About this file

This is a Contract Data Requirements List (CDRL) Form 1423-1 for Training Material deliverables under contract HDTRA1-25 for the Defense Threat Reduction Agency (DTRA). The CDRL establishes requirements for Training Support Package (TSP) development and delivery through multiple stages.

The document specifies a detailed timeline for TSP development: Conceptual Drafts (10% completion) are due 110 days before an event; Preliminary Draft Lesson Plans (25% completion) are due 90 days before; Final Document Lesson Plans (50% completion) are due 60 days before; Training Aids (75% completion) including facilitator guides, student guides and slides are due 45 days before; and Final Documents (100% completion) are due 30 days before the event. Post-event requirements include reviewing feedback within 30 days, briefing the government within 60 days, and submitting updates within 180 days of event completion. The contractor must use government-provided templates and allow 10 business days for government review cycles. Distribution requirements specify 4 final copies to be provided to various DTRA offices including OB-BP COR, OB-BP PM, OB-BP Training, and AL-ACN KO and CS.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DD FORM 1423-1, FEB 2001

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

PREVIOUS EDITION MAY BE USED.

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

Page of Pages

X

HDTRA1-25

A010 Training Material

DI-ILSS-81070 PWS DTRA OB-BP

N/A

A D

See Blk 16

Award

See Blk 16

See Blk 16

OB-BP COR 1

OB-BP PM 1

OB-BP Training 1 AL-ACN KO and CS 1

0 4 0

This DID is for reference and submissions can be tailored with COR approval. This deliverable shall consist of Training Support Package (TSP) Conceptual Drafts, TSP Preliminary Drafts, TSP Final Documents, and TSP Post Event Updates.

Block 12: Initial submission of the TSP Conceptual Drafts shall be submitted as a draft no later than 120 days before event start date unless approved otherwise by the COR.

Block 10, 13: Subsequent submissions shall be in line with the timing outlined below unless approved otherwise by the COR. Upon receipt of the drafts, the USG will have 10 business days to provide comments. Upon receipt of USG comments, the Contractor has 10 business days to provide responses/updates as required. The same review cycle timeline applies for revised submissions. Minor comments can be incorporated into the next milestone delivery (as directed by the COR). Upon Government approval, the Contractor shall distribute the final, approved deliverable.

Block 14: The Contractor shall prepare and submit the deliverable electronically using the appropriate Microsoft Office formatting. Hard copy submissions shall be provided as requested by the Government.

Block 4 and Remarks:

Alternate timelines can be recommended by the Contractor and implemented if approved by the COR. Timelines should ensure sufficient time for reviews, updates, and translation.

-TSP Conceptual Drafts: No later than 110 days before an event, the contractor shall provide drafts/outlines for lesson plans, facilitator guides, student guides, and/or slides (or other material as described by the USG) which would constitute 10% completion of the material. The Contractor shall also provide the planned timeline for the remainder of submissions.

-TSP Preliminary Draft Lesson Plan: No later than 90 days before an event, the Contractor shall submit a draft for the Lesson Plan which would constitute 25% completion of the material.

-TSP Final Document Lesson Plan: No later than 60 days before an event, the Contractor shall submit a complete Lesson Plan which would constitute 50% completion of the material.

-TSP Training Aids: No Later than 45 days before an event, the Contractor shall submit all draft training aids which would constitute 75% completion of the material. Facilitator guide, Student guide, slides, scenarios, exercises or other material as described by the USG will be considered Training Aids.

Adobe Professional 8.0

DRAFT

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued)

DD FORM 1423-1, FEB 2001 Page of Pages

X

HDTRA1-25

-TSP Final Documents: No Later than 30 day before an event, the Contractor shall submit all TSP Documents which would constitute 100% completion of the material.

-TSP Post Event Updates: Within 30 days after an event has concluded, instructional material should be reviewed for any feedback received. Within 60 days after the event has concluded, the Contractor shall brief the USG on feedback and future changes to Training Support Packages (TSPs) or Program of Instructions (PoIs). The Contractor shall make updates the material as requested and submit them within 180 days of event completion -Contractor will use the templates provided by the USG for creating for lesson plans, facilitator guides, student guides, slides, scenarios, and exercises (or other material as described by the USG)

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package;

TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.

DD FORM 1423-1 (BACK), FEB 2001