RFIs - Silver Wings B308 (1).xlsx

XLSX spreadsheet 35 KB Posted

Attached to
MXDP 23-5000 Renovate Silver Wings, B308
Solicitation number
FA309926Q0022
Issued by

About this file

This file is a Request for Information (RFI) Q&A document containing 112 questions and government responses related to the Silver Wings B308 renovation solicitation (FA309926Q0022) at Laughlin Air Force Base. The RFI addresses critical project clarifications across multiple disciplines including architectural, structural, mechanical, electrical, plumbing, fire protection, communications, and interior finishes work.

The project involves renovating a restaurant facility (Silver Wings) in Building 308, with an estimated budget range of $750,000 to $1,250,000. Key scope elements include kitchen reconfiguration with wall relocation to create additional prep space, dining area refresh with new flooring and finishes, installation of new kitchen equipment, replacement of ceiling tiles and window film, new data/communications infrastructure (Cat VI cabling for Point of Sale systems and monitors), electrical panel upgrades, mechanical system adjustments, and installation of solid surface finishes and wood-stained elements. The government clarified that no as-built drawings are available; contractors must rely on floor plans and site inspections for confirmation of existing conditions. Critical responses confirm that exterior patio work and thermostat replacement are out of scope, asbestos remediation qualifies as an unforeseen condition, buy-in to existing electrical/mechanical systems is permitted, and utility costs are covered by Laughlin AFB. The project requires RSMeans pricing submissions, site-specific permits per AF Form 103, compliance with base access procedures, and selection from government-approved submittals for wood finishes and materials. Project working hours are 7:30 AM–4:30 PM with prior approval required for extended hours.

View the file

Other files

File Type Posted
Solicitation Amendment FA309926Q00220001 SF 30.pdf PDF
5. MXDP 23-5000 SOW_20260605 (1).docx DOCX document
P-2 Switch.jpeg JPEG file
Drain kitchen.jpeg JPEG file
5. MXDP 23-5000 SOW_20260605.docx DOCX document
IMG_6241.jpeg JPEG file
Drain 1st floor(1).jpeg JPEG file
Drain 1st floor(3).jpeg JPEG file
Main Panel.jpeg JPEG file
Cicuit Directory.jpeg JPEG file
Drain prep area.jpeg JPEG file
Drain kitchen sink.jpeg JPEG file
Drain 1st floor(2).jpeg JPEG file
Solicitation - FA309926Q0022.pdf PDF
1. MXDP 23-5000 SOW.pdf PDF
2. TX20260186 – Building - 02 January 2026.pdf PDF
H. Schedule of Submittals.xlsx XLSX spreadsheet
I. Progress Schedule and Progress Report.xlsx XLSX spreadsheet
D. Environmental Quality Specifications.pdf PDF
E. Building 308 Existing Site Photographs.pdf PDF
G. FFE List.pdf PDF
A. Building 308 Floor Plan.pdf PDF
B. Division 01 Specification Guidelines.pdf PDF
C. Laughlin AFB Installation Facilities Standards.pdf PDF
F. Conceptual Design Layout.pdf PDF
J. 47 CES As-Built Deliverable Requirements.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI

RFI #DisciplineReferenceQuestionQuestionQuestionQuestionQuestionQuestionResponse
1ContractSOW 1.1Can the government please provide a list of required documents to be included/submitted in the bid package on the current due date of Sept.18, 2026 3:00PMPlease refer to the solication, section L for more info on require documents. General we will require the solication and all it attachment back including any amendment to the solictaion.
2ContractSOW 1.1Can the government provide an estimated ROM for this project?The magnitude range for this project is $750,000 to $1,250,000.
3GeneralSOW 1.1Does the government prefer RSmeans or PACES to be submitted for this project?RSMeans is preferred
4ArchitecturalSOW 2.1Can the government please provide any existing as-builts for the areas of work?No As-builts available, only floor plans
5ElectricalSOW 2.4.7Can the Government please confirm which panel is the main disconnect for the subpanel located inside Silver Wings kitchen area?See attachments for panel information
6ElectricalSOW 2.4.7Can the Government please provide a site visit and documentation of the electrical service (disconnect, main panel, and/or Transformer) that services the subpanel located inside Silver Wings kitchen area?See attachments for panel information
7FireSOW 4.1.2.1Can the government provide a site visit and documentation of the current Fire Protection Riser installed for the building that services B308See attachments for panel information
8PlumbingSOW 2.4.7.2Can the government provide a layout of existing plumbing supply and drainage locations into the kitchen area of Silver Wings from the first floor.No As-builts available, only floor plans
9MechanicalSOW 2.4.7.3.Please confirm no test and balancing of HVAC systems after replacement of only the diffusers and intake vents.Minimal with a possible adjustment (minor duct shift), localized balancing (dampers). Depending on the reconfiguration to the kitchen area and prep are wall. There is a return adjacent to the wall in the prep area.
10FFESOW 2.4.7.6 and Attachment F. Conceptual Design:The existing Overhead Rolling Grille at the entrance of Silver Wings Kitchen does not appear in this solicitation, but is shown on pg. 3 of Attachment F. Please confirm the exclusion of this item from either removal and/or replace of the overhead rolling grill.SOW amended, Para. 2.4.7.10.3
11GeneralSOW 2.4.7.6.2Please confirm that “All outside corners shall be pre-formed” is not specified for the gypsum, but is confirming stainless steel corner guards or some other specific item, please state which items.SOW amended
12ElectricalSOW 4.2.4.8Can the Government please confirm which panel is the main service disconnect for the Dining Area of the solicitation? And provide any documentation.See response for 6
13MechanicalSOW 2.4.8.2Two existing thermostats are present in the dining area on each west facing column called to be “stained solid wood”, with damage observed to the southern thermostat. Please confirm if replacement of these thermostats is Not in the SOW, or if they would need to be replaced or moved for the new finish.Not in scope
14StructuralSOW 2.4.8.3.2.1Cracking, damaged, and uneven flooring substrate was observed in the existing VCT flooring near the patio Aluminum Curtain Wall/ Storefront Door, please confirm the substrate is concrete.To the best of our knowledge there is a metal deck with light concrete over it, under the finished floor. No as-builts available to confirm. Contractor inspection required for confirmation
15StructuralSOW 2.4.8.3.2.1Cracking, damaged, and uneven flooring was observed at the outside patio of the Dining Area. Please confirm this area is not in the scope of work or if the government would like to include flooring and substrate repairs for this area.Replacement of the floor is part of the scope the repair and preparation for the new floor is part of the scope. Repair of the substate is not in scope. Interior work only, Patio not included in scope.
16StructuralSOW 2.4.8.3.2.1Cracking, damaged, and uneven flooring was observed at the outside patio of the Dining Area. If the government would like to include this work, please provide which type of flooring to install and provide information on type of existing substrate.Interior work only, Patio not included in scope
17ArchitecturalSOW 2.4.8.4Corner guards are not included in the dining area in the solicitation; please confirm no corner guards are required for the gypsum corners.Line item is meant to describe a cove base requirement. Requirement moved in Amended SOW
18Interior FinishesSOW 2.4.8.4.2 and attachment F. Conceptual:The southwest corner near the patio door is not called to be “stained solid wood” on pg.1, please confirm it is to remain drywall or if the intent is to match other corners with the solid wood on pg.3 elevation D.Remain Drywall
19Interior FinishesSOW 2.4.8.4.2 and attachment F. Conceptual:What is the preferred type of wood and finish for the “stained solid wood” columns, and preferred material corners?The Government has not pre-selected a final stain color, the Contractor's submittal for the solid wood columns should be based on a durable, commercial-grade. Required submittal of physical samples of the proposed wood species with a minimum of three stain options for Government review and approval. Final selection will be made by the Government from these submittals. He Government is also open to considering cost-effective alternative materials that provide a cost savings or value to the Government while achieving the same high-durability performance and visual aesthetic, subject to Government review and approval.
20FFESOW 2.4.8.5 and attachment F. Conceptual:On pg.1 of the attachment F., #12 calls for “Solid Surface Window Sill”, but no details are included in the SOW. Please confirm if the government would like to add the windowsills’ to the scope of work.SOW Amended: Para 2.4.8.5.3. added "The Contractor shall install a solid surface window sill to the south and north facing windows."
21Interior FinishesSOW 2.4.8.5.2“The Contractor shall window blind fastener damage to the window frame and paint to match existing” Can the Government please clarify the statement.SOW amended: Para. 2.4.8.5.2. edited to "The Contractor shall repair window blind fastener damage in the window frame and paint to match existing."
22Interior FinishesSOW 2.4.8.5.3:A history of custom window stickers is currently attached to the existing window film called to be replaced in the eastern dining area, does the government want to remove and save these? Or does the contractor disposal of all existing window film as stated?Dispose
23GeneralSOW 2.4.8.6:Two wireless data boxes is located on the dining area ceiling, will the government be removing and reinstalling this data box?Will be removed prior
24GeneralSOW 2.4.8.6:Water damage to the gypsum ceiling was observed in the dining area near the southern facing windows, can the government confirm this leak is no longer active?Leaks have been repaired
25Interior FinishesSOW 2.4.9:Please confirm if the government is open to replacing the existing VCT in the hallway between the “Hallway”, “Dining Area”, and the Southwest corner stairway access.Remain and new hallway work to match
26Interior FinishesSOW 2.4.9:Please confirm if the government is open to replacing the mismatched ceiling tiles in the hallway between “Hallway”, “Dining Area”, and the Southwest corner stairway access.Remain and new hallway work to match
27Interior FinishesSOW 2.4.9.2.1:Due to the importance of the mural at the entrance of Silver Wings, does the government want to include a decorative trim and protective cover in the SOW for the mural?Protect in Place, no additional work
28Interior FinishesSOW 2.4.9.2.1 and Attachment F. Conceptual:A “Stained Solid Wood” column is called on pg.1 of Attachment F. Conceptual to be installed on the mural corner, does the contractor include this in design, or add a gypsum corner guard in its place, or extend the wall beyond the mural to install the wood column?Remove column and remain gypsum and add corner guard. Imitate in opposite wall in order for entrance walls to match
29Interior FinishesCan 6 in. rubber base be installed instead of 4 in. rubber base?4 in rubber base in accordance to the SOW
30ElectricalWhere is the disconnect that feeds the kitchen/restaurant panel located?First floor mechanical room. See attachment
31GeneralWill a dumpster be permitted near the building (covered due to its proximity to the flight line), or will it need to be located at the contractor’s yard?Yes, See attachment 1. Potential Haul Route, Laydown yard and staging area
32ArchitecturalAre as-built drawings available? We would appreciate receiving a copy of the MEP drawings if possible.No as-builts are available
33GeneralWill a temporary soft barrier be allowed to isolate the construction area?If deemed necessary to protect facility occupants (such as dust control measures), yes.
34GeneralCan the elevator be used to transport materials and equipment to and from the construction area?No
35GeneralPlease confirm the project working hours as 7:30 AM – 4:30 PM.Requests to work outside of these hours/days shall be submitted to the Contracting Officer (CO) for approval. Any requests of this type shall be submitted no fewer than three days in advance to when the Contractor plans to work outside of the designated hours. The request shall be submitted with a description of the type of work, the requested days, and the hours for those requested days.
36GeneralIn the event asbestos samples come back positive, should we assume remediation of the affected materials would be handled as an unforeseen site condition?Remediation shall be considered an unforeseen site condition
37ContractShould the Contractor include taxes in the price proposal?Yes, the contractor should included taxes in their proposal unless stated otherwise. Refer to RFO contract clauses 52.229-4
38GeneralPlease confirm if the Superintendent, QC Manager and SSHO must be three separate positions or can the 3 positions be shared by 1 personnel?Dual hat for project superintendent and Quality Control (QC) Manager is acceptable. Due to the proximity of the project to the airfield, Site Safety and Health Officer (SSHO) shall be separate.
39ContractIs this a citizen only project or will documented workers be allowed?This Solication is not a citizen only project, but the project is on a government installation which will require every contractor/worker to meet base access requirement.
40GeneralWill a temporary fence be required around the laydown area?Yes, it is required
41ContractProvide sign‐in sheets for the pre‐bid site walk/meeting.The sign in sheet will be upload along with this site visit Q & A.
42GeneralPlease identify the required permits (local, state or regional) and the acceptance of partial permits for site, underground, foundations, etc.Form AF 103, See SOW para. 2.5.2 & Section 8.B. para. 2.
43GeneralWill temporary electric service be provided for the project or will contractor need to pay and arrange for temporary electrical service?No, the building is energized and power can be used
44ContractWill the government consider moving the proposal due date to 3 weeks beyond allow more time for subcontractor pricing following RFI Period?No the government will not move the proposal due date unless specifiy otherwise.
45ContractWill a second site visit be allowed?Yes, we will coordinate when needed.
46GeneralPlease confirm responsibility for utility connect fees. It is not specified in the RFP. If by contractor, please provide a connection fee allowance the contractor should use for bidding purposes.No connection fee
47GeneralPlease confirm all utility fees for Water & Sewer will be by Contractor or Government?Utilities are covered by Laughlin AFB
48ContractAre their any special base access procedures for labor personnel?Please see Solication, Section I Contract Clauses, Contractor Access to Department of the Air Force Installations, for more detail.
49ContractWil the Govt please provide a Assumptions & Exceptions form?Please send any assumptions/exceptions to the government in writing for approval.
50GeneralPlease provide a POC for CPS Energy and American Water.Utilities are covered by Laughlin AFB
51GeneralAre there on post borrow site for fill and disposal sites for excess soils available?See SOW para. 2.5.2 & Section 8.B. para 12.3 There should not be any excavation or generating of soils
52GeneralWill the Contractor be required to provide any extended warranties (Labor or Equipment)?See SOW section 8.B para 13.2
53ContractWill this project require Buy America or Buy American compliance. If so, please clarify as to which will be required.This project requires Buy America compliance.
54GeneralWhen making changes to the SOW, will the Govt please highlight the changes or change the font color for easily locating the changes?Red and bold
55EnvironmentalWill the Contractor be required to perform a full Hazardous Material Survey inside of the area of construction prior to starting work?No concerns with hazardous materials such as asbestos containing material or lead based paint, building was originally constructed in 2002.
56GeneralWill new exterior signage and/or interior signage be required for this project? No signage found in the scopes.Occupancy signage
57GeneralPlease confirm that the project is not required to meet the ADA accessibility criteria.DoW and other federal installations are governed by the ABA Standards, not the ADA.

See SOW para. 2.4.5.

58ControlsWill cybersecurity be required?What systems are suspected to require cybersecurity? To the best of our knowledge, no part of the scope has a cybersecurity requirement
59CommunicationsWill ISP & OSP communications be required?We do not anticipate any Outside Plant. Inside plant might be required to reconnect the VoIP phone and the wireless access points in the dining area if the existing wiring is damaged. There may be commercial internet service provider cabling required for the Point of Sale systems and the security camera. This would fall under FSS/NAF. DR 47 FSS - Per SOW only Inside Plant (ISP) communications are required for this project.

The contractor must run new data lines (Cat VI conductors) and conduits from the existing COMM box within the kitchen to the new locations for the Point of Sale (POS) stations and various monitors. This work is entirely contained within the Silver Wings restaurant space in building 308.

There is no mention of any Outside Plant (OSP) work. The contract does not require any trenching, laying of new cable between buildings, or modification of the main communication lines that feed the building. The scope is strictly limited to the internal wiring of the renovated area.

60StructuralIs there a raised floor in the area that we are working in?To the best of our knowledge there are no raised floor panels to remove and any work on flooring must be done from the first floor ceiling access area. No as-builts available to confirm. Contractor inspection required for confirmation
61StructuralPlease provide the submittal, and make/model of the raised floor.See response on question 30
62ControlsConfirm BAS/controls system type and integration requirements.Please clarify
63ControlsPlease provide BAS System Make and ModelPlease clarify
64GeneralPlease confirm GSA requirements for disposal of removed equipment and materials. Will a manifest for disposal be required?See SOW para. 2.4.7.10. & section 8. D. para. 6.2
65FireWhat is the make and model of the Fire Alarm?Harrington HS3400
66FireWho is the proprietary system for the Fire Alarm system?Fire Alarm reports to a Monaco receiving system at the Fire Station on Base, not sure if that is answering the question. Please clarify
67FirePlease confirm that the existing Fire Alarm system is not showing any faults.as of 1 Jun 2026 there are no faults, alarms or reportable conditions
68CommunicationsPlease confirm that the Prime is only to install conduit, pull strings and boxes for the Data and Communications for the building end user to finish out the Data cabling and upgrades.The 47 CS will not install cabling for this project, we recommend Inside Plant cabling (CAT6 with T568B wiring scheme) be added to the contract scope. The customer would need to coordinate cabling installation for commercial services (Point of Sale and security cameras). DR. 47 FSS - Yes, the contractor is required to provide, pull, and terminate the data cabling, delivering a complete and functional data connection to the specified locations, not just the infrastructure for future use. The customer (FSS) will not be finishing out the data cabling.
69FireWill 3rd party inspections be required for removing and reinstalling of Fire Alarm devices or swapping out head for Sprinkler Systems?A Fire Protection Engineer to shall be responsible for shop drawings and performing installation. An independent inspection shall be contracted to commission and witness final testing.
71FFEIs the Prime to provide and install the three monitors for the cooking section?Contractor's responsibility - The SOW, under the "Kitchen Area" and "Electrical" subsection, states that the contractor shall: "Provide and install new data conductors and conduits for up to three monitors for the cooking section and food preparation section."
72FireAre fire extinguishers and cabinets required?Fire extinguishers & cabinets are existing. If relocated they need to meet code required coverage.
73Interior DesignPlease clarify what "The Contractor shall window blind fastener damage to the window frame and paint to match existing" is referring to.Para. 2.4.8.5.2. edited to "The Contractor shall repair window blind fastener damage in the window frame and paint to match existing."
74Interior DesignAre Window treatments (blinds) required for the dining area?Per SOW - new window treatments or blinds are not a requirement for the dining area under the base contract. The contractor is only directed to remove and dispose of all existing window shades and blinds, repair any window frame damage left behind by the old fasteners, and install new protective window film with 99% UV protection. Because the SOW explicitly limits the new window scope to the protective film and does not contain a requirement to supply new blinds, the Prime is not responsible for installing new window treatments under the primary scope of work.
75Interior DesignWill the Window Treatments be motorized or manuel?Per SOW - New window treatments are not part of the mandatory base contract, but the Independent Government Estimate (IGE) lists an alternate option for "Mechanical Roll Down Shades." Any shades added under this alternate line item will be manually operated.
76Interior DesignWill the Window Treatments be roll up blinds?Per SOW - new window treatments are not included in the base contract, the project's cost estimate does list an alternate option for "Mechanical Roll Down Shades." These are the same as what you would call roll-up blinds. If this option is selected, the new window treatments will indeed be roll-up style shades.
77Interior DesignHow dark would the Govt like the window treatments to be?Per SOW - the government has provided specific requirements for the darkness and color of the window film, which is a mandatory part of the contract. For the window film, the requirements are:

Darkness: It must have 10% or greater Visual Light Transmittance (VLT). This means at least 10% of visible light must pass through. A lower VLT percentage results in a darker tint.

Color: The film must be Bronze in color.

The contractor is also required to provide samples of the film to the government for final approval.

78GeneralPlease clarify what "All outside corners shall be preformed" means.Line item is meant to describe a cove base requirement. Requirement moved in Amended SOW
79EnvironmentalIs an existing hazardous Material Survey available for pricing the abatement portion of the project?N/A
80ArchitecturalAre As-Builts available for all scopes in the Silver Wings area?See response on question 2
81EnvironmentalIs any mold visibly present?No, if any mold growth is present during the project, recommendation is to remove and treat the mold using a bleach solution and then identifying and addressing moisture sources. Installation cannot perform mold testing, but we can perform air monitoring if necessary
82GeneralWhere is the laydown area to be locates? (Field, parking lot)See attachment 1. Potential Haul Route, Laydown yard and staging area
83GeneralHow big will the laydown area be?See attachment 1. Potential Haul Route, Laydown yard and staging area
84StructuralIn kitchen is there any mortar beds that need to be accounted for?To the best of our knowledge there is a metal deck with light concrete over it, under the finished floor. No as-builts available to confirm. Contractor inspection required for confirmation
85GeneralIn UFGS 09 30 10 Tile spec’s call for crack isolation, is this something that need to be accounted for?Was there something in the site visit that triggered this concern? Clarification required. Site investigation and design development will determine this requirement.
86GeneralWill Dinning area get Roppe 4” cove base -577 Ginger bread?See SOW para. 2.4.8.3.1.3.
87GeneralDo we need to include any after works?Please clarify, is this after hours or after project completion?
88GeneralJust to confirm, only Hallway, Dining area, Elevator, and kitchen is getting new flooring.Yes, your understanding is correct. Per SOW - the renovation project is limited to installing new flooring in the following areas only: the kitchen, the dining area, the adjacent second-floor hallway, and the elevator located within that hallway. The document provides specific types of flooring and installation requirements for each of these distinct areas.
90FFEEquipment Disposition - will any equipment stay, if so which components? What will the Contractors due with the existing FFE? Dispose off site, or take it to another location on base? If on base, where to?Per SOW - the Contractor is required to protect and keep in place only the existing kitchen exhaust hood, the Gaylord cleaning system, and the COMM box on the kitchen wall. The Government (FSS) is responsible for the disassembly, removal, and relocation of all other existing kitchen equipment, dining room furniture, and the CCTV system, which requires the contractor to provide a 21-day notice to coordinate. The contractor is only responsible for the demolition and removal of construction-related debris (such as old millwork, flooring, and wall panels), which must be hauled off-site and disposed of at a state-approved landfill, as disposal of any contractor-demolished material on Laughlin Air Force Base is strictly prohibited.
91FFEExisting FFE to remain - For remaining chairs and tables who will remove them? If the contractor, where will the contractor take them for temp storage? Who will remove the wall plaques? Does the contractor need to re affix in the same location?Per SOW - The Government is solely responsible for removing all existing dining room tables, chairs, and furniture; therefore, the contractor is not responsible for their handling, removal, or temporary storage. The contractor is responsible for preparing all wall surfaces for painting. This standard practice implies the contractor will remove any items on the walls to complete the painting work, but there is no requirement in the SOW for the contractor to re-affix or reinstall any wall plaques once painting is finished.
92GeneralWhat is the construction date of B308?See SOW para. 1.2.1
93ArchitecturalDid the Base Architect measure the proposed new equipment to determine if it would fit within the eexisting space?The equipment does not fit in the kitchen's existing configuration. Non-load bearing walls in the kitchen area can be reconfigured. See SOW para. 2.4.7.6.1
94GeneralIf we add a new personnel entry door, does it need a window and a simple key pad lock?Per SOW - the current renovation plan does not include the addition of a new personnel entry door. Instead, it directs the contractor to demolish an existing entrance to the cooking area and reconfigure it with a wall extension.
95FFEDoes the new space need a Mop Sink?Per SOW - the attached Furniture, Fixtures, and Equipment (FFE) list, a new mop sink is not a requirement for this renovation project.

The SOW's plumbing section specifies that the contractor must provide lines and drains for the food service equipment detailed in the FFE list. After thoroughly checking this equipment list, I can confirm that it does not include a mop sink. Therefore, installing one is outside the current scope of work.

96 Communications Can we re-hang the TV or is new AV/IT required? Per SOW - "The Government (FSS) will remove the closed-circuit television before construction begins and re-install the closed-circuit television after work is complete." Therefore, the contractor is not responsible for re-hanging the existing TV.

However, the contract does require the installation of new AV/IT equipment. The contractor is responsible for providing and installing the following new components:

One new menu monitor for the service line section.

Up to three new monitors for the cooking and food preparation sections.

All associated new data conductors and conduits to support these new monitors and the Point of Sale (POS) stations.

In summary, the Government will handle the single existing TV, while the contractor must provide and install a completely new set of monitors as specified in the SOW.

97 Communications Is there any Comms required for a cmputer? Yes, absolutely. Per SOW - specific communications requirements to support the computer systems in the renovated space.

The SOW directs the contractor to provide and install the following:

For the two Point of Sale (POS) stations: The contractor must install two Category VI data lines and four electrical outlets for each station. These POS stations are the primary computers for taking orders and processing payments.

For the new monitors: The contractor must also install new data conductors and conduits for the new menu monitor and the three new monitors in the cooking/food preparation area.

Therefore, the project requires the contractor to install a significant amount of new data and communications infrastructure to support the computers and monitors in the new layout.

98CommunicationsIs the Point of Sale register connecected via WIFI or hard wired?Per SOW - the Point of Sale (POS) registers must be hard-wired. The SOW explicitly directs the contractor to provide and install two Category VI data lines for each of the two POS stations. While modern systems often have wireless capabilities, the mandate for dedicated Cat VI cabling indicates that the Government requires a stable, secure, and physical network connection for these workstations.
99CommunicationsCan we reuse existing conduit and cable trays?Yes, the vendor may use existing conduit and cable trays.
100Re ACM/LBP concerns - Are there past ACM/LBP studies that you can provide?Please expand and clarify question
101GeneralCan we work nights or weekends to replace the hallway flooring or to move equipment?See response on question 5
102ArchitecturalCan you provide Plumbing, HVAC and Electrical As-Built drawings for the area in question?See response on question 2
103FireIs the existing HALON system remaining or is a new system required?NO HALON ! Where is the issue for system coverage? There is no Halon System, however there is a Wet Chemical system and the pull station is on the wall that is to be moved. The pull station will need to remain on the wall or relocated within the authorized travel distance from the cooking appliances. See attachment 2. Image - Existing Panel
104GeneralIf we need to move the floor drains can we access the drains from the first floor?Yes, but coordination with building occupants shall be arranged with a minimum of two weeks with no operation disruption
105GeneralCan we use the Elevator to move equpment in and out?No
106GeneralWhere can the contractor place their storage containers for ease of material access?See attachment 1. Potential Haul Route, Laydown yard and staging area
107GeneralCan the contractor utilize lift equipment to bring materials close to the entry points? (i.e. over the curb and on the sidewalk near the entry way to B308).Yes. Contractor shall maintain egress between building B308 and B320, coordinate timeframes with Government prior to effort(s), submit a lift plan, and safety protocols within Safety Plan
108GeneralCan we triple hat the job - ie. 1 competent person to be Super, QCM, and SafetySee response on question 2
109ArchitecturalNeed AS-Builts on Exhaust Ventiltion. Will the air changes increase as a result of the new equipment?See response on question 2
110GeneralHow many personnel does the facility serve in a day?100 to 150 customers
111GeneralWhat is the max occupancy load of the facility?Fire Project Engineer to calculate
112ArchitecturalCan the Existing CADD Files be shared upon Award? Or will the A/E be responsible for generating completely new renovation drawings?Floor plans and Conceptual design can be provided, but it is the contractor's responsibility to deliver complete 100% designs ready to IFC
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128