H. Schedule of Submittals.xlsx
XLSX spreadsheet 32 KB Posted
- Attached to
- MXDP 23-5000 Renovate Silver Wings, B308
- Solicitation number
- FA309926Q0022
About this file
This is a Schedule of Submittals document that outlines all required contractor submissions for the MXDP 23-5000 project to renovate Silver Wings, Building 308 at Laughlin Air Force Base. The schedule is organized into three phases: NTP 1 (Design), NTP 2 (Pre-Construction), and NTP 3 (Construction), with 42 line items detailing specific deliverables, submission requirements, and deadlines.
During the Design phase, the contractor must submit design packages at 15%, 65%, 95%, and 100% completion milestones, with each successive submittal required within specified timeframes following government approval of the prior phase. Pre-Construction submittals include safety documentation (contractor safety plan, QC manager qualifications, QC plan), regulatory compliance items (hazardous material approvals, TCEQ water system notifications, asbestos abatement plans), and site documentation (construction site plan, records of existing conditions). The Construction phase requires ongoing submissions including hazardous waste manifests, monthly hazmat usage logs, weekly QC daily inspection reports, biweekly progress schedules and meeting minutes, materials testing reports, and final deliverables such as as-built drawings, operation and maintenance data, DD Form 1354, and a construction warranty management plan. Most submittals require both digital copies and specified quantities of paper copies (typically 2-3), with submission dates ranging from 2 weeks prior to base access through 2 weeks after final inspection. The document serves as a template with fields for the Project Engineer and Contract Administrator to complete contract-specific information.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXDP 23-5000 PROJECT TITLE Renovate Silver Wings, B308 SOLICITATION / CONTRACT NO.
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | C = Construction Project D = Design Project | LAUGHLIN DIV 01 SPECIFICATIONS | ENVIRONMENTAL QUALITY CONSTRUCTION SPECIFICATIONS LAFB | STATEMENT OF OBJECTIVES | NUMBER OF PAPER COPIES REQUIRED. DIGITAL COPIES ARE REQUIRED FOR ALL SUBMITTALS | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS |
APPR
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
DIS
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
| NTP 1 - Design | |||||||
| 1 | Entry Access List (EAL) | D | 1.8.2 | 2 Weeks prior to base access | |||
| 2 | Proof of OPSEC Training | D | 2.4 | 2 Weeks prior to base access | |||
| 3 | Sive visit Agenda | D | within 7 Days after NTP 1 | ||||
| 4 | Summary of site investigation | D | NLT 21 Days after NTP 1 | ||||
| 5 | 15% Design Package | D | NLT 49 calendar days after NTP1 | ||||
| 6 | 65% Design Package | D | 5.2.1 | 2 (drawings only) | NLT 42 calendar days after NTP1 | ||
| 7 | 95% Design Package | D | 5.2.2 | 2 (drawings only) | NLT 35 calendar days after Government approved 65% design submittal | ||
| 8 | 100% Design Package | D | 5.2.3 | 2 (drawings only) | NLT 28 calendar days after Government approved 95% design submittal | ||
| 9 | Progress Schedule Form and Contract Progress Report | C, D | 6.1.1 | Biweekly | |||
| 10 | Meeting Minutes | D | 6.2.1 | NLT 3 Days after meeting | |||
| NTP 2 - Pre Construction | |||||||
| 11 | Entry Access List (EAL) | C | 1.8.2 | 2 Weeks prior to base access | |||
| 12 | Proof of OPSEC Training | C, D | 2.4 | 2 weeks prior to base access | |||
| 13 | Contractor Safety Plan | C | 3.2.2 | 3.4.2.2 | NLT 30 days after NTP 2 | ||
| 14 | Certificate of Contractor Safety Compliance | 3.2.3 | NLT 7 days after NTP 2 | ||||
| 15 | QC Manager Qualifications | C, D | 4.2.3 | 3.1.2 | NLT 7 days after NTP 2 | ||
| 16 | QC Plan | C, D | 4.2.4 | NLT 30 days after NTP 2 | |||
| 17 | Construction Site Plan | 12.1 | NLT 30 days after NTP 2 | ||||
| 18 | Hazardous Material Approval (Safety Data Sheets) | C | 3.2.1 | NLT 30 days after NTP 2 (as required) | |||
| 19 | Hazardous Waste Training Certificate | 3.2.2 | Prior to NTP 3 |
(as required) 20 Hazardous Waste / Material Procedures 3.2.2 Prior to NTP 3 (as required)
| 21 | Public Water System Notification | 3.4.1 | NLT 30 days after NTP 2 (as required) |
| 22 | Customer Service Inspection Certificate (TCEQ Form 20699) | 3.4.1 | Prior to NTP 3 |
(as required) 23 TCEQ Public water system plan review submittal form (TCEQ Form 10233) 3.4.1 Prior to NTP 3 (as required) 24 Clean Water Act TCEQ’s General Permit 3.4.2 Prior to NTP 3 (as required)
| 25 | Asbestos Hazard Abatement Plan | 3.5.2.1 | NLT 10 days prior to construction start |
| 26 | Copy of notification to Department of State Health Services | 3.5.2.1 | NLT 10 days prior to construction start |
| 27 | Worker/Area Protection Plan | 3.5.2.2 | Prior to NTP 3 |
(as required)
| 28 | Records of Existing Conditions | C, D | 1.5, 7.1.1 | 2.4 | NLT 30 Days after NTP 2 | ||
| 29 | Non-Hazardous Waste Disposal Manifest and/or Waste Shipment Record | C | 5.1 / 6.2 | NLT 45 days from the date of signature of receiving facility | |||
| 30 | Submittals per Contractor's Design SOW | D | 10.4.4 through 10.4.11 | TBD | |||
| NTP 3 - Construction | |||||||
| 31 | Hazardous Waste Disposal Manifests | C | 5.2 / 6.2 | As required, prior to removal from Government property | |||
| 32 | Hazmat Usage Log | C | 6.1 | End of each month during construction | |||
| 33 | QC Daily Inspection Reports | C | 4.2.6 | Weekly | |||
| 34 | Progress Schedule Form and Contract Progress Report | C | 6.1 | Biweekly | |||
| 35 | Meeting Minutes | C | 6.2.1 | NLT 3 Days after meeting | |||
| 36 | Materials Testing | C | 7.1.3 | As required, within 7 days of test | |||
| 37 | Operation and Maintenance Data | C | 10.4.12 | NLT 2 weeks after Final Inspection | |||
| 38 | As Built Drawings/CAD Files | C | 10.4.13 | 2 (D size) | NLT 2 weeks after Final Inspection | ||
| 39 | Completion Inspection (QC Manager Punchlist) | C | 13.4 | NLT 3 days after Pre-Final Inspection | |||
| 40 | Draft DD Form 1354 | C | 13.3 | Prior to Pre-Final Inspection | |||
| 41 | Final DD Form 1354 | C | 13.3 | At Final Inspection | |||
| 42 | Construction Warranty Management Plan | C | 13.2 | NLT 2 weeks after Final Inspection | |||
| Schedule of Submittals Template, Feb 05 (SAF/AQCP) |
Task Order # FA3099-16-D-0002-0002 SOW Atch 2
&"Times New Roman,Regular"&12Page &P of &N
File details come from the government source that posted it. Updated .