About this file
This product description outlines requirements for ballistic rubber panels for Naval Special Warfare Command close quarters combat training facilities. Naval Special Warfare Command seeks to procure 8,990 rubber ballistic panels measuring 2 feet by 2 feet by 2 inches for facilities at Joint Expeditionary Base Fort Story in Virginia. The flip lock panels have a 1-inch overlapping inset perimeter allowing installation on either side. The vulcanized rubber panels must be original equipment manufacturer items not assembled from other components. Delivery of all items is required within 90 days of award to the address provided. The government reserves the right to perform quality assurance inspections and will conduct oversight in an objective and consistent manner.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| H92240-21-T-0029 0002.pdf | ||
| REVISED ADD 03 Brand Name (FARCO) FAR 13 5_Redacted.pdf | ||
| H92240-21-T-0029 0001 (AMENDMENT).pdf | ||
| REVISED Addenda 01- Product Description FARCO HDPE.pdf | ||
| Addenda 01 PWS - (Revised 05.06.2021).pdf | ||
| RESPONSE TO QUESTIONS RECEIVED.pdf | ||
| PWS Appendix 2.pdf | ||
| Addenda 03- Past Performance Information Sheet.docx | DOCX document | |
| Addenda 01 PWS - Rubber Flip-Lock Tiles Instl.pdf | ||
| H92240-21-T-0029.pdf | ||
| PWS Appendix 3.pdf | ||
| Addenda 04 - SCA Wage Determination (Virginia).pdf | ||
| Addenda 02 - Pricing Sheet.xlsx | XLSX spreadsheet |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRODUCT DESCRIPTION
Naval Special Warfare Command
CQC Rubber Tile Replacement JEBFS
1. BACKGROUND: Currently the bullet containment system Close Combat Training Facility at the Joint Expeditionary Base Fort Story requires maintenance. Rubber belting is required to maintain and sustain the AR500 ½” ballistic steel plates. NSW Range Enterprise is standardizing all Close Quarter Combat training facilities with flip-lock rubber tile, 2’ x 2” x 2” flip-lock rubber tiles as part of the containment system.
2. OBJECTIVE: Establish a contract to provide materiel for rubber tile flip-lock tiles for two east coast range sites. The award of a contracting vehicle will include the base award for the Single-Story Close Quarter Combat training facility and the Multi-Story Close Quarter Combat Training Facility. Both facilities are located at Fort Story, Virginia.
3. DESCRIPTION OF REQUIREMENT
3.1. Description and Capabilities: A ballistic rubber panel with a 1" x1" inset around the perimeter. The panel has a textured surface on both sides to allow the panel to be "flipped" and seat with the panels adjacent to it. This safety feature prevents gapping at the seams where rounds can escape control. This design also minimizes waste, where a section can merely flip over to fit in another area of the ballistic control system. Item is a 2" x 2' x 2' "flip lok" rubber panels with overlapping perimeter
3.2. Specifications/Salient Characteristics: Ballistic rubber is used to prevent escapes and ricochets in gun training ranges. Rubber can stop some rounds (depending on the thickness) but usually not. The rubber allows the bullets to pass through it and then strike a hard surface. Then its energy and original shape are lost so it safely comes to rest between the rubber and the hard surface (usually steel). Panels are manufactured with a 1" x1" inset around the perimeter. The panel has a textured surface on both sides to allow the panel to be "flipped" and seat with the panels adjacent to it. This safety feature prevents gapping at the seams where rounds can escape control. This design also minimizes waste, where a section can merely flip over to fit in another area of the ballistic control system.
3.3. Ballistic Panels with the following specifications:
• 2" x 2' x 2' "flip lok" rubber panels with overlapping perimeter
• 1” overlapping inset perimeter that allows the panel to be flipped or installed on either side.
• Manufactured as a vulcanized rubber panel or tile
• Manufactured as an original item not ground or shaped from composite or assembled components
3.4. Quantity:
DESCRIPTION Manufacturer Part Number U/I QTY Rubber Ballistic Panels N/A EA 8990
4. DELIVERY INFORMATION
4.1. Required delivery date: 90 days after award
4.2. Delivery POC Name: Ronnie Blevins, 757-763-2405 Ronnie.blevins@socom.mil
4.3. Delivery address: Joint Expeditionary Base Fort Story, Virginia Beach, VA 23451.
4.4. Special instructions: Contractor shall coordinate with point of contact relating to base access and specific delivery location and instructions.
5. QUALITY ASSURANCE
5.1. The Government reserves the right to perform inspections and surveillance to evaluate the Contractor’s compliance to the contract terms to include proper delivery of quantity and type of goods. The Government will make every effort to ensure that the surveillance methods used are conducted in an objective, fair, and consistent manner.
File details come from the government source that posted it. Updated .