Questions_09272016.doc

DOC document 28 KB Posted

Attached to
EPA CO Relocation and renovation of Building 25 at the Denver Federal Center
Solicitation number
GS-08P-16-JB-C-7031
Issued by

About this file

1st set of questions.

View the file

Other files

File Type Posted
Amendment_0007.pdf PDF
Amendment_0006.pdf PDF
Amendment_0005_EPA.pdf PDF
Amendment_0002_EPA.pdf PDF
Amendment_0004_EPA.pdf PDF
Amendment_0001_EPA.pdf PDF
Amendment_0003_EPA.pdf PDF
2016-10-12_EPA_Building_Addendum_06.pdf PDF
Questions_ _Answers_4th_Set__10122016.doc DOC document
DB_Heavy_Jefferson_06032016.doc DOC document
Questions_ _Answers_3rd_Set__10072016.doc DOC document
DB_Building_Jefferson__08052016.doc DOC document
Questions_2nd_Round__10052016.doc DOC document
2016-09-30_EPA_Building_Addendum_05.pdf PDF
Storm_Water.pdf PDF
2016-09-21_EPA_Building_Addendum_04.pdf PDF
Siemens_Sole_Brand_Justification.pdf PDF
SITE_VISIT_EPA_09222016.doc DOC document
SITE_VISIT_EPA_09082016.doc DOC document
Attachment_3_-_Offeror_Experience_Information_Document.doc DOC document
C301_GC_Reps_ _Certs_EPA.doc DOC document
Attachment_4_-_Offeror_Past_Performance_Survey.doc DOC document
Attachment_2_Request_for_Solicitation_Documents_Form.doc DOC document
Scope_of_Work_EPA_08242016.pdf PDF
Cover_Letter_GS-08P-16-JB-C-7031.pdf PDF
Attachment_1_SBU_Form_GS08P16JBC7031.docx DOCX document
C201_GC_Solicitation_EPA_Final.doc DOC document
GSA_527.pdf PDF
C101_GC_Agreement_EPA_Final.doc DOC document
SF1442_GS-08-P-16-JB-C-7031.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION GS-08P-16-JB-C-7031 QUESTIONS

September 27, 2016

1) Currently the GSA is asking for each Offeror reference to complete the Attachment 4 and send directly to the Government. We are requesting that the GSA reconsiders and allows the Offeror to use Past Performance Questionnaires that we already have on file and that the PPQs can be submitted in the books versus being sent directly to the Government.

Questionaires must be submitted in order for an offer to be considered responsive. You may reference a CPARS evaluation on the forms or provide a copy if you choose to do so.

2) The Phasing Schedule references areas labeled Blocks "B" thru "I", but these areas don't seem to be identified elsewhere in the documents. Can a drawing and/or narrative be provided that identifies the limits of these Blocks?

The “blocks” referred to in the Phasing Schedule generically correspond with the mechanical zones in the building. Referencing mechanical sheet, M101.1, the following schedule applies:

Block B = RHU-2402 Block C = AHU 1201 Block D =RHU-1301 Block E = RHU-1303 Block F = RHU-1302 Block G = RHU-1304 Block H = RHU-1305 Block I = AHU-1101 Block J = Level 2

Specific rooms associated with each phase are identified below:

Phase 1a / 1b Areas Area 1A: ST-02, 1A-010, 1A-020, 1A-030, 1A-040, 1A-060, 1A-070, 1A-075, 1A-135, 1A-145, 1A-225, 1A-226, 1A-325, 1A-410, 1A-420, 1B-035, and C1A5 Area 1B between grids 28 and 30: 1A-355, 1A-420, 1A-340, 1A-360, ST-01 Area 1C: 1B-165, 1B-170, 1B-175, 1B-215, 1B-225, 1B-245, 1B-265, 1B-275, C1B5 Area 2 (level 2): 2B-135, 2B-125, C2B1, 2C-120, 2C-110, C2B0, 2B-505, ST-02, and ST-01

Phase 2 Areas Area 1B Labs along C1C3 corridor: 1C-225, 1C-245 Area 1D Labs between grids L and O: 1C-610, 1C-630, 1D-520, 1D-540, 1D-550, 1C-130, C1D5, 1C-115, 1C-120, 1C-090, 1C-085, 1C-045, 1C-060, C1C0, 1C-025, 1C-005, 1C-210, 1C-305, , 1C-540A, 1C-540B, 1F-185, C1C0, C1C2, C1C3, C1D5, C1F1 and associated gas closets as needed

Phase 3 Areas Area 1D Labs from gridline O to the east: 1C-150, 1C-160, 1C-170, 1C-180, 1C-320, 1C-325, 1C-325A, 1C-340A, 1C-340B, 1C-360, 1C-365, 1C-405, 1C-420, 1C-425, 1C-425B, 1C-520, C1C1, C1C4, C1C5, VE-06, and associated gas closets as needed

Phase 4 Areas Area 1A Labs Final Renovation: 1A-220, 1A-110, 1A-235, 1A-250, 1A-245, 1A-260, 1A-255, 1A-225A, 1A-270, 1A-265, C1A2 and associated gas closets as needed Area 1B: 1A-375

3) These spec sections reference several alternates and unit prices which do not appear on the Pricing Schedule included with the SF1442. Will a revised Pricing Schedule be issued to include these items?

In reference to spec seciton 012200 and 012300, Please provide alternate unit prices for the control system on a supplemental pricing sheet.

4) Section 1.6, Quality Assurance - Please confirm if costs for the Certified Asbestos Building Inspector are to be paid for by the Contractor or are covered by the Owner.

The costs for the CABI are to be paid for by the Contractor.

5) Will Earthwork or SWPPP specifications be issued for this project?

See posted: Storm Water

6) Section V.2, Proposal Requirements - Item 2 references submission of a Detailed Price Proposal in Uniformat, Level 4. Please confirm if this is required in addition to the SF 1442 Pricing Schedule. If required, we respectfully request that Offerer's be allowed to submit the detailed breakdown within 24 hours following the proposal submission date.

Both the SF1442 and a detailed price breakout using the Uniformat is required. No additional days will be added for the detailed breakdown. All must be submitted for consideration.

7) General Note #3 states "Contractor will deconstruct and salvage valuable building components (e.g. windows and sills, facades, doors)". Please provide a specific list of items required to be salvaged and turned over to the Owner.

EPA has requested that the contractor salvage all items, which should all go to EPA (Karon Johncox and Tim Essman). EPA will then determine the disposition of each item and work with GSA wherever possible for the items to be repurposed or excessed.

The O&M has requested that the controls for the hoods that are being replaced and any VAV boxes for air supply that are not being used in the renovation be salvaged and returned to the O&M.