CGC_THETIS_Second_Set_of_Question_and_Answers_Amend_00001.doc

DOC document 31 KB Posted

Attached to
CGC THETIS DRYDOCK REPAIRS
Solicitation number
HSCG80-13-R-P45936
Issued by

About this file

CGC THETIS Second Set of Questions and Answers

View the file

Other files

File Type Posted
905-WMEC_588_10_5_-_C.pdf PDF
905-WMEC_588_10_2_-_C.pdf PDF
905-WMEC_154_2_1_-_B.tiff TIFF file
Amendment_A00003_THETIS.pdf PDF
905-WMEC_154_2_2_-_B.tiff TIFF file
905-WMEC_588_10_4_-_C.pdf PDF
CGC_THETIS_Spec_Rev-2.pdf PDF
905-WMEC_588_10_6_A_C.pdf PDF
905-WMEC_801_29_1_-_-.pdf PDF
905-WMEC_801_29_2_-_-.pdf PDF
905-WMEC_588_10_6_B_C.pdf PDF
Blank_Schedule_B_CGC_THETIS_Rev-2.xlsx XLSX spreadsheet
905-WMEC_588_2_2_-_H.pdf PDF
905-WMEC_588_10_1_-_C.pdf PDF
905-WMEC_588_2_1_-_H.pdf PDF
905-WMEC_588_10_3_-_C.pdf PDF
905-WMEC_801_29_3_-_-.pdf PDF
905-WMEC_588_10_7_-_C.pdf PDF
SF30_Amendment_A00002_THETIS.pdf PDF
RFP_THETIS_Feb_6_2013.pdf PDF
SF30_Amendment_THETIS.pdf PDF
THETIS_Spec_Rev-1.pdf PDF
Blank_Schedule_B_Rev-1.pdf PDF
CGC_THETIS_First_Set_of_Question_and_Answers_Amend_00001.docx DOCX document
Performance_Questionnaire_based_on_CPARS_Template.docx DOCX document
RFP_THETIS_Jan_17_2013.doc DOC document
Blank_Schedule_B_Rev-0_CGC_THETIS_.pdf PDF
CGC_THETIS_Rev-_Spec_18_Dec_12.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CGC THETIS Second Set of Question and Answers:

Question 1: SPECIFICATION ITEM NO.: Work Item 26 3.1.4 Dry Stores Tank Top, Repair

The work item states 3 SQ-FT of tank top in compartment 4-169-0-A is to be renewed. Paragraph 3.1.4 cannot be competitively priced as written.

How far aft of BHD 169 and how far outboard to Port or STBD of centerline is the insert to be centered? If the question cannot be answered, it is recommended that it is to be understood that no interference can be determined until after a repair need has been determined. Unless otherwise more precisely directed, it is mutually understood that no interference is included. If a mutually agreed understanding cannot be determined, what value is the contractor to place on paragraph 3.1.4?

ANSWER: The work item has been revised as shown on Rev 2 specifications.

Question 2: Work Item 28 paragraph 2, Hanger Superstructure Plating, Renew References not provided are as follows:

905 WMEC 588-002, Rev H, Flight Deck and Hanger Markings, A&D

905 WMEC 588-010, Rev C, Hanger A&D

905 WMEC 801-029, Rev -, Booklet of Gen Plans (USCGC THETIS WMEC 910)

905 WMEC 154-002, Rev B, Walkway 03 LVL and Hanger Top

It is requested the references be provided via e-mail.

Answer: Drawings will be provided.