H. Schedule of Submittals.xlsx

XLSX spreadsheet 32 KB Posted

Attached to
MXDP 23-5000 Renovate Silver Wings, B308
Solicitation number
FA309926Q0022
Issued by

About this file

This is a Schedule of Submittals document that outlines all required contractor submissions for the MXDP 23-5000 project to renovate Silver Wings, Building 308 at Laughlin Air Force Base. The schedule is organized into three phases: NTP 1 (Design), NTP 2 (Pre-Construction), and NTP 3 (Construction), with 42 line items detailing specific deliverables, submission requirements, and deadlines.

During the Design phase, the contractor must submit design packages at 15%, 65%, 95%, and 100% completion milestones, with each successive submittal required within specified timeframes following government approval of the prior phase. Pre-Construction submittals include safety documentation (contractor safety plan, QC manager qualifications, QC plan), regulatory compliance items (hazardous material approvals, TCEQ water system notifications, asbestos abatement plans), and site documentation (construction site plan, records of existing conditions). The Construction phase requires ongoing submissions including hazardous waste manifests, monthly hazmat usage logs, weekly QC daily inspection reports, biweekly progress schedules and meeting minutes, materials testing reports, and final deliverables such as as-built drawings, operation and maintenance data, DD Form 1354, and a construction warranty management plan. Most submittals require both digital copies and specified quantities of paper copies (typically 2-3), with submission dates ranging from 2 weeks prior to base access through 2 weeks after final inspection. The document serves as a template with fields for the Project Engineer and Contract Administrator to complete contract-specific information.

View the file

Other files

File Type Posted
Solicitation Amendment FA309926Q00220001 SF 30.pdf PDF
5. MXDP 23-5000 SOW_20260605 (1).docx DOCX document
RFIs - Silver Wings B308 (1).xlsx XLSX spreadsheet
Drain kitchen.jpeg JPEG file
5. MXDP 23-5000 SOW_20260605.docx DOCX document
IMG_6241.jpeg JPEG file
Drain 1st floor(1).jpeg JPEG file
Drain 1st floor(3).jpeg JPEG file
Main Panel.jpeg JPEG file
Cicuit Directory.jpeg JPEG file
P-2 Switch.jpeg JPEG file
Drain prep area.jpeg JPEG file
Drain kitchen sink.jpeg JPEG file
Drain 1st floor(2).jpeg JPEG file
Solicitation - FA309926Q0022.pdf PDF
D. Environmental Quality Specifications.pdf PDF
E. Building 308 Existing Site Photographs.pdf PDF
G. FFE List.pdf PDF
A. Building 308 Floor Plan.pdf PDF
1. MXDP 23-5000 SOW.pdf PDF
2. TX20260186 – Building - 02 January 2026.pdf PDF
I. Progress Schedule and Progress Report.xlsx XLSX spreadsheet
B. Division 01 Specification Guidelines.pdf PDF
C. Laughlin AFB Installation Facilities Standards.pdf PDF
F. Conceptual Design Layout.pdf PDF
J. 47 CES As-Built Deliverable Requirements.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXDP 23-5000 PROJECT TITLE Renovate Silver Wings, B308 SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALC = Construction Project D = Design ProjectLAUGHLIN DIV 01 SPECIFICATIONSENVIRONMENTAL QUALITY CONSTRUCTION SPECIFICATIONS LAFBSTATEMENT OF OBJECTIVESNUMBER OF PAPER COPIES REQUIRED. DIGITAL COPIES ARE REQUIRED FOR ALL SUBMITTALSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS

APPR

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

DIS

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

NTP 1 - Design
1Entry Access List (EAL)D1.8.22 Weeks prior to base access
2Proof of OPSEC TrainingD2.42 Weeks prior to base access
3Sive visit AgendaDwithin 7 Days after NTP 1
4Summary of site investigationDNLT 21 Days after NTP 1
515% Design PackageDNLT 49 calendar days after NTP1
665% Design PackageD5.2.12 (drawings only)NLT 42 calendar days after NTP1
795% Design PackageD5.2.22 (drawings only)NLT 35 calendar days after Government approved 65% design submittal
8100% Design PackageD5.2.32 (drawings only)NLT 28 calendar days after Government approved 95% design submittal
9Progress Schedule Form and Contract Progress ReportC, D6.1.1Biweekly
10Meeting MinutesD6.2.1NLT 3 Days after meeting
NTP 2 - Pre Construction
11Entry Access List (EAL)C1.8.22 Weeks prior to base access
12Proof of OPSEC TrainingC, D2.42 weeks prior to base access
13Contractor Safety PlanC3.2.23.4.2.2NLT 30 days after NTP 2
14Certificate of Contractor Safety Compliance3.2.3NLT 7 days after NTP 2
15QC Manager QualificationsC, D4.2.33.1.2NLT 7 days after NTP 2
16QC PlanC, D4.2.4NLT 30 days after NTP 2
17Construction Site Plan12.1NLT 30 days after NTP 2
18Hazardous Material Approval (Safety Data Sheets)C3.2.1NLT 30 days after NTP 2 (as required)
19Hazardous Waste Training Certificate3.2.2Prior to NTP 3

(as required) 20 Hazardous Waste / Material Procedures 3.2.2 Prior to NTP 3 (as required)

21Public Water System Notification3.4.1NLT 30 days after NTP 2 (as required)
22Customer Service Inspection Certificate (TCEQ Form 20699)3.4.1Prior to NTP 3

(as required) 23 TCEQ Public water system plan review submittal form (TCEQ Form 10233) 3.4.1 Prior to NTP 3 (as required) 24 Clean Water Act TCEQ’s General Permit 3.4.2 Prior to NTP 3 (as required)

25Asbestos Hazard Abatement Plan3.5.2.1NLT 10 days prior to construction start
26Copy of notification to Department of State Health Services3.5.2.1NLT 10 days prior to construction start
27Worker/Area Protection Plan3.5.2.2Prior to NTP 3

(as required)

28Records of Existing ConditionsC, D1.5, 7.1.12.4NLT 30 Days after NTP 2
29Non-Hazardous Waste Disposal Manifest and/or Waste Shipment RecordC5.1 / 6.2NLT 45 days from the date of signature of receiving facility
30Submittals per Contractor's Design SOWD10.4.4 through 10.4.11TBD
NTP 3 - Construction
31Hazardous Waste Disposal ManifestsC5.2 / 6.2As required, prior to removal from Government property
32Hazmat Usage LogC6.1End of each month during construction
33QC Daily Inspection ReportsC4.2.6Weekly
34Progress Schedule Form and Contract Progress ReportC6.1Biweekly
35Meeting MinutesC6.2.1NLT 3 Days after meeting
36Materials TestingC7.1.3As required, within 7 days of test
37Operation and Maintenance DataC10.4.12NLT 2 weeks after Final Inspection
38As Built Drawings/CAD FilesC10.4.132 (D size)NLT 2 weeks after Final Inspection
39Completion Inspection (QC Manager Punchlist)C13.4NLT 3 days after Pre-Final Inspection
40Draft DD Form 1354C13.3Prior to Pre-Final Inspection
41Final DD Form 1354C13.3At Final Inspection
42Construction Warranty Management PlanC13.2NLT 2 weeks after Final Inspection
Schedule of Submittals Template, Feb 05 (SAF/AQCP)

Task Order # FA3099-16-D-0002-0002 SOW Atch 2

&"Times New Roman,Regular"&12Page &P of &N