SSA_EVault_RFI_Round_2_-_082517.xls
XLS spreadsheet 67 KB Posted
- Attached to
- Electronic Vault (E-Vault) Federal contract opportunity
- Solicitation number
- GS-08-P-17-JA-C-0005
About this file
Response to Round Two RFI's
View the file
Other files for this federal contract opportunity
Show all 33
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1st Round
| SSA E-Vault Questions GS-08-P-17-JA-C-0005 | ||
| QUESTION | RECOMMENDED ADDENDUM TERMINOLOGY | |
| 1 | Factor 2, Past Experience, requires two or more similar contracts/task orders, substantially completed within the past seven years, to include whether initial construction or retrofit of an existing building, and further states that a more favorable evaluation may be provided for data center retrofit experience versus data center initial construction and for Tier III Data Center experience. Each of these prerequisites has the effect of limiting competition. This factor goes on to require similar Data Center building construction with both 10,000 GSF or more and a total project construction cost exceeding $10,000,000. Such limitations may further unduly restrict competition by excluding relevant past performance that does not meet these two thresholds. 1) When taken as a whole, the requirements appear to favor large businesses; please consider relaxing the 10,000 GSF and $10,000,000 minimums. 2) Please clarify how past performance for major subcontractors which are meaningfully involved in the planned project will be considered. 3) Please confirm that commercial projects may be used as Past Performance references. | Factor 2 - ADD: Summary) Data Center facilities are very complex; The goal is to ascertain the Data Center & construction knowledge of the bidders and select the most qualified for the most reasonable price. A project of this size and magnatude requires a Prime contractor that has experience managing all aspects of a multi-million dollar project. The main subcontractors (Electrical & Mechanical) shall be designated in the bid submittal. |
| 2 | The pricing excel sheet provided as part of the bid documents does not have a location for the Optional Extended Warranty line items identified in spec section 001200-4 3.5 Extended Warranty. Is the provision for pricing the extended warranty required and how should it be presented? | ADD: to the SF 1442 the 5 year warranty for all major electrical equipment: generators, ATS' + UPS', and switchboards |
| 3 | Spec section 001200 section 3.6.C requires a Factory Witness Test (FWT) of the complete power system. This is very costly and will have a significant impact on the overall construction duration. | Specification section 001200 section 3.6.C. ADD: Contractors will provide provisions for "Factory Witness Testing" (FWT) as stated in the specifications. |
| 4 | Specification section 013200 Section 1.1.C references Division 1 Section “Network Analysis Schedules”. This division 1 specification is not included in the current specification set. Please provide this specification section. | "Network Analysis Schedules" is as stated in section 013200, Part 1.2 and is entitled "CONSTRUCTION PROGRESS SCHEDULING". |
| 5 | Specification Section 001200 Part 3.4 Unit prices requires the submission of two unit prices, in accordance with 3.4.B and 3.4.C. Please add both of these unit prices to the SF1442 Pricing sheet. | These items (General Conditions Costs & Excavation of "unsuitable soil excavation" as stated in section 001200 / 3.11 - Geo-Tech Requirements) will be ADDED to the "Supplemental Pricing Sheet". Additionally, bidders may provide "DEDUCT" if "Office / Storage" trailer function is IN south end of building 94 in lieu of exterior / rented trailers. Subdivision of the space (approximately 5,600 SF) is at the GCs expense. |
| 6 | There is no requirement for unit prices for the cast in place drilled pile in the contract. This work is typically performed on a unit price basis so over runs and under runs are easily accounted for. Will a unit price for piling be added to the pricing sheet? If not will over runs in piling operations be addressed through the Differing Site Conditions Clause? | ADD Section 001200 part 3.4 / D: LUMP Sum price based on drawings and specifications - considering the "Geo-Technical" Report- AND - Provide a "Unit Price" per lineal foot of cast-in-place "DRILLED PIERS" over the dimensions indicated on the drawings. As stated in section 316326 / 1.3 AND this will be added to the GSA "Supplemental Pricing Sheet". |
| 7 | Specification Section 001200 Part 3.2 Identifies the basis of award as lowest price for the base bid under “Contract award – Sealed Bidding”. This contradicts section VI. Method of Award which identifies the use of best value to determine award. Please verify that the evaluation for award will be based on best value in accordance with section VI. Method of Award. | Specification section 001200 part 3.2.A ADD: "Contract Award shall be based on "Overall Best Value"". |
| 8 | Please clarify the extent of the High Voltage electrical work to be completed under this contract? | The DFC distribution voltage operator (Sturgeon) is the onsite Dever Federal Center coordinator of the high voltage portion of the project. |
| 9 | ||
| 10 | ||
| 11 | ||
| 12 | ||
| 13 | ||
| 14 | ||
| 15 | ||
| 16 | ||
| 17 | ||
| 18 | ||
| 19 | ||
| 20 | ||
| 21 | ||
| 22 | ||
| 23 | ||
| 24 | ||
| 25 | ||
| 26 | ||
| 27 | ||
| 28 | ||
| 29 | ||
| 30 | ||
| 31 | ||
| 32 | ||
| 33 | ||
| 34 | ||
| 35 | ||
| 36 | ||
| 37 | ||
| 38 |
2nd Round
| SSA E-VAULT QUESTIONS GS-08-P-17-JA-C-0005 | ||
| QUESTION | ANSWER | |
| 9 | What is the process of requiring permits and inspections? | Any permits required (i.e. excavation, weld or burn) will be obtained through GSA and coordination of the Project and Building Managers. All inspections will need to be scheduled and coordinated through GSA Project Manager. |
| 10 | Who is the authority having jurisdiction? Jacobs Engineering or Core of Engineers? | The authority having jurisdiction is GSA, Region 8, Fire Marshall, Alan Antonio. |
| 11 | Specification 262300-1 references “Digital Realty” building standards. Please clarify why this is in the specifications. | Disregard this reference it does not apply to this project. |
| 12 | Specification 262300-1 mentions “Low Voltage Switchgear-Pre-purchase”. Please clarify if GSA is providing this material or is the General Contractor providing? | General contractor is to provide the Switchgear. |
| 13 | Specification 001200-4 3.6 A -Factory Witness Testing. Please clarify that Factory Witness testing will be done onsite (Building 94) after all equipment has been installed and started up. | Factory Witness Testing cannot be performed on-site in the event that some revisions are required at the factory. Factory Witness Testing will be performed at the factory. |
| 14 | DSI could not find a finish schedule for flooring, painting, ceiling and door hardware. Please provide. | Apparently the Finish Schedule (Dwg #A-6.3) was inadvertantly left off the Bid Set. The finishes are indicated on that drawing vwhich is attached here. Basic door hardware is noted on Dwg #A-6.2 and in spec section #087100 part #1.8.B.1 - Your "Architectural Hardware Consultant" (AHC) will prepare the final Hardware Schedule. Please email Sarah Callies your SBU to obtain the additional drawings. |
| 15 | Sheet A-0.1 Architectural Demo Plan- Please confirm if GSA is removing the fencing or the general contractor. | Yes, GSA will be removing the existing fencing |
| 16 | During the second onsite meeting E2 Optics mentioned that they will provide an addendum for the data hall structural ceiling support grid. Tate? Please provide information or specifications. | Refer to the forthcoming modification specs section #095100. The structural capabilites have been modified as follows1.2 / a: Ceiling grid system shall be capable of supporting a uniform load up to 25 lbs/SF. |
b. Ceiling system shall be capable of a maximum static point load of 200 lbs. with standard duty connector.
As competitors - several systems are only capable of a 90 lb point load - which is too low for our anticipated loads. The revised drawing #A-3.2 is attached here.
| 17 | Please confirm GSA is providing all server cabinets, rack PDU’s and anchor brackets. How many racks will be installed day one? | SSA will be providing all server cabinets, rack PDU's and ganging kits to anchor cabinets to each other. 8 cabinets Demarc #1; 8 cabinets Demarc #2; 23 cabinets Data Hall #1 and 21 cabinets Data Hall #2; Total Cabinets = 60, See DAT-1 for details. |
| 18 | Will GSA provide server cabinet anchorage details? | Ganging kits will be provided to bolt cabinets together, there will be one standalone cabinet not bolted to another in Data Hall #1. |
| 19 | Hot Aisle Containment System (HACS) clarification. Drawing A-3.2 shows containment curtain. Specification 13 2110 section 2.3 calls for steel vertical and horizontal framing. Is this a combination of hard panels and curtains where no cabinets are being installed day one? | Yes the HACS is with hard Panels and soft curtains. -- Drawing #A-6.2 gives a very good rendition of the HACS. Coordinate drawings #A-3.2 & A-6.2 with the full specifications. The HACS system will contain an upper permanent structure that will be approximately 3-4 feet from the ceiling and will allow an attachable/detachable curtains to block the approximate 8-9 feet from the upper permanent structure to the floor. Example is on drawing A-6.2. Final dimensions will depend on Vendor chosen for proposal. |
| 20 | How many server cabinet blanking panels are required in bid proposal? 1U blanking panels or 42U blanking panels that can be cut? | Blanking panels will be part of the server cabinet order and will be supplied by SSA. |
| Drawing SC 1.10 Please confirm the base proposal includes the following quantity of bus plugs. | Quantity of 'b.' is 16, changed from 15 - all other quantities remain the same reference Drawing SC 1.10 | |
| a. (54) 60-amp bus plug RS460C9W | ||
| b. (15) 50 amp bus plug 9C54U2 | ||
| c. (80) 30 amp bus plug A-B phase L6-30R | ||
| d. (80) 30 amp bus plug B-C phase L6-30R | ||
| e. (80) 30 amp bus plug C-A phase L6-30R | ||
| 21 | f. (10) 20-amp bus plug 5-20R (was this supposed to be Locking L5-20R) | |
| 22 | Section 260573 Overcurrent Protective Device Coordination Study. Who is responsible for developing the short circuit coordination study and the Arc Flash 260574? Where is Specification 260573 and 260574 located? | Further clarification will be forthcoming. |
| 23 | The Supplementary Instructions to Bidders contains (in Section 001200) requests for more detailed pricing and/or Labor Rates. These pricing requests are not found in either June 29, 2017 Instruction to Offerors letter, nor in the C201 Solicitation document. Should those Supplementary Instructions be followed? If so, how should that pricing be included with/added to the Attachment 0008 Price Proposal Worksheet? | Please reference Construction Wage Rate Requirements that are part of the solicitation package. |
| 24 | Is the General Contractor responsible for providing diesel fuel for commissioning/testing as well as topping off at the completion of the project? | Yes, the General Contractor is required to provide the fuel for Commissioning/Testing as well as topping off at the completion of the project. |
| 25 | On the single line diagram E-4.00 “MDSA” & “MDSB” shows normally open 800 amp circuit breakers labeled “MDSA-04” & “MDSB-06”. Please clarify what these circuit breakers are for or are they spares? | Circuit breakers MDSA-04 and MDSB-06 are spares. |
| 26 | I have received two emails that the potential contractors cannot locate the actual Electrical Narrative in the document. The expectation was to find it around page 198, (before Section 5 – Physical Security), however they are unable to locate it, please advise. | Electrical narrative section is forthcoming. |
3rd Round
4th Round