTTLES”; Added “Two High Berth Unit Addition to Stateroom 2-38-3-L” and “Water Mist Tank 1-28-5-W”

Item D-2: Throughout spec added additional tank, Water Mist Tank 1-28-5-W

Item D-2, Para 4.1.2: Updated “… Coast Guard Inspector that the areas surrounding the open manholes are suitable protected in accordance with the general requirements.”

Item D-3, Para 3.1.2, Para 3.1.3.2, Para 3.1.4: Deleted

Item D-3, Para 3.1.5: Updated “… inspect and test all equipment that will be disturbed during the performance of this work IAW the general requirements.

Item D-3, Para 3.1.7: Updated “The contractor shall remove, modify, or protect all interferences to the work IAW the general requirements.”

Item D-3, Para 3.2.1: Updated and added Para 3.2.2 through Para 3.2.4.

Item D-3, Illustration 3: Deleted.

Item D-3, Figure 5: Updated.

Item D-3, Illustration 4: Deleted.

Item D-3, Para 3.4.4: Combined with Para 3.4.4.1 and updated “Perform a liquid film bubble emission leak test IAW the general requirements.”

Item D-3, Para 3.4.4.1.1 through Para 3.4.4.1.4, Para 3.5.1, Para 3.5.2, Para 3.5.6 through Para 3.5.9.1: Deleted

Item D-4, Para 3.4.5: Combined with Para 3.4.5.1 and updated “Perform a liquid film bubble emission leak test IAW the general requirements.”

Item D-4, Para 3.4.5.1.1 through Para 3.4.5.1.4: Deleted

Item D-4, Para 3.4.5.2: Updated “In the presence of Coast Guard Inspector, perform a water leakage test IAW the general requirements.

Item D-4, Para 3.4.5.2.1 through Para 3.4.5.2.5: Deleted

Item D-4, Section 3.5: Updated to match Item D-3’s Section 3.5 Restoration.

Item D-4, Section 3.6: Added section as “Documentation”

Item D-5, Para 3.1.1: Updated “All welding shall be done in accordance with the general requirements.”

Item D-5, Para 3.1.2: Deleted

Item D-5, Para 3.1.4: Updated “The Contractor shall remove, modify, or protect all intereferences IAW the general requirements.”

Item D-5, Para 3.1.6 through Para 3.1.7.2: Deleted

Item D-5, Para 3.2.4: Updated “Remove vacated stuffing tubes and weld insert plates on all holes in accordance with MIL-STD-1689A(SH), Fabrication, Welding and Inspection of Ships Structure, 11/23/1990.”

Item D-5, Para 3.2.5: Moved to Section 3.4 Restoration.

Item D-5, Section 3.2.6: Deleted

Item D-5, Para 3.3.2: Updated “All acceptance tests shall be performed IAW the general requirements.”

Item D-5, Para 3.3.5.1: Added paragraph

Item D-6, Government Furnished Property: Added GFE

Item D-6, Section 3 Note: Added “This work item has been accomplished on CGC BERTHOLF. A verification shipcheck of CGC BERTHOLF is recommended. A verification…..”

Item D-6, Para 3.1.2: Updated “In the presence of the Coast Guard Inspector, inspect and test all equipment any systems that will be disturbed IAW the general requirements.”

Item D-6, Para 3.1.5: Updated “The contractor shall remove, modify, or protect all interferences IAW the general requirements.”

Item D-6, Para 3.1.6.2: Deleted

Item D-6, Para 3.3.4.4: Updated

Item D-6, Figures: Numbering changed to all figures.

Item D-6, Para 3.3.5.4 through Para 3.3.5.6: Updated

Item D-6, Para 3.4.2 and Note for Section 3.5: Deleted.

Item D-6, Para 3.6.2: Updated “Any painted surfaces disturbed in conducting work required by this item shall be restored in accordance with the general requirements.”

Item D-6, Para 3.6.3: Updated “In company with the Contractor, the Coast Guard Inspector shall inspect and test all interferences affected by this item to verify proper operation IAW the general requirements.”

Item D-6, Section 3.7 to the end of work item: Deleted

Item D-7, Para 3.1.1: Updated “All welding shall be done in accordance with the general requirements.”

Item D-7, Para 3.1.2: Updated “In the presence of the Coast Guard Inspector, inspect and test all equipment any systems that will be disturbed IAW the general requirements.”

Item D-7, Para 3.1.4: Updated “The Contractor shall remove, modify, or protect all intereferences IAW the general requirements.”

Item D-7, Para 3.1.5: Deleted

Item D-7, Para 3.2.9.1 through Para 3.2.9.4: Deleted

Item D-7, Para 3.2.9.5: Updated.

Item D-7, Para 3.3.2: Updated “All acceptance tests shall be performed IAW the general requirements.”

Item D-7, Para 3.3.2.1: Updated “Prior to application of paint on the welds to be tested, in the presence of the Coast Guard Inspector, perform all weld inspections IAW the general requirements.”

Item D-7, Para 3.3.2.1.1, Para 3.3.2.1.2, Para 3.3.4 and Para 3.3.5: Deleted

Item D-7, Section 3.4: Added

Item D-8: Entire spec has been revised.

Item D-9: Spec has been descoped.

Item D-10, Scope: Deleted last sentence.

Item D-10, Para 3.1.1: Updated “In the presence of the Coast Guard Inspector, inspect and test all equipment any systems that will be disturbed IAW the general requirements.”

Item D-10, Para 3.1.3: Updated “The Contractor shall remove, modify, or protect all intereferences IAW the general requirements.”

Item D-10, Para 3.1.8.2: Deleted

Item D-14, Government Furnished Property: Added

Item D-15: Entire spec has been revised.

Item D-16, Scope: Updated “This cross connect will allow the forward AFFF system to supply fire fighting foam to the flight deck CMWD nozzles when the system is segregated.” Delete all of conjunction with except Install Power and MCMS PROFIBUS Cabling to the AFFF Flight Deck Sprinkling Control Valve (AFFF-V044) and Remote Control Stations.

Item D-16, 3 Requirements Note: Added last two sentences.

Item D-16, Para 3.1.3: Updated “In the presence of the Coast Guard Inspector, inspect and test all equipment any systems that will be disturbed IAW the general requirements.”

Item D-16, Para 3.1.4.1: Deleted

Item D-16, Para 3.1.6.2: Deleted

Item D-16, Para 3.2.6.1: Updated “Fire watch requirements shall be in accordance with the general requirements.

Item D-16, Para 3.2.6.2 and Para 3.2.6.3: Deleted

Item D-16, Para 3.3.2.1: Deleted last sentence.

Item D-16, Para 3.3.2.6: Deleted first sentence and added “The contractor shall use a hole saw capable of drilling out each nozzle. The contractor shall drill a 3 inch diameter hole in the AH-36 steel and a four inch diameter hole in the HSLA-80 steel.”

Item D-16, Para 3.3.2.11: Added “Note: Forward of nozzle S1, the contractor is authorized, upon approval of the COTR, to drill a second access hole in order to cap the piping.” And added Para “3.3.2.12 Nozzle P10 is located above the Ward. The overhead insulation of the Ward is Barium Sulfate Loaded Vinyl per ASC635002. The contractor is required to test the overhead insulation for led and provide the results to the COTR via CFR.”

Item D-16, Para 3.3.3.1: Added “All welding shall be done from above the flight deck. No welding shall be done from below the flight deck. The contractor shall fabricate an insert plate make a drawing for the insert plate.”

Item D-16, Para 3.4.1: Updated last sentence “The contractor shall show the proposed piping run to the Coast Guard Inspector for approval prior to the Coast Guard….”

Item D-16, Para 3.4.1.3: Added “Look up the details of the Tee and install per this work item.”

Item D-16, Para 3.4.1.5: Added “…. in the cross connect line after AFFF-V-044 in compartment 2-70-0- L, in a location approved by the Coast Guard Inspector.”

Item D-16, Para 3.4.2.4: Deleted

Item D-16, Para 3.7.5: Deleted

Item D-16, Para 3.8.2 amd Para 3.8.4: Updated

Item D-16, Section 3.9: Deleted

Item D-17, Para 3.1.5 through Para 3.1.11: Deleted

Item D-17, Para 3.4.1: Updated

Item D-17, Section 3.5 and Section 3.6: Deleted

Item D-17, Section 3.7: Updated.

Item D-17, Section 3.8: Deleted

Item D-17, Section 3.10: Updated

Item D-17, Section 4 and 5: Deleted

Item D-18, Para 3.1.4 through Para 3.1.7: Deleted

Item D-18, Section 3.2 and 3.3: Deleted

Item D-18, Para 3.6.2: Deleted

Item D-18, Section 3.7, Section 4 and Section 5: Deleted

Item D-19, Para 3.1.7, Para 3.2.2 and Para 3.4.3: Deleted

Item D-19, Para 3.7.2 through Para 3.7.6: Deleted

Item D-19, Para 3.8.1: Deleted

Item D-19, Section 4 and 5: Deleted

Item D-20, SCOPE: Updated

Item D-20, Para. 3.1.1: Added Note.

Item D-20, Para. 3.1.2: Updated “In the presence of the Coast Guard Inspector, inspect and test all equipment any systems that will be disturbed IAW the general requirements.”

Item D-20, Para. 3.1.4.1: Deleted

Item D-20, Para. 3.1.5: Updated “The Contractor shall remove, modify, or protect all interferences IAW the general requirements.”

Item D-20, Section 3.2: Updated Para 3.2.1 and Para 3.2.3. Deleted Para 3.2.3.1 through Para 3.2.3.3

Item D-20, Para. 3.6.1: Updated “The contractor shall provide redlines for the following drawings….”

Item D-21, Para. 3.1.4: Updated “The Contractor shall remove, modify, or protect all interferences IAW the general requirements.”

Item D-21, Para. 3.1.8.1 and Para 3.1.8.2: Deleted

Item D-21, Para. 3.2.1 through Para 3.2.1.4: Deleted

Item D-22, Para. 3.1.3 and Para 3.1.5: Updated

Item D-22, Para. 3.1.6: Deleted.

Item D-22, Para. 3.2.4 through Para 3.2.4.2: Moved to Section 3.3 Restore.

Item D-23, Table 3.1.A: Updated

Item D-23, Section 3.7: Deleted.

Item D-24: Entire spec has been revised.

Item D-25, Scope: Updated.

Item D-25, Para 3.1.8.1 and Para 3.1.8.2: Deleted.

Item D-25, Section 3.2: Added.

Item D-25, Para 3.4.7: Updated and deleted Para 3.4.7.1 through Para 3.4.7.1.4

Item D-26, Para 3.1.1 and Para 3.1.3: Updated.

Item D-26, Para 3.1.5.1 and Para 3.1.5.2: Deleted.