This document is a Standard Form 30 (SF 30) Amendment to Solicitation H9224025RE002 for the Integrated Electronic Security System (IESS) Services Request for Proposal (RFP) issued by the Naval Special Warfare Command. The amendment extends the proposal response due date from 09 Jul 2025 to 21 Jul 2025 at 12:00 PM EST and includes several key modifications: updating the Performance Work Statement, correcting administrative errors, updating the Exhibit Line Item Number (ELIN) Spreadsheet, and providing clarifications to the Price Evaluation process.

The amendment adds two Federal Acquisition Regulation (FAR) clauses related to Economic Price Adjustment for Standard and Semistandard Supplies (52.216-2 and 52.216-3), which allow for potential price adjustments based on established catalog or market prices, with increases limited to 10% of the original contract unit price. The document also updates the list of attachments, which includes 13 documents such as the Performance Work Statement, ELIN Spreadsheets, Task Order Requirements, Wage Determinations, and a Quality Assurance Surveillance Plan (QASP). A new clause regarding Covered Telecommunications Equipment or Services-Representation (52.204-26) was added, and other administrative representations and certifications were modified.

View the file

Other files

File Type Posted
Solicitation Amendment - H9224025RE0020001 FINAL.pdf PDF
Attachment 1 - Performance Work Statement.pdf PDF
Attachment 6 - Past and Present Performance Information Sheet 2025.pdf PDF
Attachment 8 - Wage Determination (CA)1.pdf PDF
Attachment 2 - Exhibit LineItem Number (ELIN) Spreadsheet - Final.xlsx XLSX spreadsheet
Attachment 5 - Task Order 01 PWS.pdf PDF
Attachment 11 - Wage Determination (VA)1.pdf PDF
Attachment 4 - DD254.pdf PDF
Attachment 9 - Wage Determination (HI)1.pdf PDF
Attachment 10 - Wage Determination (MS)1.pdf PDF
Attachment 12 - Quality Assurance Surveillance Plan.pdf PDF
Attachment 7- Past and Present Performance Questionnaire 2025.pdf PDF
Attachment 3 - First TO Exhibit Line Item Number (ELIN) Spreadsheet.xlsx XLSX spreadsheet
Attachment 13 - QNA.pdf PDF
H9224025RE002 Final 06.09.pdf PDF
Attachment 10 - Wage Determination (MS).pdf PDF
Attachment 8 - Wage Determination (CA).pdf PDF
Attachment 6 - Past and Present Performance Information Sheet 2025.pdf PDF
Attachment 3 - First TO Exhibit Line Item Number (ELIN) Spreadsheet.xlsx XLSX spreadsheet
Attachment 11 - Wage Determination (VA).pdf PDF
Attachment 2 - Exhibit LineItem Number (ELIN) Spreadsheet - Final.xlsx XLSX spreadsheet
Attachment 12 - Quality Assurance Surveillance Plan.pdf PDF
Attachment 7- Past and Present Performance Questionnaire 2025.pdf PDF
Attachment 5 - Task Order 01 PWS.pdf PDF
Attachment 9 - Wage Determination (HI).pdf PDF
Attachment 4 - DD254.pdf PDF
Attachment 1 - Performance Work Statement.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Solicitation/Contract Form

The following changes have been made:

INFORMATION FROM TO

Response Due Date 09 Jul 2025 21 Jul 2025

Contract Clauses

Additional Information/Notes

The following clauses were added:

FAR Clauses Incorporated by Full Text

52.216-2 Economic Price Adjustment-Standard Supplies. (Nov 2021)

Economic Price Adjustment-Standard Supplies (Nov 2021)

The Contractor warrants that the unit price stated in the Schedule (Attachment 2 - Exhibit Line Item Number (ELIN) Spreadsheet) for ELINs (a) AB001-HB049 is not in excess of the Contractor's applicable established price in effect on the contract date for like quantities of the same item. The term "unit price" excludes any part of the price directly resulting from requirements for preservation, packaging, or packing beyond standard commercial practice. The term "established price" means a price that-

Is an established catalog or market price for a commercial product sold in substantial quantities to the general public; and(1)

Is the net price after applying any standard trade discounts offered by the Contractor.(2)

The Contractor shall promptly notify the Contracting Officer of the amount and effective date of each decrease in any applicable established price. (b) Each corresponding contract unit price shall be decreased by the same percentage that the established price is decreased. The decrease shall apply to those items delivered on and after the effective date of the decrease in the Contractor's established price, and this contract shall be modified accordingly.

If the Contractor's applicable established price is increased after the contract date, the corresponding contract unit price shall be increased, upon (c) the Contractor's written request to the Contracting Officer, by the same percentage that the established price is increased, and the contract shall be modified accordingly, subject to the following limitations:

The aggregate of the increases in any contract unit price under this clause shall not exceed 10 percent of the original contract unit price.(1)

The increased contract unit price shall be effective-(2)

On the effective date of the increase in the applicable established price if the Contracting Officer receives the Contractor's written request within 10 (i) days thereafter; or

If the written request is received later, on the date the Contracting Officer receives the request.(ii)

The increased contract unit price shall not apply to quantities scheduled under the contract for delivery before the effective date of the increased (3) contract unit price, unless failure to deliver before that date results from causes beyond the control and without the fault or negligence of the Contractor, within the meaning of the Default clause.

H9224025RE0020001

No modification increasing a contract unit price shall be executed under this paragraph (c) until the Contracting Officer verifies the increase in the (4) applicable established price.

Within 30 days after receipt of the Contractor's written request, the Contracting Officer may cancel, without liability to either party, any (5) undelivered portion of the contract items affected by the requested increase.

During the time allowed for the cancellation provided for in paragraph (c)(5) of this clause, and thereafter if there is no cancellation, the (d) Contractor shall continue deliveries according to the contract delivery schedule, and the Government shall pay for such deliveries at the contract unit price, increased to the extent provided by paragraph (c) of this clause.

(End of clause)

52.216-3 Economic Price Adjustment-Semistandard Supplies. (Nov 2021)

Economic Price Adjustment-Semistandard Supplies (Nov 2021)

The Contractor warrants that the supplies identified as line items AB001-HB049 in the Schedule (Attachment 2 - Exhibit Line Item Number (a) (ELIN) Spreadsheet) are, except for modifications required by the contract specifications, supplies for which it has an established price. The term "established price" means a price that (1)is an established catalog or market price for a commercial product sold in substantial quantities to the general public, and (2)is the net price after applying any standard trade discounts offered by the Contractor. The Contractor further warrants that, as of the date of this contract, any difference between the unit prices stated in the contract for these line items and the Contractor's established prices for like quantities of the nearest commercial equivalents are due to compliance with contract specifications and with any contract requirements for preservation, packaging, and packing beyond standard commercial practice.

The Contractor shall promptly notify the Contracting Officer of the amount and effective date of each decrease in any applicable established price. (b) Each corresponding contract unit price (exclusive of any part of the unit price that reflects modifications resulting from compliance with specifications or with requirements for preservation, packaging, and packing beyond standard commercial practice) shall be decreased by the same percentage that the established price is decreased. The decrease shall apply to those items delivered on and after the effective date of the decrease in the Contractor's established price, and this contract shall be modified accordingly.

If the Contractor's applicable established price is increased after the contract date, the corresponding contract unit price (exclusive of any part of (c) the unit price resulting from compliance with specifications or with requirements for preservation, packaging, and packing beyond standard commercial practice) shall be increased, upon the Contractor's written request to the Contracting Officer, by the same percentage that the established price is increased, and the contract shall be modified accordingly, subject to the following limitations:

The aggregate of the increases in any contract unit price under this clause shall not exceed 10 percent of the original contract unit price.(1)

The increased contract unit price shall be effective-(2)

On the effective date of the increase in the applicable established price if the Contracting Officer receives the Contractor's written request within 10 (i) days thereafter; or

If the written request is received later, on the date the Contracting Officer receives the request.(ii)

The increased contract unit price shall not apply to quantities scheduled under the contract for delivery before the effective date of the increased (3) contract unit price, unless failure to deliver before that date results from causes beyond the control and without the fault or negligence of the Contractor, within the meaning of the Default clause.

No modification increasing a contract unit price shall be executed under this paragraph (c) until the Contracting Officer verifies the increase in the (4) applicable established price.

Within 30 days after receipt of the Contractor's written request, the Contracting Officer may cancel, without liability to either party, any (5) undelivered portion of the contract items affected by the requested increase.

During the time allowed for the cancellation provided for in paragraph (c)(5) of this clause, and thereafter if there is no cancellation, the (d) Contractor shall continue deliveries according to the contract delivery schedule, and the Government shall pay for such deliveries at the contract unit price, increased to the extent provided by paragraph (c) of this clause.

(End of clause)

The following clauses were deleted:

DFARS Clauses Incorporated by Reference

Number Title Effective Date Alternate/ Deviation

Variation Effective Date

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting.

(DEVIATION 2024-O0013 REVISION 1)

May 2024 Deviation 2024-O0013 May 2024

List of Attachments

Miscellaneous text in this section has been modified to:

Attachments:

Attachment 1 - Performance Work Statement

Attachment 2 - Exhibit Line Item Number (ELIN) Spreadsheet

Attachment 3 - First Task Order Exhibit Line Item Number (ELIN) Spreadsheet

Attachment 4 - DD254

Attachment 5 - Task Order 01 Requirement

Attachment 6 -Past and Present Performance Information Sheet

Attachment 7- Past and Present Performance Questionnaire

Attachment 8 - Wage Determination (CA)

Attachment 9 - Wage Determination (HI)

Attachment 10 - Wage Determination (MS)

Attachment 11 - Wage Determination (VA)

Attachment 12 - Quality Assurance Surveillance Plan (QASP)

Attachment 13 - QNA

Representations, Certification, & Other Statements

The following clauses were added:

FAR Clauses Incorporated by Reference

Number Title Effective Date Alternate/ Deviation

Variation Effective Date

52.204-26 Covered Telecommunications Equipment or Services-Representation. Oct 2020

The following clauses were deleted:

FAR Clauses Incorporated by Full Text Offeror Representations and Certifications-Commercial Products and Commercial

52.212-3 Services. (Alternate I) (May 2024) Alternate I (Feb 2024)

Alternate I . As prescribed in (b)(2), add the following paragraph (c)(12) to the basic provision:(FEB 2024) 12.301

(12) (Complete if the offeror has represented itself as disadvantaged in paragraph (c)(5) of this provision.)

Black American.

Hispanic American.

Native American (American Indians, Eskimos, Aleuts, or Native Hawaiians).

Asian-Pacific American (persons with origins from Burma, Thailand, Malaysia, Indonesia, Singapore, Brunei, Japan, China, Taiwan, Laos, Cambodia (Kampuchea), Vietnam, Korea, The Philippines, Republic of Palau, Republic of the Marshall Islands, Federated States of Micronesia, the Commonwealth of the Northern Mariana Islands, Guam, Samoa, Macao, Hong Kong, Fiji, Tonga, Kiribati, Tuvalu, or Nauru).

Subcontinent Asian (Asian-Indian) American (persons with origins from India, Pakistan, Bangladesh, Sri Lanka, Bhutan, the Maldives Islands, or Nepal).

Individual/concern, other than one of the preceding.

IDCode: J
Page: 1
Pages: 5
AmendNo: 0001
EffDate: 30 Jun 2025
ReqNo:
ProjNo:
IssCode: H92240
AdmCode:
IssuedBy: NAVAL SPECIAL WARFARE COMMAND

3632 GUADALCANAL ROAD, BLDG 165

SAN DIEGO, CA 92155-5583

UNITED STATES

Jackson Gabriel, Email: jackson.t.gabriel.civ@socom.mil Telephone: 8139392874 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: H9224025RE002
SolDate: 25 Jun 2025
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: See Section G - Contract Administration Data
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: Purpose of amendment: A) Extend the proposal due date to 21 July 2025 at 12:00 PM EST B) Correct administrative error(s) within RFP relating to Attachment numbering. C) Update Attachment 1 - Performance Work Statement D) Update and clarify Price Evaluation process; Specifically, Attachment 3- First TO Exhibit Line Item Number (ELIN) Spreadsheet calculations. E) Provide Question and Answer (QNA) documentation as Attachment 13 of Solicitation.
ContNameTitle:
CoNameTitle:
ContDate:
CODate:
52:
212-3_cb3-aI: Off
dummyFieldName1:
212-3_cb4-aI: Off
dummyFieldName2:
212-3_cb6-aI: Off
dummyFieldName3:
212-3_cb2-aI: Off
dummyFieldName4:
212-3_cb5-aI: Off
dummyFieldName5:
212-3_cb1-aI: Off

File details come from the government source that posted it. Updated .