The purpose of this amendment is to update Solicitation HQ0276-17-R-0003 to remove reference to the MAP REV B in Clause 52.246-11, Higher-Level Contract Quality Requirement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q-A_Matrix_05082018_Q33_response.xlsx | XLSX spreadsheet | |
| HQ0276-17-R-0003_Solicitation_05082018_page_11rev.docx | DOCX document | |
| AAMTDC_OS__Industry_Day_slides_MASTER_10_APR_18.pptx | PPTX presentation | |
| HQ0276-17-R-0003_Solicitation_04172018.docx | DOCX document | |
| Q-A_Matrix_04162018.xlsx | XLSX spreadsheet | |
| Q-A_Matrix_04052018.xlsx | XLSX spreadsheet | |
| Q-A_Matrix_03212018.pdf | ||
| VIEWNet_Application_instructions.pdf | ||
| Q-A_Matrix.xlsx | XLSX spreadsheet | |
| Industry_Day_Site_Visit_Registration_Form_03132018.docx | DOCX document | |
| HQ0276-17-R-0003_Solicitation_03132018.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HQ027617R0003
Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lot |
AAMDTC Weapons System O&S
CPFF
Operations and Maintenance Support for the AAMDTC at PMRF Level of Effort See Statement of Work Unit of Issue is lot for solicitation purposes but will be updated to hours upon award FOB: Destination
ESTIMATED COST
FIXED FEE
TOTAL EST COST + FEE
FSC CD: J012
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lot |
Travel in Support of CLIN 0001
COST
Travel for Operations and Maintenance Support for the AAMDTC at PMRF This is a COST only CLIN See Statement of Work
ESTIMATED COST
FSC CD: V999
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Data for CLINs 0001 and 0002
COST
Data for Operations and Maintenance Support for the AAMDTC at PMRF Contractor shall submit all data and reports as identified in the Contract, the Statement of Work and the Contract Data Requirements List (CDRLs) DD Forms 1423 This is NOT a Priced CLIN.
ESTIMATED COST
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lot |
| OPTION |
| AAMDTC Weapons System O&S |
CPFF
Operations and Maintenance Support for the AAMDTC at PMRF Level of Effort See Statement of Work
ESTIMATED COST
FIXED FEE
TOTAL EST COST + FEE
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lot |
| OPTION |
| Travel in Support of CLIN 0004 |
COST
Travel for Operations and Maintenance Support for the AAMDTC at PMRF This is a COST only CLIN See Statement of Work
ESTIMATED COST
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| OPTION |
| Data for CLINs 0004 and 0005 |
COST
Data for Operations and Maintenance Support for the AAMDTC at PMRF Contractor shall submit all data and reports as identified in the Contract, the Statement of Work and the Contract Data Requirements List (CDRLs) DD Forms 1423 This is NOT a Priced CLIN.
ESTIMATED COST
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lot |
| OPTION |
| AAMDTC Weapons System O&S |
CPFF
Operations and Maintenance Support for the AAMDTC at PMRF Level of Effort See Statement of Work
ESTIMATED COST
FIXED FEE
TOTAL EST COST + FEE
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lot |
| OPTION |
| Travel in Support of CLIN 0007 |
COST
Travel for Operations and Maintenance Support for the AAMDTC at PMRF This is a COST only CLIN See Statement of Work
ESTIMATED COST
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| OPTION |
| Data for CLINs 0007 and 0008 |
COST
Data for Operations and Maintenance Support for the AAMDTC at PMRF Contractor shall submit all data and reports as identified in the Contract, the Statement of Work and the Contract Data Requirements List (CDRLs) DD Forms 1423 This is NOT a Priced CLIN.
ESTIMATED COST
Section C - Descriptions and Specifications
CONTRACTOR MANPOWER REPORTING
Enterprise-wide Contractor Manpower Reporting Application (eCMRA) In accordance with United States Code, Title 10, Section 2330a (10 USC 2330a), the contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Missile Defense Agency via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil Beginning January 1, 2013 reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported at any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk at http://www.ecmra.mil
CLAUSES INCORPORATED BY FULL TEXT
C-01 SCOPE OF WORK (MAY 2005)
The Contractor shall perform the work specified in the Statement of Objectives/ Statement of Work (SOO/SOW) or other Attachments and Exhibits in Section J of this contract. The Contractor shall provide all necessary materials, labor, equipment and facilities incidental to the performance of this requirement.
Section D - Packaging and Marking
D-01 PACKAGING AND MARKING OF TECHNICAL DATA (APR 2009)
Technical data items shall be preserved, packaged, packed, and marked in accordance with the best commercial practices to meet the packaging requirements of the carrier and insure safe delivery at destination. Classified reports, data and documentation shall be prepared for shipment in accordance with the current National Industrial Security Program Operating Manual (NISPOM), DOD 5220.22-M.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
| CLIN |
| INSPECT AT |
| INSPECT BY |
| ACCEPT AT |
| ACCEPT BY |
| 0001 |
| Destination |
| Government |
| Destination |
| Government |
| 0002 |
| Destination |
| Government |
| Destination |
| Government |
| 0003 |
| N/A |
| N/A |
| N/A |
| Government |
| 0004 |
| Destination |
| Government |
| Destination |
| Government |
| 0005 |
| Destination |
| Government |
| Destination |
| Government |
| 0006 |
| N/A |
| N/A |
| N/A |
| Government |
| 0007 |
| Destination |
| Government |
| Destination |
| Government |
| 0008 |
| Destination |
| Government |
| Destination |
| Government |
| 0009 |
| N/A |
| N/A |
| N/A |
| Government |
CLAUSES INCORPORATED BY REFERENCE
| 52.246-5 |
| Inspection Of Services Cost-Reimbursement |
| APR 1984 |
| 52.246-15 |
| Certificate of Conformance |
| APR 1984 |
52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)
(a) The Contractor shall comply with the higher-level quality standard(s) listed below.
| Title | Number | Date | |
| Quality Management Systems | AS 9100 Rev C | Jan 2009 |
Requirements for Aviation, Space, And Defense Organizations
(b) The Contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts, in--
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require--
(i) Control of such things as design, work operations, in-process control, testing, and inspection; or
(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.
(End of clause)
Section F - Deliveries or Performance
DELIVERY INFORMATION
| CLIN |
| DELIVERY DATE |
| QUANTITY |
| SHIP TO ADDRESS |
| DODAAC / CAGE |
| 0001 |
| POP 14-MAR-2018 TO |
13-MAR-2021
| N/A |
| N/A |
| 0002 |
| 3 yrs. ADC |
| 1 |
| N/A |
| 0003 |
| N/A |
| N/A |
| N/A |
| N/A |
| 0004 |
| POP 14-MAR-2021 TO |
13-MAR-2022
| N/A |
| N/A |
| 0005 |
| 1 yr. AOE |
| 1 |
| N/A |
| 0006 |
| N/A |
| N/A |
| N/A |
| N/A |
| 0007 |
| 1 yr. AOE |
| 1 |
| N/A |
| 0008 |
| POP 14-MAR-2022 TO |
13-MAR-2023
| N/A |
| N/A |
| 0009 |
| N/A |
| N/A |
| N/A |
| N/A |
| 52.242-15 Alt I |
| Stop-Work Order (Aug 1989) - Alternate I |
| APR 1984 |
| 52.247-55 |
| F.O.B. Point For Delivery Of Government-Furnished Property |
| JUN 2003 |
| 252.247-7023 |
| Transportation of Supplies by Sea |
| APR 2014 |
Section G - Contract Administration Data
| 252.204-0004 |
| Line Item Specific: by Fiscal Year |
| SEP 2009 |
| 252.204-7002 |
| Payment For Subline Items Not Separately Priced |
| DEC 1991 |
| 252.204-7006 |
| Billing Instructions |
| OCT 2005 |
| 252.232-7003 |
| Electronic Submission of Payment Requests and Receiving Reports |
| JUN 2012 |
PGI 204.7108 Payment instructions
The payment office shall allocate and record the amounts paid to the accounting classification citations in the contract based on the type of payment request submitted (see DFARS 252.232-7006) and the type of effort using the table found at https://www.acq.osd.mil/dpap/dars/pgi/pgi_htm/current/PGI204_71.htm#payment_instructions.
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause--
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
Combo
(Contracting Officer: Insert applicable document type(s). Note: If a “Combo” document type is identified but not supportable by the Contractor's business systems, an “Invoice” (stand-alone) and “Receiving Report” (stand-alone) document type may be used instead.)
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
N/A
(Contracting Officer: Insert inspection and acceptance locations or “Not applicable”.)
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table* Field Name in WAWF Data to be entered in WAWF
| Pay Official DoDAAC | ____ | ||
| Issue By DoDAAC | HQ0276 | ||
| Admin DoDAAC | ____ | ||
| Inspect By DoDAAC | ____ | ||
| Ship To Code | ____ | ||
| Ship From Code | ____ | ||
| Mark For Code | ____ | ||
| Service Approver (DoDAAC) | ____ | ||
| Service Acceptor (DoDAAC) | ____ | ||
| Accept at Other DoDAAC | ____ | ||
| LPO DoDAAC | ____ | ||
| DCAA Auditor DoDAAC | ____ | ||
| Other DoDAAC(s) | ____ |
(*Contracting Officer: Insert applicable DoDAAC information or “See schedule” if multiple ship to/acceptance locations apply, or “Not applicable.”)
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
rodney.moye@mda.mil
(Contracting Officer: Insert applicable email addresses or “Not applicable.”)
(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
MDA e-Business Service Desk ebiz@mda.mil
(256) 450-1776
(Contracting Officer: Insert applicable information or “Not applicable.”)
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
G-01 CONTRACT ADMINISTRATION (MAY 2012)
Notwithstanding the Contractor’s responsibility for total management during the performance of this contract, the administration of the contract will require maximum coordination between the Government and the Contractor. The following individuals will be the Government points of contact during the performance of this contract:
a. CONTRACTING OFFICERS
All contract administration will be effected by the Procuring Contracting Officer (PCO) or designated Administrative Contracting Officer (ACO). Communication pertaining to the contract administration should be addressed to the Contracting Officer. Contract administration functions (see FAR 42.302 and DFARS 242.302) are assigned to the cognizant contract administration office. No changes, deviations, or waivers shall be effective without a modification of the contract executed by the Contracting Officer or his duly authorized representative authorizing such changes, deviations, or waivers.
The point of contact for all contractual matters is:
Name: Denise Lamb Organizational Code: MDA/DACW Telephone Number: (540) 663-7748 E-Mail Address: denise.lamb@mda.mil
b. CONTRACTING OFFICER’S REPRESENTATIVE/CONTRACTING OFFICER’S TECHNICAL REPRESENTATIVE
Neither the Contracting Officer’s Representative (COR) nor the Contracting Officer’s Technical Representative (COTR) is authorized to change any of the terms and conditions of the contract. The Contractor is advised that only the Contracting Officer can change or modify the contract terms or take any other action which obligates the Government. Then, such action must be set forth in a formal modification to the contract. The authority of the COR and the COTR is strictly limited to him/her, without redelegation, to the specific duties set forth in his/her letter of appointment, a copy of which is furnished to the Contractor. Contractors who rely on direction from other than the Contracting Officer, a COR or a COTR acting outside the strict limits of his/her responsibilities as set forth in his/her letter of appointment do so at their own risk and expense. Such actions do not bind the Government contractually. Any contractual questions shall be directed to the Contracting Officer.
The COR under this contract is:
To be included at contract award
The COTR under this contract is:
To be included at contract award
c. CONTRACTING OFFICIAL FOR eSRS
FAR 52.219-9, Small Business Subcontracting Plan requires the use of the Electronic Subcontracting Reporting System (eSRS) for subcontract reporting. The contracting official for eSRS under this contract is:
Name: Denise Lamb Organizational Code: MDA/DACW Telephone Number: (540) 663-7748 E-Mail Address: denise.lamb@mda.mil
For detailed information regarding eSRS visit http://www.acq.osd.mil/dpap/pdi/eb/index.html.
G-06 ALLOTMENT OF FUNDS (MAY 2005)
Pursuant to FAR 52.232-22, “Limitation of Funds,” the total amount of funds presently available for payment and allotted to this contract (which covers all items, including fee payable), and the estimated period of performance said funds cover, are as follow:
| CLIN 0001: | $TBD | |
| Estimated funds exhaustion date: | Insert Date | |
| CLIN 0002: | $TBD | |
| Estimated funds exhaustion date: | Insert Date |
G-08 PAYMENT OF FIXED FEE (ORDERING – LEVEL OF EFFORT) (JUN 2012)
The Government will make payments to the Contractor when requested as work progresses in accordance with Federal Acquisition Regulation (FAR) 52.216-7. The Contractor shall invoice the fee separately and submit such invoices to the MDA Contracting Officer's Representative (COR) for verification of the percentage of Labor Hours performed for the billing period. For this contract a Labor Hour is defined as actual PRIME AND SUBCONTRACTOR (INCLUDING CONSULTANTS) work hours exclusive of vacation, holiday, sick leave and other absences. Each invoice for Labor Hours shall contain a statement by the Contractor as to the cumulative percentage of Labor Hours invoiced. Each invoice for fee shall contain a statement by the Contractor as to the cumulative percentage of fee invoiced. Fee shall be payable, subject to other provisions of FAR 52.216-8, “Fixed Fee,” in amounts commensurate with the percentage of work performed. In no case shall the cumulative amount of the fee invoiced, when expressed as a percentage of the total fixed fee for the applicable CLIN, exceed the cumulative percentage of Labor Hours performed for that CLIN (as verified by the MDA COR) at the end of the billing period.
G-10 SEGREGATION OF COSTS (MAY 2005)
For CLIN(s) 0001 and 0002, and their respective Option CLINs, vouchers shall contain actual hours and costs by cost element (cost elements shall be at the lowest level of identification/ discrimination consistent with the Contractor's cost accounting system) and overall cumulative summaries of all work vouchered to date.
Section H - Special Contract Requirements
| 52.252-4 |
| Alterations in Contract |
| APR 1984 |
| 52.253-1 |
| Computer Generated Forms |
| JAN 1991 |
| 252.201-7000 |
| Contracting Officer's Representative |
| DEC 1991 |
| 252.203-7000 |
| Requirements Relating to Compensation of Former DoD Officials |
| SEP 2011 |
H-01 LEVEL OF EFFORT (LOE) OR COMPLETION ORDERS – FEE DETERMINATION (JUN 2012)
a. In the performance of LOE-type Task Orders issued pursuant to Special Provision, “TASK ORDERS,”, the Contractor shall provide Labor Hours level of effort as set forth in Section B above within the time period as set forth in Section F hereof.
b. Labor Hours are defined as actual PRIME AND SUBCONTRACTOR (INCLUDING CONSULTANTS) work hours exclusive of vacation, holiday, sick leave and other absences.
c. It is understood and agreed that the Contractor may, without notice to the Government, increase or decrease the approved number of Labor Hours for each labor category by no more than 10% to the extent that the ceiling price and maximum Labor Hours for the Task Order are not exceeded. If for any labor category the Labor Hours delivered are greater than 110% of the Labor Hours specified for that labor category in the Task Order, then the Labor Hours in excess of 110% for that labor category are non-fee bearing. The Contracting Officer shall reduce the fixed fee of the Task Order by an amount equal to the fee per hour for each non-fee bearing hour. The computed fee per hour for this Task Order is $TBD, which represents the fixed fee divided by the total Labor Hours.
d. In accordance with FAR 16.306(d)(2), entitlement to the total fixed fee is subject to certification by the contractor to the Contracting Officer that he has exerted the total Labor Hours level of effort, has provided the reports called for, and the effort performed and reports provided are considered satisfactory by the Government.
e. The contractor may include in provisional vouchers fixed fee based on the percentage of level of effort hours exerted to the total level of effort hours stipulated in Section B, subject to the withholding reserve of the contract clause titled "Fixed Fee."
f. Nothing in this provision shall be construed to constitute authorization for work not in accordance with the LIMITATION OF FUNDS provision of the contract.
OR
a. For completion task orders, the fixed fee shall be prorated based on the percentage of work completed. If, at the end of each task order period of performance, the Contractor has not completed the task, the fee may be reduced to reconcile the fee entitlement. No additional fee shall be paid on any cost overrun.
b. Nothing in this provision shall be construed to constitute authorization for work not in accordance with the “LIMITATION OF FUNDS” provision of the contract. In addition, nothing in this provision shall be construed to diminish the rights of the parties pursuant to the “LIMITATION OF FUNDS” provision of this contract. Nothing in this provision shall be construed to authorize the Contractor to start work under any task order issued under this contract without authorization from the Contracting Officer.
H-05 AUTHORIZED TRAVEL AND TRAVEL COSTS AS SPECIFIED UNDER A TRAVEL CLIN (MAR 2014)
a. All contractor travel that is directly billed under this contract as a specific travel CLIN must be authorized in writing by the Contracting Officer’s Representative (COR) and/or by the Procuring Contracting Officer (PCO). Travel is authorized when the COR and/or PCO approve the MDA Form 110. The Government will not reimburse travel costs for unauthorized travel.
b. Travel (non-local).
(1) All contractor travel (non-local) that is directly billed under this contract as a specific travel CLIN must be approved in writing by the COR and/or by PCO using MDA Form 110.
(2) Approval should be obtained in advance whenever possible. In the event mission requirements don’t allow sufficient time for advance approval, the PCO may provide post-travel approval. In those cases, the PCO will describe the extenuating circumstances in the remarks section of the MDA Form 110.
OR
(2) All contractor travel (non-local) shall be approved in advance.
c. Extended Commuting Travel.
(1) Extended Commuting Travel is travel that occurs regularly in the performance of this contract where an individual or individuals travel back and forth from their normal place, or city of employment to another location or locations over a 30 day (or longer) period.
(2) Extended commuting travel may be authorized for up to 90 days at a time and must be authorized in advance.
(3) All extended commuting travel under this contract must be approved by the COR and by the PCO using MDA Form 110. Extended commuting travel under this contract will be authorized only after review and government acceptance of contractor documentation showing that extended commuting travel is the most effective means of fulfilling the government’s requirements – cost and other factors considered.
H-06 INSURANCE (Apr 2009)
In accordance with FAR Part 28.307-2, Liability, the Contractor shall maintain the types of insurance and coverage listed below:
TYPES OF INSURANCE MINIMUM AMOUNT
| Workmen's Compensation and all occupational disease | As required by Federal and State law |
| Employer's Liability including all occupational disease | $100,000 per accident |
when not covered by Workmen's Compensation above
General Liability (Comprehensive) Bodily Injury $500,000 per occurrence
Automobile Liability (Comprehensive)
| Bodily Injury per person | $200,000 |
| Bodily Injury per accident | $500,000 |
| Property Damage per accident | $ 20,000 |
H-08 PUBLIC RELEASE OF INFORMATION (Jun 2013)
a. The policies and procedures outlined herein apply to information submitted by the Contractor and his subcontractors for approval for public release. Prior to public release, all information must be cleared as shown in the “National Industrial Security Program Operations Manual” (DoD 5220.22-M). At a minimum, these materials may be technical papers, presentations, articles for publication and speeches or mass media material, such as press releases, photographs, fact sheets, advertising, posters, compact discs, videos, etc.
b. All materials which relate to the work performed by the contractor under this contract must be submitted to MDA for review and approval prior to release to the public. Subcontractor public information materials must be submitted for approval through the prime contractor to MDA.
c. Upon request, the Contracting Officer’s Representative (COR) will provide the contractor the MDA Form 003, “Security and Policy Review” or any superseding MDA form. The contractor must complete Sections A-C and E-H of the Form 003 (or comply with the instructions of any superseding form) and submit it to the COR with the materials to be cleared. If the information was previously cleared, provide the Public Release Case Number, if available, and a copy of the previous document highlighting the updated information.
d. The contractor must submit the following to the COR at least 60 days in advance of the proposed release date:
| (1) the completed Form 003 and one (1) electronic copy of the material to be reviewed. File size must not exceed 25MB; and, |
| (2) a written statement, including: |
| (a) to whom the material is to be released; |
| (b) the desired date for public release; |
| (c) a statement that the material has been reviewed and approved by officials of the contractor or the subcontractor, for public release; and, |
| (d) the contract number. |
e. The items submitted must be complete. Photographs must have captions.
f. Outlines, rough drafts, marked-up copy (with handwritten notes), incorrect distribution statements, For Official Use Only (FOUO) information, export controlled, or International Traffic in Arms Regulations ( ITAR) information will not be accepted or cleared.
g. Abstracts or abbreviated materials may be submitted if the intent is to determine the feasibility of going further in preparing a complete paper for clearance. However, clearance of abstracts or abbreviated materials does not satisfy the requirement for clearance of the entire paper.
h. The MDA Director of Public Affairs (MDA/PA) is responsible for coordinating the public release review. MDA/PA will work directly with the COR if there are questions or concerns regarding submissions. MDA/PA will not work with contractors who have not gone through their COR.
i. The COR will notify the contractor of the agency’s final decision regarding the status of the request.
j. Once information has been cleared for public release, it is in the public domain and must always be used in its originally cleared context and format. Information previously cleared for public release but containing new, modified or further developed information must be submitted again for public release following the steps outlined in items a. through h. above.
H-09 ORGANIZATIONAL CONFLICT OF INTEREST (Jun 2012)
a. Purpose: The primary purpose of this clause is to aid in ensuring that:
(1) the Contractor's objectivity and judgment are not biased because of its present or planned interests which relate to work under this contract;
(2) the Contractor does not obtain unfair competitive advantage by virtue of its access to non-public information regarding the Government's program plans and actual or anticipated resources; and
(3) the Contractor does not obtain unfair competitive advantage by virtue of its access to proprietary information belonging to others.
b. Scope: Organizational Conflict of Interest (OCI) rules, procedures and responsibilities as described in FAR Subpart 9.5 shall be applicable to this contract and any resulting subcontracts.
(1) The general rules in FAR 9.505-1 through 9.505-4 and the restrictions described herein shall apply to performance or participation by the Contractor and any of its affiliates or their successors-in-interest (hereinafter collectively referred to as "Contractor") in the activities covered by this contract as prime Contractor, subcontractor, co-sponsor, joint venturer, consultant, or in any similar capacity.
(2) The Missile Defense Agency’s OCI policy is in Attachment X of this contract.
c. Access to and Use of Nonpublic Information: If the Contractor, in performance of this contract, obtains access to nonpublic information such as plans, policies, reports, studies, financial plans, or data which has not been released or otherwise made available to the public, the Contractor agrees that without prior written approval of the Contracting Officer, it shall not:
(1) use such information for any private purpose;
(2) release such information.
d. Access to and Protection of Proprietary Information: The Contractor agrees to exercise diligent effort to protect proprietary information from misuse or unauthorized disclosure in accordance with the provisions of FAR 9.505-4. The Contractor may be required to enter into a written non-disclosure agreement with the third party asserting proprietary restrictions.
e. Subcontracts: The Contractor shall include this clause in consulting agreements, teaming agreements, subcontracts, or other arrangements for provision of services or supplies of any tier. The terms "contract", "Contractor", and "Contracting Officer" shall be appropriately modified to preserve the Government's rights.
f. Representations and Disclosures:
(1) The Contractor represents that it has disclosed to the Contracting Officer, prior to award, all facts relevant to the existence or potential existence of organizational conflicts of interest as that term is used in FAR Subpart 9.5. To facilitate disclosure and Contracting Officer approval, the Contractor shall complete an OCI Analysis/Disclosure Form for each MDA, Ballistic Missile Defense (BMD), and BMD-related contract or subcontract (form shall be requested from the Procuring Contracting Officer).
(2) The Contractor represents that if it discovers an organizational conflict of interest or potential conflict of interest after award, a prompt and full disclosure shall be made in writing to the Contracting Officer. This disclosure shall include a description of the action the Contractor has taken or proposes to take in order to avoid or mitigate such conflicts.
g. Remedies and Waiver:
(1) For breach of any of the above restrictions or for non-disclosure or misrepresentation of any relevant facts required to be disclosed concerning this contract, the Government may: terminate this contract for default; disqualify the Contractor from subsequent related contractual efforts if necessary to neutralize a resulting organizational conflict of interest; and pursue such other remedies as may be permitted by law or this contract. If, however, in compliance with this clause, the Contractor discovers and promptly reports an organizational conflict of interest (or the potential thereof) subsequent to contract award, the Contracting Officer may terminate this contract for convenience if such termination is deemed to be in the best interest of the Government or take other appropriate actions.
(2) The parties recognize that this clause has potential effects which will survive the performance of this contract and that it is impossible to foresee each circumstance to which it might be applied in the future. Accordingly, the Contractor may at any time seek a waiver from the Director, MDA, (via the Contracting Officer) by submitting a full written description of the requested waiver and the reasons in support thereof.
H-10 ENABLING CLAUSE FOR BMD INTERFACE SUPPORT (APR 2009)
a. It is anticipated that, during the performance of this contract, the Contractor will be required to support Technical Interface/Integration Meetings (TIMS) with other Ballistic Missile Defense (BMD) Contractors and other Government agencies. Appropriate organizational conflicts of interest clauses and additional costs, if any, will be negotiated as needed to protect the rights of the Contractor and the Government.
b. Interface support deals with activities associated with the integration of the requirements of this contract into BMD system plans and the support of key Missile Defense Agency (MDA) program reviews.
c. The Contractor agrees to cooperate with BMD Contractors by providing access to technical matters, provided, however, the Contractor will not be required to provide proprietary information to non-Government entities or personnel in the absence of a non-disclosure agreement between the Contractor and such entities.
d. The Contractor further agrees to include a clause in each subcontract requiring compliance with paragraph c. above, subject to coordination with the Contractor. This agreement does not relieve the Contractor of its responsibility to manage its subcontracts effectively, nor is it intended to establish privity of contract between the Government and such subcontractors.
e. Personnel from BMD Contractors or other Government agencies or Contractors are not authorized to direct the Contractor in any manner.
f. This clause shall not prejudice the Contractor or its subcontractors from negotiating separate organizational conflict of interest agreements with BMD Contractors; however, these agreements shall not restrict any of the Government's rights established pursuant to this clause or any other contract.
H-11 MDA VISIT AUTHORIZATION PROCEDURES (Aug 2014)
a. The Contractor shall submit all required visit clearances in accordance with current NISPOM regulations. Visit clearances shall identify the contract number.
For Visit Requests to the National Capital Region send to:
| JPAS SMO Code: DDAAU4 |
| Missile Defense Agency |
| Attn: Access Control Center |
| 5700 18th Street, Bldg 245 |
| Fort Belvoir, VA 22060-5573 |
| 571-231-8249 |
| 571-231-8099 FAX |
| ACC@MDA.mil |
For Visit Requests to Huntsville, AL send to:
| Missile Defense Agency, |
| JPAS SMO Code: DDAAUH |
| Attn: Visitor Control |
| Bldg 5224 Martin Road |
| Redstone Arsenal, AL 35898 |
| 256-450-3214 or 256-450-3216 |
| 256-450-3222 FAX |
| mdaaccesscontrolhsv@mda.mil |
For Visit Requests to Colorado Springs, CO send to:
| Missile Defense Agency, |
| SMO Code: DDAAUJ |
| Attn: Visitor Control |
| 720 Irwin Drive, Bldg 720 Room 125 |
| Schriever AFB, CO 80912 |
| 719-721-0362 or 719-721-8230 |
| 719-721-8399 FAX |
| dosscosvar@mda.mil |
b. The COR is authorized to approve visit requests for the Contracting Officer.
H-12 CONTROL OF ACCESS TO MDA SPACES AND INFORMATION SYSTEMS (SEP 2013)
a. To maintain the security of the MDA spaces and information systems, the contractor shall notify the COR in writing whenever a prime or subcontractor employee included on the current visit authorization request/letter no longer supports this contract. This requirement shall apply to both contractor and employee initiated termination of services and to temporary suspension of services.
b. The contractor will cooperate with COR in facilitating the employee’s return of all government issued credentials, e.g., badges, common access cards (CACs), SIPRNet tokens. Specifically, upon notification, the COR will work with the organization’s Security Operations Center and the MDA Service Desk to ensure timely action to:
(1) remove the employee from the current visit authorization request/letter;
(2) cancel Government issued credentials pursuant to the visit authorization request/letter; and,
(3) terminate the MDA LAN account/access privileges.
c. In addition to actions related to MDA access control, the contractor shall maintain accountability for Government issued credentials provided under this contract. Government issued credentials are the property of the U.S. Government and shall not be retained by cardholders upon expiration, replacement, or when the DoD affiliation of employees has been terminated. The contractor shall coordinate with the COR to ensure government issued credentials are retrieved in accordance with local command or installation procedures. Unauthorized possession of an official credential, like a CAC, can be prosecuted criminally under section 701, title 18, United States Code.
d. The contractor shall identify the reason for and date of termination or expected period of suspension and submit the notification to the COR within five (5) working days prior to service discontinuation. For unplanned termination or suspension of services, notification shall be made on the same working day as the termination/suspension action.
H-14 PERSONNEL QUALIFICATIONS (MAY 2005)
a. The Contractor shall promptly notify the Contracting Officer and Contracting Officer’s Representative prior to making any changes in key staff. If replacing key staff the Contractor shall adhere to the following: (1) replacement person’s qualifications are equal to or better than the qualifications of the person being replaced; or (2) the added person’s qualifications are equal to or better than the core capabilities of this contract. Key staff positions are defined as the Program Manager and technician(s) for each of the following Aegis Baseline 9 / BMD Baseline 5 equipment: AN/SPY-1D(V), MK 41 VLS, ACI and MK 99 FCS.
b. All Contractor notifications must provide the name and departure date for the incumbent leaving, a complete resume for the proposed substitute, and any other pertinent information requested by the Contracting Officer. The Government shall be provided the opportunity to review the proposed substitution regarding qualifications, security matters or any other concerns which could, in its opinion, affect performance under this contract.
c. This clause does not, in any way, abrogate the contractor’s authority to hire or assign personnel as it sees fit, or its responsibility to fill key positions with qualified personnel.
H-23 CONTRACTOR EMPLOYEE OUT-PROCESSING (SEP 2012)
Prior to the departure of contractor personnel who have been issued MDA Common Access Cards (CACs), building passes and/or MDA computers, cell phones or other associated peripherals, the departing employee shall complete the MDA Form 14, Out-Processing Checklist, as required by MDA Instruction 1400.06-INS, and return the completed checklist, with all required signatures, to the cognizant Contracting Officer's Representative (COR). The COR will ensure the completed Out-Processing Checklist is provided to the MDA Contracting Officer for retention in the official contract file.
H-28 DISTRIBUTION CONTROL OF TECHNICAL INFORMATION (AUG 2014)
a. The following terms applicable to this clause are defined as follows:
1. DoD Official. Serves in DoD in one of the following positions: Program Director, Deputy Program Director, Program Manager, Deputy Program Manager, Procuring Contracting Officer, Administrative Contracting Officer, or Contracting Officer’s Representative.
2. Technical Document. Any recorded information (including software) that conveys scientific and technical information or technical data.
3. Scientific and Technical Information. Communicable knowledge or information resulting from or pertaining to the conduct or management of effort under this contract. (Includes programmatic information).
4. Technical Data. As defined in DFARS 252.227-7013.
b. Except as otherwise set forth in the Contract Data Requirements List (CDRL), DD Form 1423 the distribution of any technical documents prepared under this contract, in any stage of development or completion, is prohibited outside of the contractor and applicable subcontractors under this contract unless authorized by the Contracting Officer in writing. However, distribution of technical data is permissible to DOD officials having a “need to know” in connection with this contract or any other MDA contract provided that the technical data is properly marked according to the terms and conditions of this contract. When there is any doubt as to “need to know” for purposes of this paragraph, the Contracting Officer or the Contracting Officer’s Representative will provide direction. Authorization to distribute technical data by the Contracting Officer or the Contracting Officer’s Representative does not constitute a warranty of the technical data as it pertains to its accuracy, completeness, or adequacy. The contactor shall distribute this technical data relying on its own corporate best practices and the terms and conditions of this contract. Consequently, the Government assumes no responsibility for the distribution of such technical data nor will the Government have any liability, including third party liability, for such technical data should it be inaccurate, incomplete, improperly marked or otherwise defective. Therefore, such a distribution shall not violate 18 United States Code § 1905.
c. All technical documents prepared under this contract shall be marked with the following distribution statement, warning, and destruction notice identified in sub-paragraphs 1, 2, and 3 below. When it is technically not feasible to use the entire WARNING statement, an abbreviated marking may be used, and a copy of the full statement added to the "Notice To Accompany Release of Export Controlled Data" required by DoD Directive 5230.25.
1. DISTRIBUTION – Distribution statements on technical data shall be marked IAW the corresponding DD Form 1423 as noted in block 9.
2. WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) or the Export Administration Act of 1979 (Title 50, U.S.C., App. 2401 et seq), as amended. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25
3. DESTRUCTION NOTICE - For classified documents follow the procedures in DOD 5220.22-M, National Industrial Security Program Operating Manual, February 2006, Incorporating Change 1, March 28, 2013, Chapter 5, Section 7, or DoDM 5200.01-Volume 3, DoD Information Security Program: Protection of Classified Information, Enclosure 3, Section 17. For controlled unclassified information follow the procedures in DoDM 5200.01-Volume 4, Information Security Program: Controlled Unclassified Information.
d. The Contractor shall insert the substance of this clause, including this paragraph, in all subcontracts.
H-30 CONTRACTUAL TERMS & CONDITIONS (Jun 2010)
The terms and conditions herein constitute the entire contract and understanding of the parties and shall supersede all other communications, negotiations, arrangements and agreements, either oral or written, with respect to the subject matter hereof. All proposal documentation including, but not limited to, red line contract terms and conditions, red line statements of work and/or ground rules and assumptions are hereby void and carry no force or affect as it pertains to the interpretation or operation of the language of the instant contract nor should such language be used to provide meaning to any of the terms or conditions contained herein.
H-31 TECHNICAL COGNIZANCE (JUN 2011)
a The Aegis Ashore Program Office is the cognizant Government technical organization for this contract and will provide technical instruction as defined herein. Technical instructions shall be exercised by designated/appointed Contracting Officer’s Technical Representatives (COTRs):
Title/Position Authority Office Symbol
To Be Included at Contract Award
b. Technical instruction, as defined in this clause is the process by which the progress of the Contractor’s technical efforts are reviewed and evaluated and guidance for the continuation of the effort is provided by the Government. It also includes technical discussions and, to the extent required and specified elsewhere in this contract, defining interfaces between contractors; approving plans; approving Contract Data Requirements List (CDRL) submissions; approving schedules for preliminary and critical design reviews; participating in meetings; providing technical and management information; and responding to request for research and development planning data on all matters pertaining to this contract. The Contractor agrees to accept technical instruction only in the form and procedure set forth herein below.
c. Except for routine discussions having an impact on Contractor performance, technical instruction described above shall only be authorized and binding on the Contractor if provided in writing from the applicable Government official designated above. The technical instruction shall refer to the applicable paragraph(s) of the Statement of Work (SOW) and shall not effect or result in a change within the meaning of the “CHANGES” clause, or any other change in the SOW, price, schedule, or the level of effort required by the contract. All commitments or changes that affect price, quality, quantity, delivery, or other terms and conditions of the contract must be executed by the Procuring Contracting Officer (PCO). It is emphasized that such changes are outside the authority of the COTR designated above. The COTR is not authorized to issue any instruction which authorizes a change in the contract requirements. Notwithstanding any provision to the contrary in any technical instruction, the estimated cost of this contract, and, if this contract is incrementally funded, the amount of funds allotted, shall not be increased or deemed to be increased by issuance thereof.
d. A COTR serves as a liaison for technical aspects of the contract and maintains direct communications with both the Contractor and the PCO. A COTR provides surveillance and monitoring of Contractor performance and may provide technical instruction as specified above or as otherwise limited or specified in the appointment or in the contract. A COTR’s designation cannot be re-delegated unless authorized in writing by the PCO.
e. The Contracting Officer’s Representative (COR) is authorized to perform specific administrative functions on this contract. The COR monitors and reports contractor performance, inspections and acceptance, security issues, property disposal, tracking of budget and funding issues, approval of invoices (if applicable), and other approvals and administrative functions as delegated by the PCO. These administrative functions shall be exercised by designated/appointed CORs:
Title/Position Authority Office Symbol
To Be Included at Contract Award
f. The COR has no authority to make any commitments or changes that affect price, quality, quantity, delivery, or other terms and conditions of the contract. This individual is not authorized to issue any instruction which authorizes the Contractor to either exceed or perform less than the contract requirements. Notwithstanding any provision to the contrary in any COR instruction, the estimated cost of this contract, and, if this contract is incrementally funded, the amount of funds allotted, shall not be increased or deemed to be increased by issuance thereof. A COR’s designation cannot be re-delegated unless authorized in writing by the PCO.
g. Government personnel, Government Contractor Support Services (CSS) contractors and Federally Funded Research and Development Companies (FFRDCs) personnel will frequently be present at Integrated Product Team (IPT) meetings and Contractor facilities. The Government IPT members, their CSS support and FFRDCs may communicate with the Contractor on technical issues; review designs/documents/work products; and provide clarification, opinion, and advice on contract requirements. The Contractor shall not construe advice, opinions, reviews, and clarifications from the Government IPT members, their CSS support or FFRDCs as changes to the terms and conditions of the contract. A PCO is the only individual authorized to change the terms and conditions of the contract.
H-32 TRANSITION OUT (Nov 2010)
a. It is the intent of the Government to provide for an orderly transition during an off-ramp activity related to the end of the contract in order to assure uninterrupted effort throughout the assumption of follow-on Contractor responsibility. When notified, the Contractor shall work closely with the Government to develop a proposal to transition to either the Government or another contractor. The Government will provide the specifics of what the transition includes at the time of the request for change.
b. The transition requirements may include the following:
1) A transition-out period, which will be mutually agreed upon following notification by the Government of an intent to transfer lab equipment, documentation or system test resources.
2) A requirement for the Contractor to work closely with the contractor receiving the lab(s), equipment, and supporting documentation during the transition-out period to allow the receiving contractor time to establish laboratory capability.
c. The Contractor shall execute an Associate Contractor Agreement (ACA) IAW Section H Clause “PROGRAM SYNCHRONIZATION”, attend program reviews, participate in working groups, briefings, and on-site communications, and provide full disclosure of technical, cost, and programmatic information between Contractors/teams associated with meeting the various on-going requirements.
H-33 PROGRAM SYNCHRONIZATION (Nov 2010)
a. The Missile Defense Agency (MDA) requires the synchronized integration of platforms, sensors, and other components of the BMDS which were or are under separate development by multiple contractors. MDA uses the concept of End-to-End (EtE) performance to serve as the organizing principle that aligns and synchronizes these efforts to achieve the desired operational end-state for the BMDS. Synchronization is defined as the logical alignment of management, design, development, integration, modification, verification and validation, and test activities and processes such that sensors, data links, command and control (C2), and interceptors smoothly and optimally integrate within well-defined and commonly understood requirements and interfaces.
b. During the performance of this contract, the Contractor shall provide technical data and other information (to include limited and restricted rights data as defined by DFARS 252.227-7013 and 252.227-7014 or information protected under the Freedom of Information Act Exemption 4) to other Ballistic Missile Defense (BMD) Contractors and Government agencies to facilitate MDA objectives.
c. Pursuant to paragraphs (a) and (b) above the Contractor shall negotiate appropriate Associate Contractor Agreements (ACAs) and Non-Disclosure Agreements (NDAs) with other Contractors as necessary to implement the exchanges of technical data and other information required, ensure total system EtE performance, and also to protect technical data and other information from unauthorized disclosure or use. These agreements must not restrict any of the Government’s rights established pursuant to this or any other contract. A copy of each ACA and amendments to ACAs shall be provided to the PCO in order for the Government to document the flow of information.
d. When associate contracts have been entered into or modified as described in this clause, the associate contractors and general information on the purpose of the associate contracts will be incorporated into this clause as shown below:
Company Name Contract # and Description ACA Purpose
XXX Complete as Appropriate
e. The ACAs shall, at a minimum, include the following general information: (1) Identify the associate contractors and their relationships; (2) Identify the program involved and the relevant Government contracts of the associate contractors; (3) Describe the associate contractor interfaces by general subject matter; (4) Specify the categories of information to be exchanged or support to be provided; (5) Include the expiration date (or event) of the ACA; and (6) Identify potential conflicts between relevant Government contracts and the ACA; include agreements on protection of technical data or other information and restrictions on employees.
f. The Contractor’s performance with respect to integration support, cooperation, and the exchange and sharing of information with other BMD contractors, shall comply with security classification requirements as outlined in the DD Form 254 incorporated into this contract.
g. Nothing in this clause shall take precedence over any other clause or…