U.S. General Services Administration
Template Rev. 2016
SCOPE OF WORK
SOCIAL SECURITY ADMINISTRATION (SSA)
ELECTRONIC VAULT (E-Vault) May 10, 2017
Project Location Building Number 94 One Denver Federal Center Lakewood, Colorado 80225-0546 Building Manager: Cade Flournoy Phone: 970-217-2831
Project Points of Contact Contract Specialist: Sarah Callies Project Manager: Paige Jacques Phone: 303-880-5133 Phone: 303-910-7136 Email: sarah.callies@gsa.gov Email: paige.jacques@gsa.gov
PROJECT SCOPE
Project Summary The General Services Administration, Region 8, is initiating a Design-Bid-Build for an E-Vault Data Center facility to provide storage services to other computer facilities for a federal customer. The facility will be designed to experience no scheduled down time and be able to operate without external utilities for specified periods of time.
The E-Vault project area consists of 3.25 acres of pre-developed land, and will provide improvements, including an expanded facility with associated parking, utilities, landscaping improvements, and an additional access road.
Building 94 is located at One Denver Federal Center, Lakewood, Colorado on the Denver Federal Center (DFC) Campus.
The building was built in 1992, is one-story and sits on a concrete slab. Building 94 is approximately 28,000 sq. ft. in size and currently serves as a warehouse - 18,000 sq. ft. is being converted from warehouse space into the E-Vault space. It is constructed of modern steel and CMU and it has no interior walls and wide column spacing. There is a built- in loading dock and outside room for generator, substation and cooling pads. The construction, layout and setbacks of this location make it an ideal candidate from security and life safety standpoints to house the E-Vault.
The project shall comply with PBS-P100, Facilities Standards for the Public Buildings Service and the following standards and criteria documents; The Uptime Institute Tier III and/or Telecommunications Infrastructure (TIA-942) Standards for Data Centers.
This building has been determined ineligible for nomination to the National Register of Historic Places. Consultation with the State Historic Preservation Office and GSA Center for Historic Buildings is not required as part of this project.
The Government will be using a brand name product to fulfill a portion of the fiber optic cable construction requirements through a subcontract for the brand name product under the General Contractor. The requirements call for a subcontract to a Corning Manufacturer Certified Installer with a 25 year warranty.
Project Objectives The contractor shall provide labor, materials, equipment and supervision necessary to perform:
• Construction of the E-Vault Facility in accordance with all design drawings, specifications and narratives.
• Complete project in the agreed prescribed timeframe
• Secure access badging for work on the Denver Federal Center in Lakewood, Colorado mailto:sarah.callies@gsa.gov mailto:paige.jacques@gsa.gov
SSA E-Vault– Statement of Work
Contractor shall field verify all requirements at time of pre-bid walk through.
All work shall comply with codes and standards applicable to each type of work through the course of this project.
Contractor shall also comply with the requirements of GSA BuildGreen Standards and the PBS P100.
Project Duration Once notice to proceed has been issued, the contractor has 459 calendar days to complete the project. Extensions will be granted for unforeseen conditions and other factors outside of the contractor’s control at the Contracting Officer’s discretion.
Proposal Pricing When submitting a proposal, provide a cost breakdown for each task into the following categories: Materials, Equipment, Labor Hours, Subcontractor's Quotes, Overhead, and Profit. (SEE ATTACHED PRICE PROPOSAL
WORKSHEET)
General Requirements:
I. Submittals A. Contractor shall submit a Method of Procedures (MOP) to the Project Manager (PM), Paige Jacques, for approval prior to commencement of work. At a minimum, the MOP shall include:
1. Brief narrative describing method of accomplishment, construction techniques, etc
2. Project schedule
3. Service/Utility Outages (if necessary)
4. Phasing schedule (if necessary)
5. Any building infrastructure/BAS equipment that may be impacted
B. All products specified are to establish a standard of quality. Submittal response by the government shall be 14 calendar days or less. If product samples are not submitted in a timely fashion, any delays caused by the contractor will not warrant a time extension. After completion of all work, the Contractor shall submit to the project manager the manufacturer's specifications, instructions and material specification sheets in original form. Additionally, the Contractor shall submit all inventory changes (removals, additions, upgrades, etc., and new condition codes) to the COR
II. Equipment A. The contractor shall provide all equipment associated with the project, operate in a safe manner and adhere to all OSHA and GSA standards.
III. Contractor Use of the Premises A. During the period of the project, the contractor will have access to the site only during business hours of
6:00 am to 6:00 pm. No on-site work shall be performed outside these hours or on holidays unless otherwise directed by the Contracting Officer. The contractor will need to coordinate with the Contracting Officer to arrange access to the parking lot. The contractor shall make every effort to cause a minimum of damage to parking lots, any other paved areas, any items that need to be moved during the course of the project, and any areas not included in this scope of work. Any damage caused will be repaired at the contractor’s expense.
B. In the event that any other special working hours or after hours are requested, special permits may be required. Advanced notice of these events shall be put in writing to the Project Manager at least two (2) weeks in advance of the event.
IV. Progress Meetings A. The contractor shall schedule weekly meetings with the GSA, the Construction Manager as Agent (CMa) and all subcontractors. The contractor shall keep meeting minutes and distribute copies at the following meetings. The meeting agenda will include the following as a minimum: Approval of previous meeting, review of work progress, field observations, problems and decisions, identification of problems which impede planned progress, review of submittals schedule and status of submittals, maintenance of progress schedules, planned progress during the succeeding work period.
V. Fire System Impairment and Hot Work A. When a fire suppression or alarm system impairment is required, contractor shall provide written outage request to GSA for approval in advance of impairing any systems. Contractor shall be responsible for having a GSA approved NICET certified fire alarm contractor perform all system impairments. During fire alarm/suppression impairments or hot work procedures, contractor shall provide a fire watch per the GSA Regional Fire Watch Guidelines.
VI. Badging and Security A. All contractor and sub-contractor personnel must obtain an HSPD-12 badge. An HSPD-12 badged worker may escort up to five non-badged workers at a time for up to 15 days.
VII. Housekeeping A. The project site shall be kept in a neat, orderly, and safe condition at all times. The contractor shall provide enough containers for collecting construction debris and construction materials to be recycled.
VIII. Construction Indoor Air Quality A. The General Contractor or other qualified party shall prepare and submit a Construction IAQ
Management Plan to the Owner and Architect for approval. The Construction IAQ Management Plan shall meet the following criteria:
i. Construction activities shall be planned to meet or exceed the standards included in
Chapter 3 of the Sheet Metal and Air Conditioning National Contractors’ Association (SMACNA) “IAQ Guidelines for Occupied Buildings under Construction”, 2nd Edition 2007. This requirement includes, but is not limited to the following:
a. Protection of existing building HVAC systems, to include shutting down systems where possible and protecting supply and return ducts within the work area by covering or filtering.
b. Controlling pollution sources.
c. Suppressing dust with wetting agents or sweeping compounds.
d. Interrupting dust pathways via dust curtains or temporary enclosures.
e. Isolating areas of work to prevent contamination. Pressure differentials shall be used where feasible to prevent migration of dust/contaminants.
ii. Absorptive materials shall be protected from moisture damage when stored on-site and after installation.
iii. Filtration media shall be installed to protect ductwork and/or equipment used during the construction process.
iv. Dust covered materials that will be disturbed during demo shall be pre-cleaned using an effective dust collecting method, such as damp cloth, wet mop, etc., and shall be immediately bagged, sealed, and removed from the project area.
v. A Sequence of Finish Installation Plan shall be developed, highlighting measures to reduce the absorption of VOCs by materials that act as ‘sinks’.
vi. Immediately prior to occupancy, the building shall be subject to an outside air flush out, OR, shall be subject to pre-occupancy air quality testing.
IX. Salvage/Recycling Requirements A. Achieve end-of-Project rates for salvage/recycling of 50 percent minimum by weight of total waste generated by the work unless additional rates are indicated. Practice efficient waste management in the use of materials in the course of the Work. Use all reasonable means to divert construction and demolition waste from landfills and incinerators. Facilitate recycling and salvage of materials.
i. Salvage/recycling goal is 50 percent.
ii. Mandatory minimum salvage/recycling requirement is 50 percent.
B. Required Submittals
a. To demonstrate compliance with the above listed recycling requirements, contractor shall submit the following to GSA project manager:
i. Waste Management Plan: Submit plan within 14 days of date established for the Notice to
Proceed, prepare and submit a Waste Management Plan including, but not limited to, the following:
1. List of the recycling facilities, reuse facilities, municipal waste landfills and other disposal area(s) to be used. Include:
a. Name, location, and phone number.
b. Copy of permit or license for each facility.
2. Identify materials that cannot be recycled or reused. Provide explanation or justification.
3. Revise and resubmit Plan as required by Owner.
a. Approval of Contractor’s Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations.
ii. Waste Reduction Calculations: Before request for Substantial Completion, submit calculated end-of-Project rates for salvage, recycling, and disposal as a percentage of total waste generated by the Work.
iii. Recycling and Processing Facility Records: Indicate receipt and acceptance of recyclable waste by recycling and processing/salvaging facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
iv. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
X. Green Purchasing Requirements A. Key sustainable products: Any of the five below listed materials purchased as part of this project must comply with their respective sustainability standards. Contractor shall submit product data for each material used demonstrating that the material meets the sustainability standard.
Product Sustainability Standard
Nylon carpet
NSF 140 Gold certification and ≥ 10% post-consumer recovered content
Interior latex paint
≤ 50 grams per liter (g/L) VOCs post-tint (SCAQMD Rule 1113 standard)
Gypsum board
Greenguard Gold certification
Acoustical ceiling tiles
Meets the California Section 01350 standard for low-VOC materials and Total recycled content ≥ 20% and Recyclable in a closed loop process and USDA Certified BioPreferred and Environmental Product Declaration (EPD) available
Concrete (ready-mix and site-mix)
≥ 15% fly ash or ≥ 25% ground granulated blast-furnace (GGBF) slag
B. In addition to the above listed key sustainable products, all other interior finishes must meet, at a minimum, the baseline environmental requirements specified in the 2015 GSA P100 facilities standards, Chapter 3, Architecture and Interior Design. Contractor shall submit product data for each finish material used, demonstrating compliance with the appropriate environmental requirements.
C. Sustainability requirements for specific interior finishes and construction materials may also be found at www.sftool.gov
XI. Safety and Health Program A. Contractor Responsibility: The Contractor shall assume full responsibility and liability for compliance with applicable codes, standards and regulations pertaining to the health and safety of personnel during execution of the Work, and shall hold the Government harmless for any action on the Contractor's part, or http://www.sftool.gov/ that of the Contractor's employees or subcontractors, that results in illness, injury or death.
B. References: In addition to publications referenced in the Construction Contract Clauses, the following
Code of Federal Regulations (CFR), publications apply to conduct of the work. State and local safety and health regulations that apply are not cited herein. Current editions at the date of the agreement apply.
The more stringent requirements apply.
i. 29 CFR, Part 1910: Occupational Safety and Health Administration (OSHA) General Industry and Health Standards.
ii. 29 CFR, Part 1926 " Safety and Health Regulations for Construction"
iii. 40 CFR 260, "Hazardous Waste Management System"
iv. 40 CFR 261, "Identification and Listing of Hazardous Waste."
v. 40 CFR, Part 761, EPA Polychlorinated Biphenyls (PCBs), Manufacturing, Processing, Distribution in Commerce and Use Prohibitions. [GSA Project Team: Check if any work involves sealant removal as PCBs may be present.]
vi. National Fire Protection Association (NFPA) 70E Electrical Safety Requirements for Workplace Safety
vii. U.S. Army Corps of Engineers (USCOE) Safety and Health Requirements Manual, EM 385-1-1, current edition.
viii. Federal Standard: Fed. Std. 313A, Material Safety Data Sheets, Preparation and the Submission of.
C. The Contractor shall submit for approval a project safety and health program, including but not limited to the following:
i. Occupational Noise Exposure.
ii. Fall Protection.
iii. Personnel Protective Equipment.
iv. Control of Hazardous Energy.
v. Electrical Safety Related Work Practices.
vi. Lead.
vii. Asbestos.
viii. Polychorlinated Biphenyls (PCBs)
ix. Respirator Protection.
x. Confined spaces.
D. In addition to specific safety and health programs applicable to the project, Contractor shall submit firm's general safety plan at the pre-construction conference listing emergency procedures and contact persons with home addresses and telephone numbers.
XII. Lead Based Paint A. Paint must be tested for lead content when alterations or demolitions require the sanding, burning, welding, or scraping of painted surfaces. Lead-based paint controls must be implemented in accordance with 29 CFR
1926.62. Lead-based paint that is intact and in good condition need not be abated unless required for alteration or demolition. Lead-based paint must be abated in child care centers. Refer to PBS-P140 for specific details. Construction waste containing lead-based paint must be considered hazardous waste unless testing proves otherwise.
XIII. Excavation Permit A. Contractor shall obtain an excavation permit prior to performing any excavation work on the Denver Federal
Center. Permits are issued by GSA’s EPG; consult GSA Project Manager for additional information.
XIV. Utility Locates A. Contractor shall be responsible for obtaining public and private utility locates prior to performing any excavation activities. The Denver Federal Center has pre-approved locate contractors that shall be used for private utility locates. These contractors may charge a fee for their locating services; payment of fees associated with utility locates are the responsibility of the contractor; coordinate with GSA project manager prior to proposal submission.
XV. Cleaning & Closeout A. Final inspection shall be coordinated and scheduled through the project manager and contracting officer.
B. Before commencement of the final inspection, the Contractor shall:
1. Remove all tools, equipment, surplus material, and rubbish;
2. Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract;
3. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces;
4. Thoroughly clean building interiors;
5. Pickup all construction debris from the site; and
C. At the time of final inspection, project shall be thoroughly cleaned and ready for use. Any asbuilts/red-lines, equipment manuals, waste manifests, and project related documentation shall be submitted to the Project Manager/Contracting Officer for review and acceptance as closeout documents.
| Scope of work |
| SoCIAL SECURITY ADMINISTRATION (ssa) |
| Project Location |
| Project Points of Contact |
| PROJECT SCOPE |
| I. Submittals |
| II. Equipment |
| III. Contractor Use of the Premises |
| IV. Progress Meetings |
| V. Fire System Impairment and Hot Work |
| VI. Badging and Security |
| VII. Housekeeping |
| VIII. Construction Indoor Air Quality |
| IX. Salvage/Recycling Requirements |
| i. Salvage/recycling goal is 50 percent. |
| ii. Mandatory minimum salvage/recycling requirement is 50 percent. |
| a. To demonstrate compliance with the above listed recycling requirements, contractor shall submit the following to GSA project manager: |
| X. Green Purchasing Requirements |
| XI. Safety and Health Program |
| XII. Lead Based Paint |
| XIII. Excavation Permit |
| XIV. Utility Locates |
| XV. Cleaning & Closeout |