HQ0147-09-R-0006
Attachment 10
MDA/DTR
Airborne Sensors (ABS) Program
EXHIBIT A
CONTRACT DATA
REQUIREMENTS LIST
4 FEBRUARY 2010
A. INTRODUCTION
The Contract Data Requirements List (CDRL) is prepared in a word processing format to increase the efficiency of electronic development and transmission. Block numbering and titles remain as used in the DD Form 1423 as derived from Procedures for the Acquisition and Management of Technical Data, DoD 5010.12-M.
B. APPLICABLE DOCUMENTS
DoDD 5230.24, Distribution Statements on Technical Documents, March 18, 1987
C. AUTHORITIES (BLOCK 4)
Data Item Descriptions (DIDs) entered in CDRL blocks 2 and 4 are selected from the Acquisition Streamlining and
Standardization Information System (ASSIST) data base. The application of any DID tailoring is indicated by addition of the suffix "T" to the DID number entered in Block 4. Such tailoring is accomplished to relax format requirements or conform the data requirement to those requirements contained in the Statement of Work (SOW).
D. APPROVAL (BLOCK 8)
Selected data will require approval before their submission is considered final. The approving authority shall be the
MDA/DTR Contracting Officer’s Representative (COR) or government designated Task Manager (TM) as indicated by the first addressee entry of Block 14.a. The use of “N/A” in Block 8 does not forfeit or otherwise affect the Government’s right to consider unacceptable any submission of data that does not comply with the contract requirements.
E. DATA DELIVERY DUE DATES (BLOCKS 12 AND 13)
Data will be considered delinquent when not physically arriving or electronically available at the distribution destination on the date(s) specified. Unless otherwise indicated, references to “days” are calendar days.
F. SUPPLEMENTAL INFORMATION
N/A.
G. DEFINITIONS OF ACRONYMS AND ABBREVIATIONS
Entry Definition
LT Letter of transmittal
N/A Not applicable
ASREQ As required
ANNLY Annually
MTHLY Monthly
DAC Days after contract initiation
MAC Months after contract initiation xx DARP xx Days After Reporting Period
H. ADDRESSEE LIST
Block 14 Entry Complete Mailing Address
MDA/DTR Missile Defense Agency
MDA/DACT ATTN: MDA/______
Missile Defense Agency (MDA)
Building 5222 Martin Road
Redstone Arsenal, AL 35896
CDRL LISTING
CDRL
SOW Paragraph
Reference Data Item Description
001 Program Plan 2.1.3, 2.1.10 DI-MGMT-80909
002 Contract Work Breakdown Structure (CWBS) 2.1.2b DI-MGMT-81334
003 Integrated Master Schedule (IMS) 2.1.4, DI-MISC-81183A
004 Cost Performance Report (CPR) modified 2.3.3 DI-MGMT-81466
005 RESERVED RESERVED RESERVED
006 Contract Funds Status Report (CFSR) 2.3.3 DI-MGMT-81468
007 Interface Design Description 3.1.4 DI-IPSC-81436A
008 Product Drawings 3.1.4 DI-SESS-81000C
009 O&M Instructions for R&D Equipment 4.2.1 b DI-MISC-81414 010 Mission Assurance Implementation Plan (MAIP) 3.0, 3.1.2, 3.2.3, 3.2.4, 3.3, 3.4.1
DI-MISC-80048
011 T&E Program Plan 3.1.4 DI-NDTI-81284
012 RESERVED RESERVED RESERVED
013 Mission Status/Planning & Data Review Report 4.1.2.3, 4.1.2.4, 4.1.2.5, 4.1.4.1b, 4.1.4.1d
DI-MISC-80508B
014 Mission Final Report & Data Products 4.1.4.1b DI-MISC-80508B
015 Report, Record of meetings/Minutes 2.1.6 DI-ADMIN-81505
016 Improvement & Modernization Report 4.3.1 DI-MISC-80508B
017 Status Report 2.1.6b, 2.3.3 DI-MGMT-80368/M
Scientific and Technical Reports - Verification/Final Report 3.1.4 DI-MISC-80508B
019 Test Plan 3.1.4 DI-NDTI-80808
020 Recommended Spare Parts List 3.3.3 DI-ILSS-80134A
021 Technology Development Plan 4.4.1 DI-MISC-80508B
022 Technology Control Plan 2.1.10 DI-MISC-80508B
023 Software Test Report 3.1.4, 3.4.1 DI-ISPC-81440A
024 RESERVED RESERVED RESERVED
025 Hazardous Materials Mgmt Prgm (HMMP Report) 3.2.2 DI- MISC-81398
026 Software Version Description 3.4.1 DI-IPSC-81442A
027 Hazardous Waste Report 3.2.2 DI-MGMT-80899
028 Technical Data Package 3.1.3, 3.1.4, 4.1.1.2a DI-MISC-80508B
Non-CDRL Plans Requiring Document
029 Award Fee Plan Contract DI-ADMIN-80925
Government Furnished Property Management Plan Contract DI-ADMIN-80925
029 List of Compliance and Referenced Documents Contract DI-ADMIN-80925
029 Subcontract Plan Contract DI-ADMIN-80925
029 Subcontract Reports SF 294/295 Contract DI-ADMIN-80925
029 Physical Security Plan DD254 DI-ADMIN-80925
029 Physical Security Implementation Plan (PSIP) DD254 DI-ADMIN-80925
029 OPSEC Plan DD254 DI-ADMIN-80925 029 Information System Certification and Accreditation
Plan
DD254 DI-ADMIN-80925
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
C O N T R A C T D A T A R E Q U I R E M E N T S L I S T
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
Contract/PR No. in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
Airborne Sensor Program
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
Program Plan
3. SUBTITLE
18. EST TOTAL
PRICE
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-80909
5. CONTRACT REFERENCE
SOW Paragraph 2.1.3, 2.1.10
6. REQUIRING OFFICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
One
12. DATE OF FIRST SUBMISSION
30 DAC
14. DISTRIBUTION
8. APP CODE
A
F 11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBM.
ASREQ
a. ADDRESSEE b. COPIES final draft reg repr
16. REMARKS
BLOCK 4: Contractor format is acceptable. Electronic submission shall be made using
Microsoft Office Products. Document shall provide a comprehensive plan indicating how the contractor will approach and perform the efforts required under this contract.
DID Specific Tailoring
10.2.2 Deleted. CWBS should be developed to the level specified in CDRL
A002.
BLOCK 9: Distribution Statement F. Further distribution only as directed by MDA/DTR (Test
Resources -Airborne Sensor Program) or higher DoD authority.
Block 14: Electronic submission required, posting to ABS Portal may satisfy this requirement. Hard copies will be made available upon request. If document is posted to the
ABS Portal, each addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A Section H, Addressee List. CDRLs due on weekends and holidays shall be due the morning of the next business day.
G. PREPARED BY
H. DATE
I. APPROVED BY
ACO
MDA/DACT
15. TOTAL -----> 0 3 0
J. DATE
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page 1 of 1 pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
00013
B. EXHIBIT
A
C. CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A002
2. TITLE OF DATA ITEM: CONTRACT WORK BREAKDOWN
STRUCTURE (CWBS)
3. SUBTITLE 18. EST TOTAL
PRICE
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81334
5. CONTRACT REFERENCE:
SOW para 2.1.2.b
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
8. APP CODE
A
F 11. AS OF DATE
SEE BLOCK 16
13. DATE OF SUBSEQUENT SUBM.
ASREQ
a. ADDRESSEE b. COPIES final
BLOCK 4:
a. The CWBS Index (Part I) and Dictionary (Part II) shall be prepared in accordance with the Contractor Cost Data Reporting (CCDR) Plan.
b. The CWBS Index and Dictionary shall be extended from the summary reporting level provided by the Government in the CCDR Plan to the lowest level at which work will be done including identification of each individual management/control account. Contractor shall identify subcontracted effort, including subcontracted effort and name at the lowest level of the extended CWBS.
c. The CWBS shall be developed at a sufficient level of detail to provide cost visibility for the following prime and Subcontractor cost elements: a) nonrecurring design and recurring prototype manufacturing for all hardware elements; b) and software development at the component WBS level.
d. Contractor format is acceptable. Submission shall be made electronically. The
Government will have access, on an as-required basis, to electronic Contractor
CWBS data.
BLOCK 9: Distribution Statement F. Further distribution only as directed by MDA/DTR
(Test Resources -Airborne Sensor Program) or higher DoD authority.
BLOCKS 11, 12, & 13: Draft CWBS Index (Part I) shall be submitted with the proposal in response to the Government RFP. The complete CWBS Index and Dictionary shall be submitted in electronic format no later than 30 calendar days after award of definitized contract. Electronic submission shall be made using Microsoft Office Products.
requirement. Hard copies will be made available upon request. If document is posted to the ABS Portal, each addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A Section H, Addressee List. CDRLs due on weekends and holidays shall be due the morning of the next business day.
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page 1 of 1 pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A003
2. TITLE OF DATA ITEM
INTEGRATED MASTER SCHEDULE (IMS)
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81183A
5. CONTRACT REFERENCE
SOW Para 2.1.4
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
MONTHLY
12. DATE OF FIRST SUBMISSION
30 DAC
14. DISTRIBUTION
SEE BLOCK 16
8. APP CODE
N/A
F 11. AS OF DATE
SEE BLOCK 16
13. DATE OF SUBSEQUENT SUBM.
SEE BLOCK 16
a. ADDRESSEE b. COPIES final draft reg repr
Block 4:
a. An IMS shall be required for the ABS contract. Reporting shall include Program
Events, Accomplishments and Tasks.
b. Contractor format is acceptable. Electronic submission shall be made using
Microsoft Office Products. Schedule outputs will contain, at a minimum, Baseline
Start & Finish dates, Actual Start & Finish dates, durations, constraints (type and date), Predecessors, Successors, Percent complete, and unique activity ID numbers, SOW reference, WBS.
c. The contractor shall participate in periodic schedule risk assessments (SRA) at the request of the government. Frequency shall be as required.
Block 9: Distribution Statement F. Further distribution only as directed by MDA/DTR (Test
Block 11: Last day of contractor’s monthly accounting period.
Block 12: Initial submittal accompanied delivery of the firm proposal. First submittal 30 Days
After Contract Award.
Block 13: Subsequent submittals are due on the 15th of the month following contractor's accounting month with the exception of the December submittal, which will be submitted on 31
January. One additional day will be added to the delivery date for each company and/or federal holiday falling between the 1st and 15th of the month.
BLOCK 14: Electronic submission required, posting to ABS Portal may satisfy this requirement.
Hard copies will be made available upon request. If document is posted to the ABS Portal, each addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A Section H, Addressee List. CDRLs due on weekends and holidays shall be due the morning of the next business day.
FOR OFFICIAL USE ONLY
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page 1 of 2 pages
FOR OFFICIAL USE ONLY
C O N T R A C T D A T A R E Q U I R E M E N T S L I S T
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503. Please DO NOT
RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A004
2. TITLE OF DATA ITEM
MODIFIED COST PERFORMANCE REPORT (CPR)
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81466
5. CONTRACT REFERENCE
SOW Paragraph 2.3.3
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
MONTHLY
12. DATE OF FIRST SUBMISSION
30 DAC
14. DISTRIBUTION
SEE BLOCK 16
F
11. AS OF DATE
final draft reg repr
16. REMARKS
Block 4:
a. Contractor format is acceptable. Electronic submission shall be made using ANSI
ASC X 12 Transaction Set 839C, Project Cost Reporting, Version 004010. The
Government shall have access to, on an as-required basis, electronic Contractor Cost
Performance Report (CPR) data.
b. Reporting levels shall be IAW the contractor’s Work Breakdown Structure (WBS).
c. Format 1 reporting will be at Level Four of the WBS unless a different level of reporting is mutually agreed upon as required for areas of significant, cost and/or schedule risk. The contractor, with Government approval, shall review and update
Format 1 reporting annually in conjunction with the contractor’s annual EAC update consistent with the contractor’s system description. Current month cost (CV) and schedule variance (SV) explanations are required.
d. Formats 2 and 3 of the CPR are not required.
e. Format 5 shall incorporate at least the top 10 current month and cumulative cost variances, the top 10 current month and cumulative schedule variances, and an explanation of changes for the top 10 variance at completion (VAC) deltas. The current period variances shall be subject to a +/- $25K minimum threshold. The cumulative variances shall be subject to a +/- $50K minimum threshold. The variances at completion shall be subject to a +/- 10 percent minimum threshold. All
Budget at Completion (BAC) changes on Format 1 shall be explained in Format 5.
All Management Reserve (MR) transactions, including the work scope to be covered by the MR, the amount of MR to be distributed by WBS element and the forecasted/actual date of MR distribution shall be explained on Format 5.
Undistributed Budget (UB) transactions shall be explained in a similar manner.
Specific corrective actions, forecasted closure date, and impact to the Estimate at
Completion (EAC) shall be included in each variance narrative. Contractor shall explain to the lowest CWBS level necessary to completely explain the variances
“Best case” and “Worst case” EACs. Explanation of the PMB changes shall be in sufficient detail to explain the rationale for PMB adjustments for all periods.
f. The Government reserves the right to review and modify, through negotiations, the variance analysis requirements for Format 1during the performance of the contract, but no sooner than six months after contract award.
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page 2 of 2 pages
Block 4 (cont.):
g. CPRs from major subcontractors shall be for the same/similar accounting period as the prime contractor consolidated submittal.
h. The contractor shall submit copies of major subcontractors as attachments to the prime contractor consolidated submittal.
i. For format 5 variance narratives include the nature of the problem, reasons for CV or
SV, impact on other WBS(s) tasks, impact to the program, corrective action and expected recovery. Also note if the variance is to continue, for how long.
Block 9: Distribution Statement F. Further distribution only as directed by MDA/DTR
Block 13:
a. Formats 1, 4 and 5 subsequent submissions are due on the 15th of the month following contractor's accounting month with the exception of the December submittal, which will be submitted on 31 January. One additional day will be added to the delivery date for each company and/or federal holiday falling between the 1st and 15th of the month.
the ABS Portal, each addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A, Section H, Addressee List. CDRLs due on weekends and holidays
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page 1 of 1 pages
FOR OFFICIAL USE ONLY
C O N T R A C T D A T A R E Q U I R E M E N T S L I S T
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington
Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the
Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. in Block E.
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A006
2. TITLE OF DATA ITEM
CONTRACT FUNDS STATUS REPORT (CFSR)
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT 81468
5. CONTRACT REFERENCE
SOW Para 2.3.3
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
Monthly
12. DATE OF FIRST SUBMISSION
30 DAC
14. DISTRIBUTION
SEE BLOCK 16
8. APP CODE
N/A
F 11. AS OF DATE
SEE BLOCK 16
13. DATE OF SUBSEQUENT SUBM.
SEE BLOCK 16
a. ADDRESSEE b. COPIES final draft reg repr
16. REMARKS
Block 4:
a. Contractor format is acceptable. Electronic submissions shall be made electronically using Microsoft Office products. The Government shall have access, on an as-required basis, to electronic Contractor CFSR data.
b. Report by CLIN in block 11 of CFSR.
c. The “at completion” column of Block 12 shall be the contractor’s Estimated Price at
Completion (EPC) (including Government share of any projected overruns).
d. Projections in blocks 12,13,14 of the CFSR shall be monthly for at least six months, quarterly for the remainder of the government fiscal year, four quarters of the following fiscal year, and then annual to completion.
e. For block 15 of the CFSR, report actual payments received as a cumulative value for the period from contract award through the current report date. Include any pertinent information to explain a projected change in funding required or change to the EPC.
f. A reconciliation of the CFSR and CPR shall be performed and submitted as an attachment to the CFSR.
g. The contractor shall submit copies of major subcontractors CFSRs as attachments to the Contractor’s consolidated submittal.
Block 9: Distribution Statement F. Further distribution only as directed by MDA/DTR (Test
Block 13: Subsequent submittals are due on the 15th of the month following contractor's accounting month with the exception of the December submittal, which will be submitted on 31 January. One additional day will be added to the delivery date for each company and/or federal holiday falling between the 1st and 15th of the month.
addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A, Section H, Addressee List. CDRLs due on weekends and holidays shall be due the morning of the next business day.
15. TOTAL ---
0 3 0
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A007
2. TITLE OF DATA ITEM
Interface Design Description
4. AUTHORITY (Data Acquisition Document No.)
DI-IPSC-81436A
5. CONTRACT REFERENCE
SOW Paragraph 3.1.4
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
One/R
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
As REQ final
Microsoft Office Products.
BLOCK 12: Initial submittal required 6 months after contract award. The Government has 30 calendar days to review the first draft. The contractor has 30 calendar days, after receipt of Government comments, to prepare and deliver the final report.
BLOCK 13: Subsequent delivery, as required, for modifications or new developments:
delivery is required 6 weeks after final design acceptance (Gate 2).
addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A, Section H, DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of
Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503. Please DO NOT
RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. in Block E.
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A008
2. TITLE OF DATA ITEM
Product Drawings and Associated Lists
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81000C
5. CONTRACT REFERENCE
SOW Paragraph 3.1.4
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
One/R
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
final
BLOCK 4: Contractor format is acceptable. Electronic submission shall be made.
Content shall include all Drawings, Program Documentation, Test Documentation, Test and Instrumentation Data, Certification/Engineering Reports, Software Documentation, Technical Publications Documentation, and “As-Built” installation data. Contractor shall identify commercially available drawing development software to allow for government to purchase for viewing. Drawings shall be delivered in format capable of being viewed by the identified commercial software package and PDF.
BLOCK 12: For design changes, drawing updates, modifications or new developments, initial submission required 6 weeks after initial drawing completion. The Government has 30 calendar days to review.
Block 13: Updates as required with final submittal required 6 weeks after completion of flight validation testing. The Government has 30 calendar days to review all submittals.
The contractor has 30 calendar days, after receipt of Government comments, to prepare and deliver the final drawings/products.
addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A, Section H, DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A009
2. TITLE OF DATA ITEM
Operations and Maintenance (O&M) Instructions for R&D Equipment
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-81414
5. CONTRACT REFERENCE
SOW Paragraph 4.2.1.b
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
One/R
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
As Req final
Microsoft Office Products. The contractor shall prepare and deliver system description, subsystem descriptions, operation procedures, maintenance manuals, calibration procedures, schedule maintenance procedures, support equipment requirements, aircraft installation and checkout procedures, and data reduction procedures.
BLOCK 12: Delivery due 6 weeks after completion of flight validation testing for any modification or new development. The Government has 30 calendar days to review the first draft. The contractor has 30 calendar days, after receipt of Government comments, to prepare and deliver the final report.
addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A, Section H, DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A010
2. TITLE OF DATA ITEM
Scientific and Technical Reports Summary
3. SUBTITLE
Mission Assurance Implementation Plan
18. EST TOTAL
PRICE
4. AUTHORITY (Data Acquisition Document No.)
DI MISC-80048
5. CONTRACT REFERENCE
SOW Para 3.0, 3.1.2, 3.2.3, 3.2.4, 3.3. 3.4.1
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
ONE
12. DATE OF FIRST SUBMISSION
See Block 16
14. DISTRIBUTION
See Block 16 final
BLOCK 4: Contractor format is acceptable – recommend using any MDA provided tools or guides. Electronic submission shall be made using Microsoft Office Products.
Airborne Sensors (ABS) tailored MDA Assurance Provisions (MAP) shall provide the technical and management principles used to assure ABS mission success. Mission
Assurance Implementation Plan (MAIP) shall provide a comprehensive plan indicating the methods to be used by the contractor to implement the tailored MDA Assurance
Provisions (MAP) once approved by the Government.
BLOCK 9: Distribution Statement F. Further distribution only as directed by
MDA/DTR (Test Resources -Airborne Sensor Program) or higher DoD authority.
BLOCK 12: Contractor shall provide a draft MAP with the proposal. Contractor shall provide a draft MAIP within 30 calendar days after tailored MAP is approved by the
Government.
BLOCK 13: Contractor shall provide an updated document (applies to MAP and MAIP) addressing Government comments within 30 days of receipt (until final approval is received).
Subsequent updates only as necessary to address changes in identified processes.
Cost information may be requested, as necessary, to support this activity.
BLOCK 14: Electronic submission required, posting to ABS Portal may satisfy this the ABS Portal, each addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A, Section H, Addressee List. CDRLs due on weekends and
15. TOTAL -----> 01 3 0
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A011
2. TITLE OF DATA ITEM
Test and Evaluation Program Plan
4. AUTHORITY (Data Acquisition Document No.)
DI-NDTI-81284
5. CONTRACT REFERENCE
SOW Paragraph 3.1.4
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
One/R
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
AS REQ
final
BLOCK 12: Initial submittal required 60 days after delivery order award for a modification or technology development. The Government has 30 calendar days to review the first draft. The contractor has 30 calendar days, after receipt of Government comments, to prepare and deliver the final report.
addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A, Section H, Addressee List. CDRLs due on weekends and holidays shall be due the morning of the next
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A013
2. TITLE OF DATA ITEM
TECHNICAL REPORT – STUDY SERVICES
3. SUBTITLE
MISSION STATUS / PLANNING & DATA REVIEW REPORT
18. EST TOTAL
PRICE
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80508B
5. CONTRACT REFERENCE
SOW Para 4.1.2.3, 4.1.2.4, 4.1.2.5, 4.1.4.1b, 4.1.4.1d
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
AS REQ
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
final draft reg repr
16. REMARKS
NOTE: This CDRL consolidates the requirements for Mission Planning documents
(MSP), Mission status (planning meetings), data review meetings, and mission reports (4-hr PMSM, 48-hr PMSSR, & MFR) into a new CDRL A013 for Mission Status/Mission
Reports.
Blk 4: Contractor format is acceptable. Electronic submission shall be made using
Blk 12: Documents will be submitted:
Mission Support Plan (MSP). MSP will be submitted in response to specific Mission
Requirements Documents (MRD) to document planned mission support for a specific mission. Report is required 30 days prior to first scheduled launch date (T-0). The MSP will be submitted to MDA/DTR for review and final distribution. Mission Status/Data
Review meetings. If lead time allows (typically 10 work days) prior to a presentation, draft presentation materials will be submitted to MDA/DTR for review 5 days prior to meeting. If time is short, final version of presentation and facing page narratives will be delivered 10 work days after review/meeting.
Mission Reports. Typical mission reports for each mission will be delivered IAW the
Data Management Plan/Data Handling Plan provided by the User. The 4-hr Post-Mission
Status Message (PMSM) and the 48-hr Post-Mission Status & Summary Report (PMSSR) are delivered to the MDA/DTR Government Representative to make secondary distribution. The Mission Final Report (MFR) will be provided to MDA/DTR for review and comment prior to making final distribution IAW the DMP/DHP. The MSP, PMSSR and MFR will include the following topics as appropriate: 1) Executive Summary, 2)
Mission overview and objectives, Vehicle(s) description, Timeline/Data Collection Plan, Mission and Post-mission support requirements and planning, 3) Test to be executed/Supported, 4) Range Interface requirements planning, 5) Sensor configuration and Data management activities.
Mission Assurance Briefings/Certification Letters. Provided to MDA/DTR after MSP submission at the Government’s request. Mission Critical Checklists will be delivered to
MDA/DTR post-mission at the Government’s request.
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
Contract FA8632-05-D-2455
CDRL A013
Block 16, Cont.
Blk 14: Electronic submission required. Posting to ABS Portal may satisfy this requirement.
However, copies to User Org and Test Range personnel shall be provided electronic copies of reports directly. Hard copies will be made available on request. If document is posted to the Portal, each addressee shall be notified by e-mail indicating the date and to which folder the report was posted. E-mail and physical addresses are provided in Exhibit A, Section H, DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A014
2. TITLE OF DATA ITEM
Technical Report – Study Services
3. SUBTITLE
Mission Data Products
18. EST TOTAL
PRICE
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80508B
5. CONTRACT REFERENCE
SOW Paragraph 4.1.4.1b
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
final
Block 4: Contractor format is acceptable. Electronic submission shall be made using
Block 9: Distribution Statement F: Further distribution only as directed by MDA/DTR
Block 12: Mission Data Products will be delivered in accordance with (IAW) the requirements established in the User's Data Management Plan/Data Handling Plan.
Block 14: Electronic submission required. Posting to ABS Portal may satisfy this requirement. However, copies to User Org and Test Range personnel shall be provided electronic copies of reports directly. Hard copies will be made available on request. If document is posted to the Portal, each addressee shall be notified by e-mail indicating the date and to which folder the report was posted. E-mail and physical addresses are provided in Exhibit A, Section H, Addressee List. CDRLs due on weekends and holidays
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A015
2. TITLE OF DATA ITEM
REPORT, RECORD OF MEETINGS/MINUTES
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMIN-81505
5. CONTRACT REFERENCE
SOW Para 2.1.6
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
NONE
final
BLOCK 8: Only at the Quarterly Performance Review (QPR) meetings will MDA/DTR have approval for the minutes, the others will be documentary to record discussions, decisions (and associated rationale), and action items.
BLOCKs 10, 12 & 13: Documents to be submitted within 20 working days after each government attended meeting.
addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A, Section H, DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A016
2. TITLE OF DATA ITEM
TECHNICAL REPORT – STUDY SERVICES
3. SUBTITLE
IMPROVEMENT AND MODERNIZATION REPORT
18. EST TOTAL
PRICE
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80508B
5. CONTRACT REFERENCE
SOW Para 4.3.1
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
12MAC
14. DISTRIBUTION
ANNLY
final
BLOCK 12: Report shall contain, as a minimum, detailed rationale, plans, design concept, performance improvement, technical payoff and cost information to allow technical assessment and evaluation of proposed improvements and modernization to system. Revisions shall be submitted annually to align with the government budget cycle.
The Government has 30 calendar days to review the first draft. The contractor has 30 calendar days, after receipt of Government comments, to prepare and deliver the final product.
addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A, Section H, DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A017
2. TITLE OF DATA ITEM
Status Report
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-80368A
5. CONTRACT REFERENCE
SOW Para 2.1.6b, 2.3.3
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
MONTHLY
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
final
BLOCK 12: Initial report is to cover period to end of first full month following award.
Report is due 15 days after completion of each month’s effort. If report is presented orally, provide viewgraphs and facing page narrative to attendees at meeting, (NTE 10 copies) in addition to written report.
Provide reporting down to WBS level sufficient to track progress to task and mission level.
addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A, Section H, DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A018
2. TITLE OF DATA ITEM
TECHNICAL REPORT – STUDY SERVICES
3. SUBTITLE
VERIFICATION/FINAL REPORT
18. EST TOTAL
PRICE
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80508B
5. CONTRACT REFERENCE
SOW Para 3.1.4
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
ONE
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
final
BLOCKs 12 & 13: Report shall contain a complete description of the support performed under the contract period of performance. Report shall provide a summary of all missions supported, results and system technical state and status:
1. Program Description
2. Mission Supported
3. Data Collected
4. Data Distribution/Archival Location
5. Data Release Authority
6. System Performance
7. Status of any upgrades/development activities
8. Status and/or disposition of all GFE or hardware
Submission of draft is due 60 days prior to contract end. The Government has 30 calendar days to review the first draft. The contractor has 30 calendar days, after receipt of Government comments, to prepare and deliver the final product.
addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A, Section H,
15. TOTAL -----> 01 3 0
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___ of ___1___Pages
(1 Data Item)
Forms Approved
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to
Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite
1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington DC 20503.
Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the
B. EXHIBIT
A
C: CATEGORY:
TDP TM OTHER X
17. PRICE GROUP
D. SYSTEM/ITEM
A019
2. TITLE OF DATA ITEM
TEST PLAN
4. AUTHORITY (Data Acquisition Document No.)
DI-NDTI-80808
5. CONTRACT REFERENCE
SOW paragraph 3.1.4
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
XTIMES
12. DATE OF FIRST SUBMISSION
See Block 16
14. DISTRIBUTION
final
Microsoft Office Products
BLOCK 9: Distribution Statement F: Further distribution only as directed by MDA/DTR
BLOCK 12: For modifications and new technology development, Test Plan is due 60 days before testing commences. The Government has 30 calendar days to review and provide comments on the plan. The Contractor has 30 calendar days, after receipt of
Government comments, to prepare and deliver the final product. Subsequent drafts are due as required.
BLOCK 13: Updates due as required.
addressee shall be notified by e-mail indicating to which folder and subfolder the report has been posted and the date posted. E-mail and physical addresses are provided in Exhibit A, Section H,
15. TOTAL -----> 03 04 0
DD Form 1423-1, JUN 90 Previous Editions are obsolete Page __1___…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .