Past Performance Questionairre

View the file

Other files for this federal contract opportunity

Other files attached to Operations Staff Specialist Services and Program Management Assistance Services to, newest first.
File Type Posted
A.07.24_Amd_HQ023618R0004-0003.pdf PDF
A.07.24_Amd_HQ023618R0004-0002.pdf PDF
A.07.24_Amendment_HQ023618R0004-0001.pdf PDF
A.07.23_RFP_Att_Pricing_HQ023618R0004.xlsx XLSX spreadsheet
A.07.23_RFP_HQ023618R0004_(final).pdf PDF
A.07.23_Pre-Solicitation_PfPC_Ops__PM.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment - Past Performance Questionnaire

Solicitation HQ023618R0004

Attachment - Past Performance Questionnaire Solicitation HQ023618R0004

PAST PERFORMANCE ASSESSMENT QUESTIONNAIRE

Message to the assessor: This questionnaire is provided to assist the Defense Security Cooperation Agency (DSCA) in the past performance evaluation of offerors pertaining to a competitive acquisition that will result in the award of federal contracts. Therefore, it is important that your information be as factual, accurate and complete as possible to preclude the need for follow-up queries by the evaluators. Offeror shall include this PPQ with their proposal. However, the assessor may e-mail the completed questionnaire(s) to: andrew.gonzalez@marshallcenter.org and Rima.Zimmermann@marshallcenter.org PART I. (To be completed by the Offeror)

A. CONTRACT INFORMATION:

Contractor Doing Business As (DBA) Name:

Address:

Contract Number:

Program Identification/Title:

Government or Non-government Contract:

Contract Type:

Prime Contractor Name (if different from the contractor name cited above):

CAGE Code:

Contract Award Date:

Forecasted or Actual Contract Completion Date:

Nature of the Contractual Effort or Services Provided:

B. ASSESSOR INFORMATION:

Organization/Location:

Name:

Title:

Date:

Telephone Number:

E-mail Address:

PART II. EVALUATION (To be completed by Point of Contact – Respondent)

Check appropriate box and provide comments based on the following ratings/definitions.

Rating
Definition
Outstanding
Performance meets contractual requirements and exceeds many to the Government's benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Good
Performance meets contractual requirements and exceeds some to the Government's benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
Acceptable
Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Marginal
Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions.
Unacceptable
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the contractor's corrective actions appear or were ineffective.

A. Compliance with requirements in the Performance Work Statement.

Outstanding

Good

Acceptable

Marginal

Unacceptable

Comments:

B. Adherence to contract schedules, including timely submittal of documentation and all administrative aspects of performance, required throughout contract performance

Outstanding

Good

Acceptable

Marginal

Unacceptable

Comments:

C. Overall effectiveness of Contract/Project Management (to include use and control of subcontractors).

Outstanding

Good

Acceptable

Marginal

Unacceptable

Comments:

D. Ability to adapt to changes in the contract requirement.

Outstanding

Good

Acceptable

Marginal

Unacceptable

Comments:

E. Commitment to Customer Satisfaction and Business-like Concern for its Customers’ Interest.

Outstanding

Good

Acceptable

Marginal

Unacceptable

Comments:

F. Overall Satisfaction.

Outstanding

Good

Acceptable

Marginal

Unacceptable

Comments:

G. General Comments. Provide any other relevant performance information. Has the Contractor ever been given a cure notice, show cause notice, suspension of progress payment, letter of direction, partial or complete termination? Would you have any reservations about recommending a future contract award to this contractor?

Outstanding

Good

Acceptable

Marginal

Unacceptable

Comments:

H. Other Information Sources. Please provide the following information:

Are you aware of other relevant past efforts by this company?

If yes, please provide the name and telephone number of a point of contact: