Questions 14 - 15
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers 2.pdf | ||
| Final SOO for ARSOSSA and TAPO Racks 6-14-10.docx | DOCX document | |
| Rack drawings A1 B1 C1.pdf | ||
| Questions and Answers.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers 3
Question 14. The description on the SOO and related drawings totals to a different quantity of material list than the list requested on the solicitation. Which material list should be included in the lump sum totals?
Answer: Use the material list noted for CLIN 1 and 2. Numbers/Quantities are correct. Only one error was noted in the SOO, Phase 2, Bldg 195, Cantilever Racks, Para. c.
The following is changed from:
c. Install uprights with two (2) 60” braces between uprights (marked by an “X” on the drawing);
install four (4) straight arms on each upright;
to:
c. Install uprights with two (2) 60” braces between uprights (marked by an “X” on the drawing);
install five (5) straight arms on each upright;
Question 15. The change posted on 15 Jun 10 leaves only 96 each 10' beams for line item 2.
Please confirm that the requirements changed.
Answer: 96 ea - 10'-0" beams is correct as noted in CLIN 2. See Answer 14 above.