HDEC03-14-R-0003
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
COMMISSARY SITEWORK
FFP
Contractor shall provide all plant, labor, equipment and materials necessary to perform the construction Sitework identified in the drawings beyond the 5ft.
building perimeter.
FOB: Destination
SIGNAL CODE: A
NET AMT
0002 1 Job
COMMISSARY BUILDING CONSTRUCTION
FFP
Contractor shall provide all plant, labor, equipment, and materials necessary to perform the work to 5 ft. outside the Commissary Building and identified as “Construction” in the drawings and specification Sections 01 26 00, 101500 and 101400
Solicitation HDEC03-14-R-0003 NAS Jacksonville Amend 01 Attachment 03 - Section B Amended
0003 1 Job
COMMISSARY EQUIPMENT
FFP
Provide all plant, labor, equipment, and materials necessary to complete all items specifically identified as “Equipment”” in specification Section 01 26 00.
0004 1 Job
DEMOLITION UTILITIES & EXISTING BLDG
FFP
DEMOLITION/SITE UTILITIES AND MODIFICATION TO EXISTING
BUILDING : Demolition of existing commissary , site utilities and associated where wall adjoins. Modification of existing wall; Interior; Canopy/Roof Modification, Plumbing, FP system, and Electrical and sitework.
0005 1 Job
NEX - ADDITION RENOVATION AREA 1 & SITE
FFP
NAVY EXCHANGE - ADDITION RENOVATION AREA 1 AND SITE WORK
: Provide all plant, labor, equipment, and materials necessary to complete the new addition to the East, the renovation of the existing Exchange indicated as Area 1 in drawings ( CS-102,CG-701, CU-101)
0006 1 Job
NEX – RENOVATION AREA 2 AND SITEWORK
FFP
NAVY EXCHANGE– RENOVATION AREA 2 AND SITEWORK : Provide all plant, labor, equipment, and materials necessary to perform the renovation of Area 2 as indicated in the drawings (A-100 & I-100)
0007 1 Job
NEX OPTION - FLOORING UPGRADES
FFP
NAVY EXCHANGE OPTION - FLOORING UPGRADES 1: Provide all plant, labor, equipment and materials necessary to perform the upgrade to the following areas: Employee Lounge, Employee Lockers and GNC area (A-100 & I-100)
0008 1 Job
NEX OPTION - FLOORING UPGRADE
FFP
NAVY EXCHANGE OPTION - FLOORING UPGRADES 2 – Provide all plant, labor, equipment, and materials necessary to complete flooring upgrade in Sales Area 1 indicated in the drawings (A-100 & I-100)
0009 1 Job
NEX OPTION - NORTH PARKING LOT
FFP
NAVY EXCHANGE OPTION - NORTH PARKING LOT: – Provide all plant, labor, equipment, and materials necessary to complete North Parking lot and all associated work indicated in the drawings (CS102 & CG702)
0010 1 Job
NEX OPTION – COLUMN WRAP UPGRADE
FFP
NAVY EXCHANGE OPTION – COLUMN WRAP UPGRADE: Provide all plant, labor equipment, and material necessary to complete column wrap enclosures indicated Areas A and H and in the drawings (A-101, A-404 & A- 501)
0011 1 Job
NEX OPTION - RENOVATE BARBER/LAUNDRY/OPT
FFP
NAVY EXCHANGE OPTION – RENOVATE BARBER/BEAUTY
LAUNDRY/DRY CLEAN & OPTICAL SHOP: Provide all plant, labor, equipment, and materials necessary to perform the renovation for the following areas: Barber/Beauty, Laundry/Dry Clean and Optical Shop indicated in the drawings (A-100)
0012 1 Job
NAVY HOSPITAL SATELLITE PHARMACY DRIVE T
FFP
NAVY HOSPITAL SATELLITE PHARMACY DRIVE THRU : Provide all plant, labor, equipment, and material necessary to perform the building construction, Canopy, Pharmacy Drop –off window and etc.
0013 1 Job
PHARMACY EQUIPMENT
FFP
Provide all plant, labor, equipment and material necessary to complete all items specifically identified as “Equipment “ In specification Section 149200 Drive – Thru Conveyor System
0014 1 Job
PHARMACY NEW SITE WORK AND DEMOLITION
FFP
Provide all plant, labor equipment, and materials necessary to complete all site work including paving, utilities and demolition indicated in drawings (CD101
&CS101)
peterssh Typewritten Text Total Commissary CLIN's 0001 - 0003 $_______________________________ Total Demolition CLIN 0004 $_______________________________ Total NEXCOM CLIN's 0005 - 0011 $_______________________________ Total Pharmacy CLIN's 0012 - 0014 $_______________________________ Total All CLIN's 0001 - 0014 $_______________________________ peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text peterssh Typewritten Text