Amend05_FormSF30.pdf

PDF 1 MB Posted

Attached to
O&M Services
Solicitation number
GS-09P-15-KS-D-0040
Issued by

About this file

Amend05

View the file

Other files

File Type Posted
Amend07_FormSF30.pdf PDF
Amend06_FormSF30.pdf PDF
Q A_Compiled_Responses_8-12-15.pdf PDF
2800 Cottage Way - Child Care Center.xls XLS spreadsheet
2800 Cottage Way - shop.xls XLS spreadsheet
2800 COttage way - main.xls XLS spreadsheet
Section_M_-Evaluation_Revised_8-10-15.pdf PDF
Amend04_FormSF30.pdf PDF
Sign-in_Sheet_Pre-Proposal_and_Site_visit_7-21-15.pdf PDF
O M_SOW__-Sacramento_2015_Rev_1_8-4-2015.pdf PDF
Amend03_FormSF30.pdf PDF
GSA-PBS_PM_Guide_Oct2012.pdf PDF
CA0083ZZ_801_I_street.xls XLS spreadsheet
Attachment_4_References.docx DOCX document
WDA_2005-2055_Rev_17.txt TXT text file
CA0199MM_2800_Cottage_Way.xls XLS spreadsheet
CA0152ZZ_650_Capitol_Mall.xls XLS spreadsheet
Sacramento_CBA_2012_-_2016.pdf PDF
Solicitation_O M_Sacto_FinalRev1_7-22-15.pdf PDF
Q A_Responses_7-22-2015.docx DOCX document
Amend02_FormSF30.pdf PDF
Exhibit_1_-_Building_Operating_Plan.docx DOCX document
CA0306ZZ_Robert_Matsui_CH_Oct_2014.xlsx XLSX spreadsheet
Amend01_FormSF30.pdf PDF
Attachment_A_-_FormSF1449.pdf PDF
Solicitation_O M_Sacramento_FB.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NSN 7540-01-152-8070 STANDARD FORM 30. (Rev. 10-83) Previous Edition unusable Prescribed by GSA FAR (48 CFR) 53.243

Page of Pages AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code

2. AMENDMENT MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (if applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than item 6) CODE

(x) 9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

8. NAME AND ADDRESS OF CONTRACTOR (NO., Street, Country, State and ZIP Code)

CODE FACILITY CODE

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning ______ copies of amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OR OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

Check One

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR 16B. UNITED STATES OF AMERICA

(Signature of person authorized to sign)

15C. DATE SIGNED

(Signature of Contracting Officer)

16C. DATE SIGNED

Continuation Page

PAGE 2 OF 4 GS-09P-15-KS-D-0040/05

Continued from Block 14...

Also, to clarify the proposal due date is, Thursday, August 13, 2015 at 3:00 PM (PST). Proposal should be mailed or deliver to the attention of Tania Ramsay, 50 United Nations Plaza, 4th Floor, Room 4670, San Francisco, CA 94102.

Attachment Page

PAGE 3 OF 4 GS-09P-15-KS-D-0040/05

M. EVALUATION FACTORS FOR AWARD

M.1. METHOD OF AWARD

The Government will make award to the responsible Offeror whose offer conforms to the solicitation and offers the greatest value to the Government, price and technical factors combined. The combined weight of the technical factors is greater in importance than price in determining the greatest value to the Government. Accordingly, as technical scores become more divergent among those considered for award, price differences become of less significance.

The Government will pay more for a firm of greater technical competence as long as the price is fair and reasonable, and as long as the price difference is not significant and technical superiority insignificant. Once a range of prices has been determined where anyone in that range may be considered fair and reasonable, the Government may, though is not obligated to, choose from among those firms, the one with the highest technical score.

M.2. EVALUATION OF OFFERS

Proposal will be evaluated based upon the following technical factors, (1) Experience; (2) Past Performance (3) Management & Staffing Plan. These factors are described in further details herein.

The combined weight of the above technical evaluation factors is more important than price, and the “best value concept” will be used for selecting the contractors. The objective is to select the proposal which offers the most value for the money, not necessarily the lowest price.

M.3. TECHNICAL EVALUATION FACTORS

The evaluation factor consists of three components; Experience, Past Performance, and Management & Staffing Plan. Offerors will be evaluated based on relevant experience and past performance on Similar Work. Therefore, each Offeror is required to submit a completed Experience/Past Performance Data Sheet for a minimum of 3 projects within the past three (3) years in their technical proposal.

Attachment 4 shall be used to submit Experience information. The period of performance for each project MUST be clearly denoted on the sheet. If more than 3 projects are provided, the Offeror must denote which 3 projects is to be considered for evaluation. Otherwise, the government reserves the right to select the first 3 submission, or if multiple projects are denoted on a single sheet, i.e. a Reference List, the first 3 projects from this list.

Offerors should be cautioned to verify the accuracy of the contact information (the "references") for the past performance evaluation. If the SSEB is unable to contact a submitted reference, then that Offeror will be given a neutral past performance rating for that reference. In addition to those references provided directly by the Offeror, the Government may identify and analyze such relevant past performance or experience of the Offeror on any other contract that the Offeror currently has or had of which the Government has knowledge or obtains knowledge, including but not limited to projects listed in the Past Performance Retrieval Systems (PPIRS).

M.1. Similar Work Similar Work means Operations and Mechanical maintenance and related services detailed in the Basic Services of the solicitation, in a building consisting of commercial office, executive, and public meeting spaces of 400,000 gross square feet or above and a minimum of 10 stories.

M.2. Evaluation Factor 1 – Experience

Attachment Page

PAGE 4 OF 4 GS-09P-15-KS-D-0040/05

This factor considers the Offeror’s experience in carrying out Similar Work. The standard is met when the Offeror demonstrates that it has performed Similar Work on 3 projects within the past three (3) years. A more favorable evaluation may be given to those offers that demonstrate having experience with courthouses/secured facilities, building automation systems (BAS), Controls programming expertise, Energy-savings and Building efficiency performance, and chemical-free water treatment systems.

M.3. Evaluation Factor 2 – Past Performance This factor considers the quality of the Offeror’s past performance in carrying out Similar Work.

The Government reserves the right to check the past performance on 3 of the projects submitted by the Offeror. If the Offeror submits more than 3 projects, the SSEB will contact only 3 references for evaluation purposes. The standard is met when the Offeror submits at least 3 projects within the past three (3) years demonstrating Similar Work and the past performance was rated as "Meets Requirement" or better.

Those firms receiving a rating higher than "Meets Requirement" in Customer Satisfaction, and whose response came from a property manager or an actual on-site representative, may be given a more favorable evaluation. Offerors without any past performance on Similar Work or whose references cannot be contacted will be given a neutral rating.

M.4. Evaluation Factor 3 - Management & Staffing Plan This factor considers the Offeror’s management & staffing plan. The Offeror must describe methods and positions which will be used to staff the contract requirements, including major sub-contractors, and corporate support. The standard is met when the Offeror demonstrates a complete management and staffing plan that will address all requirements of the contract to include resumes of the Chief Engineer and Project Manager. An additional point will be given to those offers that demonstrate management of Federal building, courthouse, etc.

M.4. PROPOSAL FORMAT REQUIREMENTS

In order to efficiently review the proposal and reduce the amount of time it takes to evaluate them, the number of pages for the technical proposal should be no more than twenty-five (25), to include the minimum of three projects from the Offeror's completed Experience/Past Performance Data sheet (Attachment 4). An Offeror may include a narrative or any other document it deems necessary to demonstrate its experience in meeting Similar Work but MUST include the completed Attachment 4 and/or a document that contains the same information that is on Attachment 4 in the technical proposal.

M.5. EVALUATION OF OPTIONS

Except when it is determined in accordance with FAR 17.206(b) not to be in the government’s best interests, the government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of these options will not obligate the government to exercise the option(s). (End of provision)

M.6. DISCUSSIONS

Pursuant to FAR 52.215-1 contained in this solicitation, the government may evaluate proposal and award without discussions with offerors, except for clarifications as described in FAR

15.206. As such, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price technical standpoint. The government reserves the right to conduct discussions if the contracting officer later determines it is necessary.

Descript: This amendment is issued to clarify that Offerors must submit 5 copies of their Technical proposals and 1 Price proposal.

In addition, Section M is revised to reflect the priority for the technical evaluation factors.

...See Continuation Page

Descript1:
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT:
IDCode:
pdfpage1: 1
Pages: 4
DocNo: 05
EffDate:
ReqNo: 9P3PSFN-15-0088
ProjNo:
IssuedByCode: 9P3PMFT
IssuedBy: GSA, FMSP DIV, TECHNICAL SECTION

50 UNITED NATIONS PLAZA, 4TH FL (9P3PMFT)

SAN FRANCISCO CA 94102

AdminByCode:
AdminBy:
ContractorCode:
FacCode:
SolChg: Yes
AwdChg: Off
SolNo: GS-09P-15-KS-D-0040
SolDate: JUL 15, 2015
AwdNo:
AwdDate:
NoCopies:
Amended: Yes
OffrExt: Off
OffrNoEx: No
ApprData: See Schedule
ChgeOrd: Off
ChgeOrder:
Modify: Off
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).:
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
SignName:
SignTitl:
ContDate:
ContrOfficerInfo:
CODate:
Contractor Info:
ContractorPOC:
Contractor:
ModAmount:
Header:
15B. CONTRACTOR/OFFEROR:
Footer1:
signature:

File details come from the government source that posted it. Updated .