Attachment #13 Key Government Milestones & Deliverables
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_10_-_Question_Matrix.xlsx | XLSX spreadsheet | |
| Attachment_1_SOO_v3.docx | DOCX document | |
| Attachement_16_-_SF328.pdf | ||
| HC1047-18-R-4007_Draft_RFP_Ver2.docx | DOCX document | |
| Attachment_6_-_CLIN_v2.xlsx | XLSX spreadsheet | |
| Attachment_2_-_FRD_v2.pdf | ||
| Attachment_10_-_Question_Matrix.xlsx | XLSX spreadsheet | |
| Attachment_8__-_Sample_Consent_Letter.docx | DOCX document | |
| Attachment__6_CLIN.xlsx | XLSX spreadsheet | |
| DEOS_DRAFT_RFP_4-16.docx | DOCX document | |
| Attachment_5_-QASP_Template.docx | DOCX document | |
| Attachment_10_-_Question_Matrix.xlsx | XLSX spreadsheet | |
| Attachment__4_PWS_Temp.DOC | DOC document | |
| Attachment_15_-_NonDisclosure_Agreement_Contractor.pdf | ||
| Attachment_9_-_Past_Performance_Volume_Submission_Template.docx | DOCX document | |
| Attachment___2_FRD.pdf | ||
| Attachment_14_-_EULA_Addendum.docx | DOCX document | |
| Attachment_12_-_Small_Business_Parti.docx | DOCX document | |
| Attachment_7_-_QUESTIONNAIRE_COVER_LETTER.docx | DOCX document | |
| Attachment___1_SOO.DOCX | DOCX document |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Milestone Criteria Government Implementation Milestones/Deliverables/Activities for
Phase Milestone ID Milestone Acronym Milestone Name Deliverables / Activities Due Date (Notional) Design Readiness Milestones DM1 PDR Preliminary Design Review • Architecture, DoDAF Artifacts/Diagrams (AV, OV, SV, StdV, CV) *
• Interfaces, Ports & Protocols Baseline **
• Service Support Functions and Integration Plan *
• D-DIL Architecture/ Integration Plan *
• Performance Monitoring Strategy *
• Data Loss Prevention Plan *
• Security Architecture Analysis
• Migration Strategy *
• Migration Schedule *
• Transition Strategy **
• Requirements Management Plan / Traceability Matrix**
• Licensing Structure *
| 30 days after Task Order Execution | ||||
| DM2 | TENANCY | Tenancy Review | • Single Tenancy/Multitenancy Recommendation ** |
• Cloud Service Administration Portal Plan **
• Single sign on with ADFS and Directory Synchronization Plan *
• Support model and Service Requests Plan **
| 30 days after Acceptance of DM1 | ||||
| DM3 | PRR | Production Readiness Review | • Updated Architecture, DoDAF Artifacts/Diagrams (AV, OV, SV, StdV, CV) * |
• Service Management Plan *
• Change Management Documentation *
• Continuous Monitoring Test Plan *
• Incident Response Plan and Procedures *
• CPMP
• Service Desk Strategy *
| 30 days after Acceptance of DM2 | |||||
| DM4 | CDR | Critical Design Review | • DM1, DM2, DM3 Document Updates ** | 45 days after Acceptance of DM3 | |
| DM5 | TRAINING | Training | • Training Strategy * |
* End User Fact Sheets/Manuals *
• System Administrator Configuration Guides for NIPR, SIPR, and D-DIL Environments*
• Training Requirements Definition *
• Training Material *
• Training Feedback Forms *
| 15 days after Acceptance of DM4 | ||||
| Integration Milestones | CIM1 | ATC | Authority to Connect | • Impact Assessment Report * |
• Implementation Status Report *
• Implemented Controls *
• Security Assessment Report *
• Selected Security Control Assessment *
• Issue Resolution Report *
• Plan of Action & Milestones *
• Remediation Status Report *
• Residual Risk Statement *
• Risk Acceptance Recommendation *
• Risk Assessment **
• Security Assessment Report *
• Security Control Selection Documentation *
| • System Security Plan * | 90 days after Task Order Execution | ||||
| CIM2 | HOSTING | DNS, Network, Transport, Hosting (FRD section 7.3) | • Request and Obtain IP Addresses from the NIC (For DoD IPs) *** |
• Request and Obtain IP Addresses from the CSP (For CSP IPs) **
• Configure IP Addresses in CSP Routers **
• Configure IP Addresses in DISA Routers ***
• Configure Secure NAT ***
• Connectivity Test *
• Test SNAT Translation *
• Identify DNS Names and structure and notional record types
• Determine process to add URL *
• DNS Routing issues, sink holing, reverse proxy *
• Provide TTL and other parameters *
• Configure Domain in CSP Portal *
• Configure DNS Whitelist (Vendor's URLs) *
• Review external DNS records and SSL certificates
• Configure external/internal DNS; Ensure auto discover is working
• Configure DNS Failover
| 30 days after Acceptance of CIM1 | ||||
| CIM3 | PA | Provisional Authorization | • Contractor provides FedRAMP PA to DISA for Validation ** |
• Coordinate Technical Kick Off meeting with DISA SCA and CSP Representatives; include site visits if applicable **
• Validate deltas between CSP inherited controls and required inherited controls **
• Validate Implemented inheritable controls deltas **
• Approved SAR is submitted to AO office***
• Prepare POA&M addressing residual risk ***
• Submit eMASS Package ***
• Submit Provisional Authorization (PA) recommendation ***
| • Provisional Authorization Package Review *** | 30 days after Acceptance of CIM1 | ||||
| CIM4 | IATT | Interim Authority to Test (IATT) | • Initiate RMF Security Plan /Update System Security Plan (SSP) ** |
• Conduct Site/ ST&E Visit if applicable **
• DSS SCA Assessor to develop security assessment repot (SAR) **
• DSS SCA Assessor reviews report with Vendor ISSM ***
• DSS SCA Assessor coordinate SAR with DSS SCA leadership for approval
• Vendor ISSM prepares POA&M addressing residual risk findings **
• Complete self-assessment and IA controls, System Implementation Plan (SIP), RMF Implementation Plan (DIP), RMF Scorecard, System POA&Ms ***
• Continuous monitoring strategy **
• System Security Plan (SSP), Service Operations Annex (SOX) ***
• Information System Contingency Plan (ISCP) ***
• CONOPS, Change Management Plan (CMP), IRP Updates ***
• ISSM and ISSO Appointment letters ***
| 30 days after Acceptance of CIM1 | ||||
| CIM6 | SW | System Wide Requirements Enablement (FRD Section 3) | ||
| 15 days after Acceptance of CIM5 | ||||
| CIM7 | IDAM | Identity & Access Management Integration (FRD Section 7.2) | • Identify Replication Mechanism (e.g. IDSS) * |
• Produce Architecture Diagrams *
• Identify Enterprise Wide Lookup Mechanism (e.g. GAL) *
• Determine attributes to be replicated *
• Detail Replication Process *
• Create Documentation and Architecture Diagrams•
• Implement Provisioning Mechanism *
• Generate Server Side Certificates *
• Identify MILDEP POCs (Local Registration Authority) for CSR submission *
• Facilitate DoD PKI Certificate Generation/Signing *
• OCSP/CRL Integration *
• User Certificate Selection (e.g. PIV Certificates) *
• IP Transport *
| 45 days after Acceptance of CIM6 | ||||
| CIM8 | DODIN-CS | DoDIN Protection / Cybersecurity Assessment (FRD Sections 3, 7.4) | • Cybersecurity Assessment Reports * |
• Produce Architecture Diagrams (e.g. Traffic Flows) *
• Assessment Report *
• Provisioning / Authentication Assessment Documentation *
• Impact Assessment *
• Privacy Impact Assessment *
• Privacy Threshold Analysis *
• Remediation Status Report *
• Residual Risk Statement *
• Security Assessment *
• Vulnerability Assessment *
| 60 days after Acceptance of CIM6 | ||||
| CIM9 | SMI | Service Management Integration (FRD Section 7.1) | • OSS/JMN Integration Plan |
• Access Management Support Plan
• Event Management Support Plan
• Incident Management Support Plan
• Request Fulfillment Support Plan
• Storefront Integration Plan
• Service Desk Support Plan
• Service Desk Integration Plan
• Problem Management Support Plan
• Customer Satisfaction Metric Collection Proposal
• GSD / Mission Partner Helpdesk Integration Plan
• Integrated / Non-Integrated Service Desk Plan
• NETOPS Plan
• Out of Band Integration
| 90 days after Acceptance of CIM6 | |||||
| CIM10 | CCE | Core Capability Enablement (FRD Section 2) | • Legacy Records Migration Plan * | ||
| • Records Disposition Schedule *** | 15 days after Acceptance of CIM9 | ||||
| CIM11 | ATO | Authority to Operate (ATO) | • Business Impact Analysis ** |
• Contingency Plan *
• Initial Risk Assessment Documentation *
• Security Assessment Plan *
• Security Control Selection Documentation *
• System Definition Document *
• System Security Plan *
• System Security Plan Analysis *
| • Threat Assessment * | 30 days after Acceptance of CIM10 | ||||
| Test & Evaluation Milestones | TEM1 | TEP | Test & Evaluation Planning & Facilitation | • Test Plans ** |
• Test Environment(s) Idenfiyed **
| • Test & Evaluation Requirements Compliance Matrix (FRD Section 10 Test & Evaluation) ** | 10 days after Acceptance of CIM11 | ||||
| TEM2 | CS-TE | Cybersecurity T&E Activities / CSP Interoperability & Integration Testing | • Cybersecurity Requirements Definition ** |
• Change Management Documentation (including Risk Analysis) **
• Continuous Monitoring Test Plan **
• Incident Response Plan and Procedures **
| 30 days after Acceptance of TEM1 | ||||
| TEM3 | IAT | Integration & Acceptance Testing (I/AT) | • I/AT for FRD Section 2 (Core System Requirements) * |
• I/AT for FRD Section 3 (System Wide Requirements) *
• I/AT for FRD Section 4 (DoDIN Protection) *
• I/AT for FRD Section 7 (Core Service Support Functions & Integration Points) *
| • I/AT for FRD Section 9 (Performance Objectives and Environmental Metrics) * | 60 days after Acceptance of TEM1 | |||||
| TEM4 | LUT/OA | Limited User Test / Operational Assessment (LUT/OA) | • LUT Risk Assessment Report (based on Government conducted LUT) ** | 30 days after Acceptance of TEM4 | ||
| TEM5 | IOT&E | Initial Operational Test & Evaluation | • Recommended Production Configuration Changes ** |
• Cloud Infrastructure and Workload assessment report **
| 15 days after Acceptance of TEM5 | |||||
| TEM6 | FOT&E | Follow-on Operational Test & Evaluation | • FOT&E Risk Assessment Report (based on Government conducted FOT&E) ** | 45 days after Acceptance of TEM6 | |
| Deployment Milestones | IOC1 | LUD | Limited Deployment User Testing | • Limited Fielding Implementation Plan * |
• Configuration Definition (i.e. – “As Built”) *
• Defect Tracking List *
| 45 days after Acceptance of TEM6 | |||||
| IOC2 | LDD-CC | Core Capabilities Deployment (LDD Decision) | Limited Deployment Decision Notice *** | 5 days after Acceptance of IOC1 | |
| IOC4 | IOC | Initial Operational Capability | IOC Declaration Notice *** | 5 days after Acceptance of IOC3 | |
| FOC1 | FDD | Full Deployment Decision | Full Deployment Decision Notice *** | 5 days after Acceptance of IOC4 | |
| FOC3 | LDD-INT | Optional Integration Points Deployment (LDD Decision) | 20 days after Acceptance of FOC1 | ||
| FOC4 | FOC | Final Operational Capability (DISA Core Capabilities + Integration Points) | FOC Declaration Notice *** | 5 days after Acceptance of FOC2 | |
| Sustainment Milestones | SM1 | SUS | Sustainment | • Evergreen Strategy ** |
• Updated System Baseline **
• Updated Configuration Baseline **
• Usage Reports (by feature capability) **
• Incident Reports **
• FISMA Reporting and Updates **
| • FEDRAMP Reporting and Updates ** | Ongoing after FOC Declaration until the end of the contract |
| Legend: | |
| * - 50% Government responsibility and 50% contractor responsibility | |
| ** - 100% Contractor responsibility | |
| *** - 100% Government responsibility |