RFI 3.pdf
PDF 60 KB Posted
- Attached to
- Cincinnati Elevator Services Federal contract opportunity
- Solicitation number
- Not on record
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Walk Thru Sign in.pdf | ||
| Pre-Proposal Conference Agenda.pdf | ||
| RFI 2.pdf | ||
| PreProposal Conference Attendance .pdf | ||
| RFI 1.pdf | ||
| J.7 Elevator Inspection Form.pdf | ||
| RFP 47PF0021Q0095.pdf | ||
| GSA527-15e (1).pdf | ||
| J.13 Electric Traction Elevator Checklist 08-2018.pdf | ||
| J.13 Hydraulic Elevator Checklist 08-2018.pdf | ||
| OH0189CN - J.W. Peck Building Asbestos Notification Letter (12_2019).pdf | ||
| OH0028CN - Potter Stewart CTHSE Asbestos Notification Letter (11_2019).pdf | ||
| Contractor Proposal Worksheet - Peck 2.13.20.xls | XLS spreadsheet | |
| Contractor Proposal Worksheet - PSCH 2.13.20.xls | XLS spreadsheet | |
| Contractor Proposal Worksheet - FDA 2.13.20.xls | XLS spreadsheet |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI #3
47PF0021Q0095
Q: Can I request for history on callbacks for all three buildings?
-Total Service Calls for John Weld Peck Federal Building: 119
9/2016 - 4/2017 0 4/2017 - 4/2018 5 4/2018 - 4/2019 47 4/2019 - 4/2020 52 4/2020 - 4/2021 15
-Total Service Calls for Potter Stewart Courthouse: 57
9/2016 - 4/2017 0 4/2017 - 4/2018 9 4/2018 - 4/2019 28 4/2019 - 4/2020 13 4/2020 - 4/2021 7
-FDA Chemistry Center
“Believe only 5 times since contract inception (June 2018) have they had to report anything to them and possibly only 2 of those were times they reported outside of their regularly scheduled maintenance visit.”
Q: Also, how much each building spent on repairs/emergencies via GSA form 300?
-I would like to point you to Section C.2 and C.2.1.2 Repair and Replacement of the
RFP that dictates, “Full maintenance service is defined as all services, repairs, inspections and testing necessary to maintain all elevators, appurtenances, and accessories in a fully operational mode at all times except for pre-scheduled downtime including all labor, parts and materials.” Contractor is responsible for all repairs and this is covered under standard services/in the monthly price.