Text version

Questions & Responses #3

1. Do all subcontractors need to be registered in SAM or just the prime?

Response: Just the prime contractor needs to be registered in SAM.

2. We understand per Amendment 0001 that all parts of the SF330 form must be included within Volume II of our proposal. We anticipate including several SF330 Part II forms for our offices and those of subcontractors. Will Part II forms be excluded from the 50-page limit set on this section?

Response: The Part II forms are included in the 50 page limit.

3. Would you please clarify. If the prime and a subcontractor are both submitting PPQs on the same project, should the subcontractor get the PPQ filled out by the prime or the ultimate client. For example the prime used the proposed sub on project x for client y. Both the prime and the proposed sub are submitting PPQs for for project x with this proposal. Does the sub ask the prime or client y to complete the PPQ?

Response: Primes and Subs are to submit references. Subs should send the questionnaires to their primes for completion, not the ultimate customers.