Pages 2-62 of Solicitation

View the file

Other files

File Type Posted
Attachment 6b - Continuation Page - DD FORM 254 SECTION 13 .doc DOC document
Attachment 8b - Supplemental clarification of answers to questions under RFP HSCG44-10-R-TEDSSA.doc DOC document
FINAL REVISED TEDDS RFP(1).doc DOC document
Attachment 3-TEDDS_RateSchedule.doc DOC document
Attach9-C3CECOrg(FINAL).rtf RTF text file
Attachment 1 - FINALTEDDS PWS.docx DOCX document
Attachment 6-DD254(2).pdf PDF
Attach 2-TEDSS-Pricing Spreadsheet.xls XLS spreadsheet
Attachment 8 - TEDSS List of Questions and Answers.doc DOC document
TEDSS20-pdf.pdf PDF
FINAL TEDDS_RFP(1).doc DOC document
Attachment 5 - TEDSS-Past Performance Questionnaire.doc DOC document
Attachment 6 - DD254 TEDSS signed.pdf PDF
Attachment 4 - WageDet-05-2543.doc DOC document
Attachment 7 - Statement of Equivalent Rates for Federal Hires.doc DOC document
Attachment 3 - TEDDS CLIN Structure - Labor Category Descriptions.doc DOC document
Attachment 1 - TEDDS_PWS_10DEC10.docx DOCX document
Attachment 2 - TEDSS Pricing Spreadsheet.xls XLS spreadsheet
P00011 Solicitation.doc DOC document
P00010 Solicitation.doc DOC document
P00009 Solicitation.doc DOC document
P00008 Solicitation.doc DOC document
P00007 Solicitation.doc DOC document
Contractor Clarifications to Government Responses.doc DOC document
Attachment E Sept Revised.pdf PDF
Attachment C NEW DOL WD.pdf PDF
Attachment B Revised.pdf PDF
P00006 Solicitation.doc DOC document
TEDSS RFP P00006.pdf PDF
P00005 Solicitation.doc DOC document
P00004 Solicitation.doc DOC document
Contractor Questions and Govt Response.doc DOC document
TEDSS RFP Aug 2010.doc DOC document
C3CEN Standard Orientation Brief July2010 TEDSS.pdf PDF
P00003 Solicitation.doc DOC document
TEDSS Preproposal Conference Attendees List.doc DOC document
TEDSS Preproposal Conference Power Point RFP.ppt PPT presentation
P00002 Solicitation.doc DOC document
P00001 Solicitation.doc DOC document
Attachment E.pdf PDF
Attachment C DOL Wage Determination Virginia.txt TXT text file
Attachment A.xls XLS spreadsheet
Solicitation Page 1 of 62.pdf PDF
Attachment D.doc DOC document
Attachment B.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation HSCG44-10-R-TEDSSA

TEDSS RFP Document

FAR PART 12

PART A: SF1449:

SECTION B: SUPPLIES AND SERVICES

B.1 LABOR CATEGORIES AND LABOR RATES CONTRACT LINE ITEMS:

The Labor Categories and Labor Rates tables below represent all CLINS for labor rates. The hourly labor rates are inclusive of all contract cost, except for Other Direct Costs (ODCs) and travel. ODCs and travel cost will be incorporated into individual task orders that are issued under this contract.

B.1.A Base Period Labor Categories and Rates:

See Attachment A for a listing of all labor categories, labor rates, and activity descriptions

B.1.B Option Period 1 Labor Categories and Rates:

See Attachment A for a listing of all labor categories, labor rates, and activity description.

B.1.C Option Period 2 Labor Categories and Rates:

See Attachment A for a listing of all labor categories, labor rates, and activity description.

B.1.D Option Period 3 Labor Categories and Rates:

See Attachment A for a listing of all labor categories, labor rates, and activity description.

B.1.E Option Period 4 Labor Categories and Rates:

See Attachment A for a listing of all labor categories, labor rates, and activity description.

Note: The Labor Categories and Labor Rate Tables in Section B.1 represent all CLINS for labor rates (CLIN) for the IDIQ contract utilizing Firm-Fixed Price Labor Rates. The hourly labor rates proposed/awarded under this IDIQ contract, as shown in Bid Schedule Attachment A, are fully burdended/loaded and are inclusive of all profit, overhead and general/administrative cost. The Other Direct Costs, ODC and Travel,proposed/awarded general and administrative fee shown as a percentage of ODC and Travel on the Bid Schedule. Travel shall be reimbursed in accordance with the Federal Joint Regulation. The Government may order any combination of hours from Schedule B.1. Specific Labor, ODC and Travel will also be proposed/awarded at individual delivery order/task order level. The contractor will follow the order procedures contained in Section C, using the labor rates contained in Section B.1 schedule. Discounts of the labor rates are encouraged at the Task Order Level. The contractor will propose a level of effort inclusive of labor categories, labor rates, hourly rates and extended totals at the individual delivery order/task order level. Discounts off the hourly rates are encouraged at the delivery order/task order level.

ODC and Travel not to exceed amounts may set by the Government or proposed by the contractor at the individual task order level.

B.2 STATEMENT OF WORK.

The Contractor shall perform work as outlined in section D (IDIQ PWS), and detailed work performed under each Task Order (TO) issued.

This contract is being entered into pursuant to Section 8(a) of the Small Business Act. The NAICS Code for this procurement is 541519. The size standard is $25 Million.

B.3 PRICING

In pricing task orders, the Contractor shall use the applicable labor rates contained in Attachment A.

B.3.1 Contract Type

This is an Indefinite Delivery / Indefinite Quantity contract. The Contractor shall use the labor rates contained in Section B.1. Each Task Order Request for Proposal (RFP) shall identify the pricing mechanism deemed appropriate by the Government for that task order.

B.3.2 Fixed Price and Fixed Price Performance Based Task Orders

Under Fixed Price and Fixed Price Performance Based Task Orders the quantity of each item or labor category ordered shall be multiplied against the labor rates listed in Attachment A. The cumulative extended total of all items ordered (to include all labor and Other Direct Costs (ODC) if authorized by the government) shall define the fixed price for the Task Order, less any discounts.

Travel and ODC, if applicable, may be estimated for each Task Order. The payment schedule will be specified in each task order.

B.3.3 Time and Material Task Orders

For Time and Material-type Task Orders (T&M), the quantity of hours ordered from each labor category shall be specified as deliverable hours billable at the ceiling rates specified in Attachment A. Travel and ODC’s shall be estimated for each T&M order; no mark ups will be applied to Travel or Other Direct Costs (ODCs). The cumulative extended total of all labor categories ordered, plus travel and ODC, shall define the Task Order ceiling price that shall not be exceeded. The Government shall not reimburse the Contractor for costs incurred beyond the ceiling price, for hours not delivered, for hours delivered but in excess of the quantities ordered for a particular labor category, or for travel and ODC’s exceeding the ordered amount. Labor dollars shall not be used to pay for ODC’s, nor ODC’s dollars used to pay for labor, without a task order modification.

B.4 CONTRACT IDIQ MINIMUM AND MAXIMUM VALUE

The minimum and maximum values of this IDIQ contract are $100,000 and $250 Million respectively.

B.5 PERIOD OF PERFORMANCE:

The total period of performance is 60 months from the date of contract award if all option periods are exercised.

B.5.A Base Period of Performance CLINS 1001-1043:

The Base Period of Performance is 12 months from date of award (specific calendar dates will incorporated into the contract at the time of award.

B.5.B Option Period 1 Period of Performance CLINS 2001-2043:

Option Period 1 Period of Performance is 12 months from date of the base period ends (specific calendar dates will incorporated into the contract at the time of award.

B.5.C Option Period 2 Period of Performance CLINS 3001-3043:

Option Period 2 Period of Performance is 12 months from date that the first option period expires (specific calendar dates will incorporated into the contract at the time of award.

B.5.D Option Period 3 Period of Performance CLINS 4001-4043:

Option Period 3 Period of Performance is 12 months from date that the second option period expires (specific calendar dates will incorporated into the contract at the time of award.

B.5.D Option Period 4 Period of Performance CLINS 5001-5043:

Option Period 3 Period of Performance is 12 months from date that the fourth option period expires (specific calendar dates will incorporated into the contract at the time of award.

B.6 TASK ORDER COMPLETION:

All task orders issued under this IDIQ contract must be completed within two (2) years after the expiration of contract or the specified task order period of performance if a contract option is not exercised.

B.7 GOVERNMENT SITE RATES (FOR FIXED PRICE, FIXED PRICE PERFORMANCE BASE,

AND T&M TYPE TASK ORDERS)

When performing at Government Sites, the Government will provide only office space, furniture, office equipment and supplies, information technology, and telecommunications (data) and landline, if deemed necessary by the Contracting Officer. For Off-Site rates, the Government will not provide any equipment, supplies, information technology, and telecommunications (data), or landline, or any other type support.

B.7. PLACE OF PERFORMANCE

Performance may be at any Coast Guard facility within the United States and territories. The primary place of performance will be Portsmouth, Virginia, Alexandria, Virginia, and Martinsburg, West Virginia, and various locations on the West Coast of the United States including but not limited to Seattle, Oakland, San Diego and Petaluma. The actual performance location of each Task Order will be specified at the time that the Task Order is issued.

SECTION C: CONTRACT CLAUSES

C.1 FAR Clause 52.212-4 CONTRACT TERMS AND CONDITIONS - COMMERCIAL ITEMS

(MARCH 2009)

FAR Clause 52.212-4 is applicable to all Fixed Price and Fixed Price Performance Base Task Orders that are issued under this contract.

(a) Inspection /Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or re-performance of nonconforming services at no increase in contract price. If repair/replacement or re-performance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights (1) within a reasonable time after the defect was discovered or should have been discovered; and (2) before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g. use of the Government-wide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to the Contract Disputes Act of 1978, as amended (41 U.S.C. 601-613). Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized), to the address designated in the contract to receive invoices. An invoice must include--

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, contract line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic Funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer-Central Contractor Registration, or 52.232-34, Payment by Electronic Funds Transfer-Other Than Central Contractor Registration), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment.

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and OMB prompt payment regulations at 5 CFR part 1315.

(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212- 5(b) for the appropriate EFT clause.

(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected contract line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(6) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in Section 611 of the Contract Disputes Act of 1978 (Public Law 95-563), which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by

33.211 if—

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall immediately notify the Contracting Officer and request instructions for disposition of the overpayment.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law.

If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. 3701, et seq., Contract Work Hours and Safety Standards Act; 41 U.S.C. 51-58, Anti-Kickback Act of 1986; 41 U.S.C. 265 and 10 U.S.C. 2409 relating to whistleblower protections; Section 1553 of the American Recovery and Reinvestment Act of 2009 relating to whistleblower protections for contracts funded under that Act; and 49 U.S.C 40118, Fly American; 41 U.S.C. 423 relating to procurement integrity..

(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order: (1) the schedule of supplies/services; (2) the Assignments, Disputes, Payments, Invoice, Other Compliances, and Compliance with Laws Unique to Government Contracts paragraphs of this clause; (3) the clause at 52.212-5; (4) addenda to this solicitation or contract, including any license agreements for computer software;

(5) solicitation provisions if this is a solicitation; (6) other paragraphs of this clause; (7) the Standard Form 1449; (8) other documents, exhibits, and attachments; and (9) the specification.

(t) Central Contractor Registration (CCR).

(1) Unless exempted by an addendum to this contract, the Contractor is responsible during performance and through final payment of any contract for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government's reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(2) (i) If a Contractor has legally changed its business name, “doing business as” name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-ofname agreements in FAR subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to (A) change the name in the CCR database; (B) comply with the requirements of subpart 42.12; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (t)(2)(i) of this clause, or fails to perform the agreement at paragraph (t)(2)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.

(3) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor's CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of payment” paragraph of the EFT clause of this contract.

(4) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the internet at http://www.ccr.gov or by calling 1-888-227-2423 or 269-961- 5757.

C.1.1 FAR Clause 52.212-4 CONTRACT TERMS AND CONDITIONS - COMMERCIAL ITEMS

ALTERNATE 1 (OCTOBER 2008)

FAR Clause 52.212-4 ALTERNTE 1 is applicable to all Time and Material and Labor Task Orders issued under this contract.

(a) Inspection/Acceptance.

(1) The Government has the right to inspect and test all materials furnished and services performed under this contract, to the extent practicable at all places and times, including the period of performance, and in any event before acceptance. The Government may also inspect the plant or plants of the Contractor or any subcontractor engaged in contract performance. The Government will perform inspections and tests in a manner that will not unduly delay the work.

(2) If the Government performs inspection or tests on the premises of the Contractor or a subcontractor, the Contractor shall furnish and shall require subcontractors to furnish all reasonable facilities and assistance for the safe and convenient performance of these duties.

(3) Unless otherwise specified in the contract, the Government will accept or reject services and materials at the place of delivery as promptly as practicable after delivery, and they will be presumed accepted 60 days after the date of delivery, unless accepted earlier.

(4) At any time during contract performance, but not later than 6 months (or such other time as may be specified in the contract) after acceptance of the services or materials last delivered under this contract, the Government may require the Contractor to replace or correct services or materials that at time of delivery failed to meet contract requirements.

Except as otherwise specified in paragraph (a)(6) of this clause, the cost of replacement or correction shall be determined under paragraph (i) of this clause, but the “hourly rate” for labor hours incurred in the replacement or correction shall be reduced to exclude that portion of the rate attributable to profit. Unless otherwise specified below, the portion of the “hourly rate” attributable to profit shall be 10 percent. The Contractor shall not tender for acceptance materials and services required to be replaced or corrected without disclosing the former requirement for replacement or correction, and, when required, shall disclose the corrective action taken.

(5) (i) If the Contractor fails to proceed with reasonable promptness to perform required replacement or correction, and if the replacement or correction can be performed within the ceiling price (or the ceiling price as increased by the Government), the Government may--

(A) By contract or otherwise, perform the replacement or correction, charge to the Contractor any increased cost, or deduct such increased cost from any amounts paid or due under this contract; or

(B) Terminate this contract for cause.

(ii) Failure to agree to the amount of increased cost to be charged to the Contractor shall be a dispute under the Disputes clause of the contract.

(6) Notwithstanding paragraphs (a)(4) and (5) above, the Government may at any time require the Contractor to remedy by correction or replacement, without cost to the Government, any failure by the Contractor to comply with the requirements of this contract, if the failure is due to—

(i) Fraud, lack of good faith, or willful misconduct on the part of the Contractor's managerial personnel; or

(ii) The conduct of one or more of the Contractor's employees selected or retained by the Contractor after any of the Contractor's managerial personnel has reasonable grounds to believe that the employee is habitually careless or unqualified.

(7) This clause applies in the same manner and to the same extent to corrected or replacement materials or services as to materials and services originally delivered under this contract.

(8) The Contractor has no obligation or liability under this contract to correct or replace materials and services that at time of delivery do not meet contract requirements, except as provided in this clause or as may be otherwise specified in the contract.

(9) Unless otherwise specified in the contract, the Contractor's obligation to correct or replace Government-furnished property shall be governed by the clause pertaining to Government property.

(e) Definitions. (1) The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

As used in this clause--

(i) Direct materials means those materials that enter directly into the end product, or that are used or consumed directly in connection with the furnishing of the end product or service.

(ii) Hourly rate means the rate(s) prescribed in the contract for payment for labor that meets the labor category qualifications of a labor category specified in the contract that are--

(A) Performed by the contractor;

(B) Performed by the subcontractors; or

(C) Transferred between divisions, subsidiaries, or affiliates of the contractor under a common control.

(iii) Materials means--

(A) Direct materials, including supplies transferred between divisions, subsidiaries, or affiliates of the contractor under a common control;

(B) Subcontracts for supplies and incidental services for which there is not a labor category specified in the contract;

(C) Other direct costs (e.g., incidental services for which there is not a labor category specified in the contract, travel, computer usage charges, etc.);

(D) The following subcontracts for services which are specifically excluded from the hourly rate: [Insert any subcontracts for services to be excluded from the hourly rates prescribed in the schedule.]; and

(E) Indirect costs specifically provided for in this clause.

(iv) Subcontract means any contract, as defined in FAR Subpart 2.1, entered into with a subcontractor to furnish supplies or services for performance of the prime contract or a subcontract including transfers between divisions, subsidiaries, or affiliates of a contractor or subcontractor. It includes, but is not limited to, purchase orders, and changes and modifications to purchase orders.

(i) Payments. (1) Services accepted. Payment shall be made for services accepted by the Government that have been delivered to the delivery destination(s) set forth in this contract. The Government will pay the Contractor as follows upon the submission of commercial invoices approved by the Contracting Officer:

(i) Hourly rate.

(A) The amounts shall be computed by multiplying the appropriate hourly rates prescribed in the contract by the number of direct labor hours performed. Fractional parts of an hour shall be payable on a prorated basis.

(B) The rates shall be paid for all labor performed on the contract that meets the labor qualifications specified in the contract. Labor hours incurred to perform tasks for which labor qualifications were specified in the contract will not be paid to the extent the work is performed by individuals that do not meet the qualifications specified in the contract, unless specifically authorized by the Contracting Officer.

(C) Invoices may be submitted once each month (or at more frequent intervals, if approved by the Contracting Officer) to the Contracting Officer or the authorized representative.

(D) When requested by the Contracting Officer or the authorized representative, the Contractor shall substantiate invoices (including any subcontractor hours reimbursed at the hourly rate in the schedule) by evidence of actual payment, individual daily job timecards, records that verify the employees meet the qualifications for the labor categories specified in the contract, or other substantiation specified in the contract.

(E) Unless the Schedule prescribes otherwise, the hourly rates in the Schedule shall not be varied by virtue of the Contractor having performed work on an overtime basis.

(1) If no overtime rates are provided in the Schedule and the Contracting Officer approves overtime work in advance, overtime rates shall be negotiated.

(2) Failure to agree upon these overtime rates shall be treated as a dispute under the Disputes clause of this contract.

(3) If the Schedule provides rates for overtime, the premium portion of those rates will be reimbursable only to the extent the overtime is approved by the Contracting Officer.

(ii) Materials.

(A) If the Contractor furnishes materials that meet the definition of a commercial item at FAR 2.101, the price to be paid for such materials shall be the contractor's established catalog or market price, adjusted to reflect the--

(1) Quantities being acquired; and

(2) Any modifications necessary because of contract requirements.

(B) Except as provided for in paragraph (i)(1)(ii)(A) and (D)(2) of this clause, the Government will reimburse the Contractor the actual cost of materials (less any rebates, refunds, or discounts received by the contractor that are identifiable to the contract) provided the Contractor--

(1) Has made payments for materials in accordance with the terms and conditions of the agreement or invoice; or

(2) Makes these payments within 30 days of the submission of the Contractor's payment request to the Government and such payment is in accordance with the terms and conditions of the agreement or invoice.

(C) To the extent able, the Contractor shall--

(1) Obtain materials at the most advantageous prices available with due regard to securing prompt delivery of satisfactory materials; and

(2) Give credit to the Government for cash and trade discounts, rebates, scrap, commissions, and other amounts that are identifiable to the contract.

(D) Other Costs. Unless listed below, other direct and indirect costs will not be reimbursed.

(1) Other Direct Costs. The Government will reimburse the Contractor on the basis of actual cost for the following, provided such costs comply with the requirements in paragraph (i)(1)(ii)(B) of this clause: [Insert each element of other direct costs (e.g., travel, computer usage charges, etc. Insert “None” if no reimbursement for other direct costs will be provided. If this is an indefinite delivery contract, the Contracting Officer may insert “Each order must list separately the elements of other direct charge(s) for that order or, if no reimbursement for other direct costs will be provided, insert ‘None’.”]

(2) Indirect Costs (Material Handling, Subcontract Administration, etc.). The Government will reimburse the Contractor for indirect costs on a pro-rata basis over the period of contract performance at the following fixed price: [Insert a fixed amount for the indirect costs and payment schedule. Insert “$0" if no fixed price reimbursement for indirect costs will be provided. (If this is an indefinite delivery contract, the Contracting Officer may insert “Each order must list separately the fixed amount for the indirect costs and payment schedule or, if no reimbursement for indirect costs, insert ‘None’).”]

(2) Total cost. It is estimated that the total cost to the Government for the performance of this contract shall not exceed the ceiling price set forth in the Schedule and the Contractor agrees to use its best efforts to perform the work specified in the Schedule and all obligations under this contract within such ceiling price. If at any time the Contractor has reason to believe that the hourly rate payments and material costs that will accrue in performing this contract in the next succeeding 30 days, if added to all other payments and costs previously accrued, will exceed 85 percent of the ceiling price in the Schedule, the Contractor shall notify the Contracting Officer giving a revised estimate of the total price to the Government for performing this contract with supporting reasons and documentation. If at any time during the performance of this contract, the Contractor has reason to believe that the total price to the Government for performing this contract will be substantially greater or less than the then stated ceiling price, the Contractor shall so notify the Contracting Officer, giving a revised estimate of the total price for performing this contract, with supporting reasons and documentation. If at any time during performance of this contract, the Government has reason to believe that the work to be required in performing this contract will be substantially greater or less than the stated ceiling price, the Contracting Officer will so advise the Contractor, giving the then revised estimate of the total amount of effort to be required under the contract.

(3) Ceiling price. The Government will not be obligated to pay the Contractor any amount in excess of the ceiling price in the Schedule, and the Contractor shall not be obligated to continue performance if to do so would exceed the ceiling price set forth in the Schedule, unless and until the Contracting Officer notifies the Contractor in writing that the ceiling price has been increased and specifies in the notice a revised ceiling that shall constitute the ceiling price for performance under this contract.

When and to the extent that the ceiling price set forth in the Schedule has been increased, any hours expended and material costs incurred by the Contractor in excess of the ceiling price before the increase shall be allowable to the same extent as if the hours expended and material costs had been incurred after the increase in the ceiling price.

(4) Access to records. At any time before final payment under this contract, the Contracting Officer (or authorized representative) will have access to the following (access shall be limited to the listing below unless otherwise agreed to by the Contractor and the Contracting Officer):

(i) Records that verify that the employees whose time has been included in any invoice meet the qualifications for the labor categories specified in the contract;

(ii) For labor hours (including any subcontractor hours reimbursed at the hourly rate in the schedule), when timecards are required as substantiation for payment-

(A) The original timecards (paper-based or electronic);

(B) The Contractor's timekeeping procedures;

(C) Contractor records that show the distribution of labor between jobs or contracts; and

(D) Employees whose time has been included in any invoice for the purpose of verifying that these employees have worked the hours shown on the invoices.

(iii) For material and subcontract costs that are reimbursed on the basis of actual cost--

(A) Any invoices or subcontract agreements substantiating material costs;

and

(B) Any documents supporting payment of those invoices.

(5) Overpayments/Underpayments. Each payment previously made shall be subject to reduction to the extent of amounts, on preceding invoices, that are found by the Contracting Officer not to have been properly payable and shall also be subject to reduction for overpayments or to increase for underpayments. The Contractor shall promptly pay any such reduction within 30 days unless the parties agree otherwise.

The Government within 30 days will pay any such increases, unless the parties agree otherwise. The Contractor's payment will be made by check. If the Contractor becomes aware of a duplicate invoice payment or that the Government has otherwise overpaid on an invoice payment, the Contractor shall--

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected contract line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(6) (i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury, as provided in section 611 of the Contract Disputes Act of 1978 (Public Law 95-563), which is applicable to the period in which the amount becomes due, and then at the rate applicable for each six month period as established by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final Decisions. The Contracting Officer will issue a final decision as required by 33.211 if—

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt in a timely manner;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see FAR 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.

(viii) Upon receipt and approval of the invoice designated by the Contractor as the “completion invoice” and supporting documentation, and upon compliance by the Contractor with all terms of this contract, any outstanding balances will be paid within 30 days unless the parties agree otherwise. The completion invoice, and supporting documentation, shall be submitted by the Contractor as promptly as practicable following completion of the work under this contract, but in no event later than 1 year (or such longer period as the Contracting Officer may approve in writing) from the date of completion.

(7) Notwithstanding paragraphs (a)(4) and (5) above, the Government may at any time require the contractor to remedy by correction or replacement, without cost to the Government, any failure by the Contractor to comply with the requirements of this contract, if the failure is due to—

(i) Fraud, lack of good faith, or willful misconduct on the part of the Contractor's managerial personnel; or

(ii) The conduct of one or more of the Contractor's employees selected or retained by the Contractor after any of the Contractor's managerial personnel has reasonable grounds to believe that the employee is habitually careless or unqualified.

(8) This clause applies in the same manner and to the same extent to corrected or replacement materials or services as to materials and services originally delivered under this contract.

(9) The Contractor has no obligation or liability under this contract to correct or replace materials and services that at time of delivery do not meet contract requirements, except as provided in this clause or as may be otherwise specified in the contract.

(10) Unless otherwise specified in the contract, the Contractor's obligation to correct or replace Government-furnished property shall be governed by the clause pertaining to Government property.

(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid an amount for direct labor hours (as defined in the Schedule of the contract) determined by multiplying the number of direct labor hours expended before the effective date of termination by the hourly rate(s) in the contract, less any hourly rate payments already made to the Contractor plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system that have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred that reasonably could have been avoided.

C.2 Addendum to FAR Clause 52.252-2

C.2.1 Clauses Incorporated by Reference (Feb 1998)

In addition to other parts of Section C, this contract incorporates one or more clauses, shown in the table below, by reference, with the same force and effect as if they were given in full text. The full text of a clause can be accessed electronically at: http://www.acqnet.gov/far.

FAR Clause Number FAR Clause Title Date 52.203-5 Covenant Against Contingent Fees APR 1984 52.203-6 Restrictions on Subcontractor Sales to the Government

Alternate I

OCT 1995

52.203-7 Anti-Kickback Procedures JUL 1995 52.204-2 Security Requirements AUG 1996 52.204-4 Printed or Copied Double Sided on Recycle Paper AUG 2000 52.204-7 Central Contractor Registration APR 2008 52.204-9 Personal Identity Verification of Contractor Personnel SEP 2007 52.209-6 Protecting the Government’s Interest when

Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment

SEPT 2006

52.213-1 Fast Pay Procedures MAY 2006 52-216-22 Indefinite Quantity OCT 1995 52-216-27 Single or Multiple Award OCT 1995 52.227-14 Rights In Data General DEC 2007 52.227-14 Rights In Data General Alternate I DEC 2007 52.227-14 Rights In Data General Alternate II DEC 2007 52.227-14 Rights In Data General Alternate III DEC 2007 52.227-14 Rights In Data General Alternate IV DEC 2007 52.227-14 Rights In Data General Alternate V DEC 2007

52.227.15 Representation of Limited Data Rights and Restricted

Computer Software

DEC 2007

52.227-16 Additional Data Rights JUN 1987 52.227-18 Rights In Data – Existing Works DEC 2007 52.227-19 Commercial Computer Software License DEC 2007 52.227-23 Rights to Proposal Data (Technical) JUN 1987 52.227-17 Rights in Data – Special Works DEC 2007 52.228-5 Insurance-Work On a Government Installation JAN 1997 http://www.acqnet.gov/far

52-228-7 Insurance-Liability to Third Persons MAR 1996 52.224-1 Privacy Act Notification APR 1984 52.224-2 Privacy Act APR 1984 52.237-2 Protection of Government Buildings, Equipment,and

Vegetation

(APR 1984)

52.237-3 Continuity of Services JAN 1991 52.245-1 Government Property JUN 2007 52.247-34 F.O.B Destination NOV 1991

C.2.2 FAR 52.216-18 Ordering (OCT 1995)

a. Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from date of award through 60 months from the date of award (Dates will be established at the time of contract award)

b. All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.

c. If mailed, a delivery order or task order is considered “issued” when the Government deposits the order in the mail. Orders may be issued orally, by facsimile, or by electronic commerce methods only if authorized in the Schedule.

C.2.3 FAR 52.217-8 Option to Extend Services (Nov 1999)

The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months.

The Contracting Officer may exercise the option by written notice to the Contractor within 30 days from the date the contract expires.

C.2.4 FAR 52.217-9 Option to Extend the Term of the Contract (MAR 2000)

a) The Government may extend the term of this contract by written notice to the Contractor within 30; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 30 days before the contract expires. The preliminary notice does not commit the Government to an extension.

b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 60 months.

C.2.5 FAR 52.219-18 Notification of Competition Limited to Eligible 8(a) Concerns (June 2003)

a) Offers are solicited only from small business concerns expressly certified by the Small

Business Administration (SBA) for participation in the SBA’s 8(a) Program and which meet the following criteria at the time of submission of offer—

1) The…