Amendment 01 - GS05P11SVD0042.pdf
PDF 679 KB Posted
- Solicitation number
- GS-05P-11-SV-D-0042
About this file
Amendment 01 to Solicitation GS-05P-11-SV-D-0042
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NSN 7540-01-152-8070 STANDARD FORM 30. (Rev. 10-83) Previous Edition unusable Prescribed by GSA FAR (48 CFR) 53.243
Page of Pages AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code
2. AMENDMENT MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (if applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than item 6) CODE
(x) 9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
8. NAME AND ADDRESS OF CONTRACTOR (NO., Street, Country, State and ZIP Code)
CODE FACILITY CODE
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
� The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of offers � is extended, �is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning ______ copies of amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OR OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
Check One
A. THIS ORDER ID ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor � is not, � is required to sign this document and return _______ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 16B. UNITED STATES OF AMERICA
(Signature of person authorized to sign)
15C. DATE SIGNED
(Signature of Contracting Officer)
16C. DATE SIGNED
1 89
01 OCT 31, 2011 5PSSC1A-11-0549
SV000
GENERAL SERVICES ADMINISTRATION
MI SERVICE CENTER - PROCUREMENT TEAM
6 PARKLANE BLVD, SUITE 451
DEARBORN MI 48126-2696
See Block 6
GS-05P-11-SV-D-0042
OCT 13, 2011
See Schedule
See Supplementary Page.
Supplementary Page
PAGE 2 OF 89 GS-05P-11-SV-D-0042/01
Description of Modification/Amendment:
INDEFINITE DELIVERY, INDEFINITE QUANTITY, REPAIR, ALTERATION AND CONSTRUCTION FOR
VARIOUS LOCATIONS IN THE STATE OF MICHIGAN
GS-05P-11-SV-D-0042 is hereby amended by the following:
Repair, Alteration and Construction IDIQ GS05P11SVD0042 Various Locations State of Michigan
Amendment 01 has been issued to amend and clarify technical information in the subject solicitation as follows:
1.) Page 5 of the C101, delete entire Section II.A.3, “Unit Prices and Allowances” 2.) Page 5 of the C101, delete entire Section II.A.4, “Options” 3.) Page 6 of the C101, delete entire Section III.A.1, “Commencement, Prosecution and Completion of Work” and replace with:
III.A.1 Commencement, Prosecution, and Completion of Work
FAR 52.211-10, Commencement, Prosecution, and Completion of Work, is supplemented as follows:
The Contractor shall not commence the Work under the Contract until the Contracting Officer has issued NTP on the Contract.
TASK ORDERS: The Contractor shall diligently prosecute the Work so as to achieve Substantial Completion, as defined in III.A.8(a), of the Work within the time specified in Paragraph I.C of the Agreement. If the Contract specifies different completion dates for different phases or portions of the Work, the Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of such phases or portions of the Work within the times specified.
NOTICE TO PROCEED (NTP)
1. The Contracting Officer may issue a Notice To Proceed on the Contract upon verification that the Contractor has received approved security clearances for a suitable number of employees to begin on-site work and receipt of acceptable insurance, bond coverage and safety plan. The Contract Performance Period, as stated in block 11 of the SF 1442, begins upon the issuance of the Notice To Proceed.
4.) Page 8 of the C101, In Section III.A.2(i), replace “IAW” with “in accordance with”.
5.) Page 9 of the C101, in Section III.A.4(e), replace “Contracting Officer” with
“Construction Engineer”.
6.) Page 11 of the C101, in the first sentence of Section III.A.7(a), replace
“Contracting Officer” with “Project Manager/Construction Engineer”.
7.) Page 18 of the C101, in Section III.A.16, delete “52.217-8 and”.
8.) Page 18 of the C101, in Section III.A.17(1.6), “Task Orders”, Replace:
“Task orders shall not be split into several orders to avoid compliance with the preceding ordering limitation.”
With:
“Task orders shall not be split into several orders to avoid compliance with the ordering limitation as stated in FAR 52.216-19 in Section III.B.3.”
PAGE 3 OF 89 GS-05P-11-SV-D-0042/01
9.) Page 22 of the C101, in Section III.A.17(2.0), insert:
2.17 Work
The term Work as used in this contract is defined as the scope of work as identified in the task orders.
2.18 Contract Documents
The term Contract Documents as used in this contract refer to the Agreement and any document referenced or attached to the document, any task order scope of work, task order drawings or additional task order documents provided in a request for quote/request for proposal.
10.) Page 24 of the C101, in Section III.A.17(6.0)(c)(7), replace “or” with “of”.
11.) Page 27 of the C101, in Section III.A.17(11.0)(c), “If a contractor does not complete the work in the time specified, liquidated damages may be assessed by the Contracting Officer at the rate specified in the task order.”
With:
“If a contractor does not complete the work in the time specified, liquidated damages may be assessed by the Contracting Officer/Ordering Official at the rate specified in Section III.A.17(15.0) or the task order.”
12.) Page 28 of the C101, in Section III.A.17(13.0), replace “COR” with “Construction
Engineer”.
13.) Page 28 of the C101, in Section III.A.17(14.0)(f), replace “schedule” with
“Contract Price Schedule”.
14.) Page 30 of the C101, Replace the entire Section III.A.17(18.0)(d) with:
(d) Enforcement of safety, health, accident and fire prevention provisions of the contract rests with the ordering officials of other agencies when orders are placed by them. The contracting officer must require that a certified payroll be submitted by the contractor each week for any task order placed against the contract. The payroll must be submitted to the contracting officer through the Construction Engineer; the Construction Engineer may retain payrolls until the task order is completed and final payment made, and may be delegated the authority to check payrolls. The contractor may use any payroll form that contains the information shown on Form WH-347, Payroll, which is certified by the contractor. In addition to the required wage information on each employee, the contractor must break down the weekly payroll to show the number of hours each employee worked on each task order during the weekly period. If Form WH-347 is used, the contractor may have to list an employee's name more than once to provide the information
PAGE 4 OF 89 GS-05P-11-SV-D-0042/01
needed for each task order. A confidential interview is required for each craft and should be done at staggered intervals, when work is in progress, during the life of the contract; that is, interviews are not required on every task order. At least one person from each craft must be interviewed. GSA Form 3017, Labor Standards Interview, must be used to document results of the interviews. The GSA Form 3017 must be compared with the payrolls to determine the contractor's compliance or noncompliance with the labor standards provisions. Both payrolls and records of interviews must be made part of the contract file. The procedures at GSAR 522.3 are to be followed when there is a violation of the Contract Work Hours and Safety Standards Act.
15.) Page 32 of the C101, in Section III.A.17(21.0), “The GSA Property Manager will assign space for the storage of materials and equipment, combustible and flammable materials.”
With:
“The GSA Property Manager will assign space, if available, for the storage of materials and equipment, combustible and flammable materials.”
16.) Pages 33-34 of the C101, in Section III.A.17(23.0)(b), (c) and (d), replace “COR” with “Construction Engineer” .
17.) Page 36 of the C101, in Section III.A.17(33.0)(a), replace “COR’s” with “Construction Engineer’s”.
18.) Pages 36-37 of the C101, in Section III.A.17(33.0)(b) and (34.0)(b), replace “COR” with “Construction Engineer”.
19.) Page 44 of the C101, in Section III.A.17(36.4)(f) and (g), replace “applied to the contractor through the proposed deduction process.” with “born by the contractor.”
20.) Page 56 of the C101, in Section III.B.3, The entire clause “FAR 52.217-8 OPTION TO EXTEND SERVICES”
With:
OPTION TO EXTEND SERVICES
The Government may require continued performance of any services within the limits and at the rates specified in the contract. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within __30_ days of the contract expiration date.
PAGE 5 OF 89 GS-05P-11-SV-D-0042/01
21.) Technical Specifications, Section 01010 – B page 9, Under 601-9000 Resilient Tile & Base:
9010 & 9020 – Unit Measure #2
With:
9010 – Unit Measure #1, 9020 – Unit Measure #2
22.) Technical Specifications, Section 01010 – B page 10, 2nd paragraph, last sentence:
Payment for work above 12’ shall be made at the unit price listed for “above 12’.
Payment for work above 12’ will be Non Line Item Pricing.
23.) In Building profile sheets attached the C101, insert the following contact information for the designated buildings:
Cargo Inspection Facility, Detroit, MI – Contact Dennis Turzak at 313 226-dennis.turzak@gsa.gov Theodore Levin U.S. Courthouse, Detroit, MI – Contact Steve Ernest at 313 226-2534 steven.ernest@gsa.gov Rosa Parks Federal Building, Detroit, MI – Contact Mark Bespalko at 313 226-7413 mark.bespalko@gsa.gov
24.) Page 4 of the C201, Section I.E, for the base year only for the base year plus all options per zone
25.) Page 5 of the C201, Section II.A, insert “Contractor shall submit one original and two copies of the price proposal and one copy of the technical proposal.”
26.) Page 7 of the C201, Section II.C.1, delete “and current fax number”.
27.) Page 8 of the C201, in Section III.A.2, replace “15” with “13”
PAGE 6 OF 89 GS-05P-11-SV-D-0042/01
28.) Page 14 of the C201, The entire Section III.B.2 FAR 216-1, Type of Contract (APR 84)
With:
The Government contemplates award of an IDIQ contract resulting from this solicitation. The task orders issued under the IDIQ contract shall be Firm- Fixed-Price.
29.) Page 23 of the C201, The entire Section V.G.,Evaluation of Joint Venture Offers
With:
In the evaluation of responsibility and non-price factors, information submitted for a party to the joint venture will not be evaluated to the extent that the terms of the joint venture agreement limit such party's performance or financial obligations as a party to the Contract contemplated by this Solicitation.
30.) The terms “Award Price Schedule” and “Contract Price Schedule” are used synonymously throughout the solicitation package.
31.) As applicable, the following Wage Determination revisions are made:
a) Wage Determination MI100007, Dated 10/14/2011
b) Wage Determination MI100195, Dated 10/14/2011
c) Wage Determination MI100199, Dated 10/14/2011
d) Wage Determination MI100202, Dated 10/14/2011
e) Wage Determination MI100205, Dated 10/14/2011
f) Wage Determination MI100204, Dated 10/14/2011
g) Wage Determination MI100188, Dated 10/14/2011
h) Wage Determination MI100192, Dated 10/14/2011
PAGE 7 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 2 Statewide – Highway – ZONE 1, 2 and 3
ZONE 1 - Macomb, Oakland, St. Clair and Wayne counties
General Decision Number: MI100007 10/14/2011 MI7
Superseded General Decision Number: MI20080007
State: Michigan
Construction Types: Highway (Highway, Airport & Bridge xxxxx and Sewer/Incid. to Hwy.)
Counties: Michigan Statewide.
Modification Number Publication Date 0 03/12/2010 1 03/19/2010 2 04/16/2010 3 05/07/2010 4 06/04/2010 5 06/18/2010 6 07/02/2010 7 08/06/2010 8 08/13/2010 9 09/03/2010 10 09/24/2010 11 11/05/2010 12 11/19/2010 13 12/03/2010 14 01/07/2011 15 01/14/2011 16 01/28/2011 17 02/11/2011 18 04/01/2011 19 04/15/2011 20 04/22/2011 21 05/06/2011 22 05/13/2011 23 06/03/2011 24 07/29/2011 25 08/19/2011 26 09/09/2011 27 09/30/2011 28 10/14/2011
CARP0004-004 06/01/2010
REMAINDER OF STATE
Rates Fringes
PAGE 8 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 3
CARPENTER ( Piledriver)..........$ 25.79 13.97
CARP0004-005 06/01/2010
LIVINGSTON (Townships of Brighton, Deerfield, Genoa, Hartland, Oceola & Tyrone), MACOMB, MONROE, OAKLAND, SANILAC, ST. CLAIR
AND WAYNE COUNTIES
CARPENTER (Piledriver)...........$ 28.23 20.07
ELEC0017-005 06/07/2010
HURON COUNTY; INGHAM COUNTY (Townships of Leroy, Locke, Wheatfield, White Oak and Williamson); LAPEER COUNTY; LENAWEE COUNTY (Townships of Clinton and Macon); LIVINGSTON COUNTY (Townships of Brighton, Conway, Genoa, Green Oak, Hamburg, Handy, Hartland, Howell, Iosco, Marion, Oceola and Putnam);
MACOMB COUNTY; MONROE COUNTY (Townships of Ash, Berlin, Dundee, Exeter, Frenchtown, Ida, London, Milan, Monroe, Raisinville and Summerfield); OAKLAND, ST. CLAIR, SANILAC AND TUSCOLA COUNTIES;
WASHTENAW COUNTY (Townships of Ann Arbor, Augusta, Bridgewater, Dexter, Freedom, Lima, Lodi, Northfield, Pittsfield, Salem, Saline, Scio, Superior, Webster, York and Ypsilanti); AND WAYNE
COUNTY:
Line Construction Groundman/Driver............$ 25.07 11.26 Journeyman Signal Tech......$ 34.05 13.57 Journeyman Specialist.......$ 39.16 14.88 Operator A..................$ 28.84 12.23 Operator B..................$ 26.94 11.74
Classifications
Journeyman Specialist: Refers to a crew of only one person working alone.
Operator A: Shall be proficient in operating all power equipment including: Backhoe, Excavator, Directional Bore and Boom/Digger truck.
Operator B: Shall be proficient in operating any 2 of the above mentioned pieces of equipment listed under Operator A.
ELEC0876-001 06/06/2011
Rates Fringes
LINE CONSTRUCTION
Cable Splicer...............$ 36.09 14.04 Light Equipment
PAGE 9 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 4 Statewide – Highway – ZONE 1, 2 and 3
Operator/Groundman/Truck Driver/Groundman (winch, A frame, diggers when used for distribution line truck and used for distribution work, distribution truck driver, 5th wheel type trucks, bucket trucks, ladder trucks and all live boom trucks, all equipment 85 hp or under)................$ 22.83 10.62 Lineman/Line Technician.....$ 35.35 25.75%+5.00 Operator/Groundman (digger, tractor and setting rig with tracks or rough terrain vehicle, large bombardier, backhoe over 85 hp, hydraulic crane 10 ton or over).......$ 26.06 11.46 Truck Driver/Groundman (trucks with winch or boom or dump, other than distribution work)..........$ 21.74 10.34
FOOTNOTE: Operators of 5/8 yard, rated capacity, backhoe or over; and operators of 25 ton, rated capacity, crane or over; and operators of heavy duty tension or pulling machinery on 345 KV and above: to receive the journeyman line technician rate of pay.
ENGI0324-003 07/01/2011
ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, CLARE, CLINTON,
CRAWFORD, GENESEE, GLADWIN, GRATIOT, HURON, INGHAM, IOSCO,
ISABELLA, JACKSON, LAPEER, LENAWEE, LIVINGSTON, MACOMB,
MIDLAND, MONROE, MONTMORENCY, OAKLAND, OGEMAW, OSCODA, OTSEGO,
PRESQUE ISLE, ROSCOMMON, SAGINAW, ST. CLAIR, SANILAC,
SHIAWASSEE, TUSCOLA, WASHTENAW AND WAYNE COUNTIES:
OPERATOR: Power Equipment (Steel Ereection)
GROUP 1....................$ 42.37 19.45
GROUP 2....................$ 43.37 19.45
GROUP 3....................$ 40.87 19.45
GROUP 4....................$ 41.87 19.45
GROUP 5....................$ 39.37 19.45
GROUP 6....................$ 40.37 19.45
GROUP 7....................$ 39.10 19.45
GROUP 8....................$ 40.10 19.45
GROUP 9....................$ 38.65 19.45
GROUP 10....................$ 39.65 19.45
GROUP 11....................$ 37.92 19.45
GROUP 12....................$ 38.92 19.45
PAGE 10 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 5 Statewide – Highway – ZONE 1, 2 and 3
GROUP 13....................$ 37.56 19.45
GROUP 14....................$ 38.56 19.45
GROUP 15....................$ 36.92 19.45
GROUP 16....................$ 30.11 19.45
GROUP 17....................$ 28.70 19.45
GROUP 18....................$ 35.47 19.45
FOOTNOTE:
Paid Holidays: New Year's Day, Memorial Day, Fourth of July, Labor Day, Thanksgiving Day and Christmas Day.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Engineer when operating combination of boom and jib 400' or longer
GROUP 2: Engineer when operating combination of boom and jib 400' or longer on a crane that requires an oiler
GROUP 3: Engineer when operating combination of boom and jib 300' or longer
GROUP 4: Engineer when operating combination of boom and jib 300' or longer on a crane that requires an oiler
GROUP 5: Engineer when operating combination of boom and jib 220' or longer
GROUP 6: Engineer when operating combination of boom and jib 220' or longer on a crane that requires an oiler
GROUP 7: Engineer when operating combination of boom and jib 140' or longer
GROUP 8: Engineer when operating combination of boom and jib 140' or longer on a crane that requires an oiler
GROUP 9: Tower crane & derrick operator (where operator's work station is 50 ft. or more above first sub-level)
GROUP 10: Tower crane & derrick operator (where operator's work station is 50 ft. or more above first sub-level) on a crane that requires an oiler
GROUP 11: Engineer when operating combination of boom and jib 120' or longer
GROUP 12: Engineer when operating combination of boom and jib 120' or longer on a crane that requires an oiler
GROUP 13: Crane operator; job mechanic and 3 drum hoist and excavator
GROUP 14: Crane operator on a crane that requires an oiler
GROUP 15: Hoisting operator; 2 drum hoist and rubber tired
PAGE 11 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 6 Statewide – Highway – ZONE 1, 2 and 3 backhoe
GROUP 16: Compressor or welder operator
GROUP 17: Oiler
GROUP 18: Forklift and 1 drum hoist
ENGI0324-004 05/01/2011
AREA 1: ALLEGAN, BARRY, BERRIEN, BRANCH, CALHOUN, CASS, EATON,
HILLSDALE, IONIA, KALAMAZOO, KENT, LAKE, MANISTEE, MASON,
MECOSTA, MONTCALM, MUSKEGON, NEWAYGO, OCEANA, OSCEOLA, OTTAWA,
ST. JOSEPH, VAN BUREN
AREA 2: ANTRIM, BENZIE, CHARLEVOIX, EMMET, GRAND TRAVERSE,
KALKASKA, LEELANAU, MISSAUKEE AND WEXFORD COUNTIES:
(Steel Erection)
AREA 1
GROUP 1....................$ 29.04 19.70
GROUP 2....................$ 28.79 19.70
GROUP 3....................$ 28.29 19.70
GROUP 4....................$ 23.19 19.70
GROUP 5....................$ 21.54 19.70
GROUP 6....................$ 18.94 19.70
AREA 2
GROUP 1....................$ 29.04 19.70
GROUP 2....................$ 28.79 19.70
GROUP 3....................$ 27.79 19.70
GROUP 4....................$ 22.89 19.70
GROUP 5....................$ 21.24 19.70
GROUP 6....................$ 18.44 19.70
FOOTNOTES:
Crane operator with main boom and jib 300' or longer: $1.50 additional to the group 1 rate. Crane operator with main boom and jib 400' or longer: $3.00 additional to the group 1 rate.
Certified Crane Operator Premiums:
a) Swing Boom Truck Operator over 12 tons-$.50 per hour
b) Hydraulic Crane Operator 75 tons and under-$.75 per hour
c) Hydraulic Crane Operator over 75 tons-$1.00 per hour
d) Lattiee Boom Crane Operator-$1.50 per hour
PAID HOLIDAYS: New Year's Day, Memorial Day, Fourth of July, Labor Day, Thanksgiving Day and Christmas Day.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS:
PAGE 12 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 7 Statewide – Highway – ZONE 1, 2 and 3
GROUP 1: Crane Operator with main boom & jib 400', 300', or 220' or longer. Tower Crane Operator with CCO certification for combined length of mast and boom 220' or longer.
GROUP 2: Crane Operator with main boom & jib 140' or longer, Tower Crane(Operators without CCO certification, or less than 220' length) Gantry Crane; Whirley Derrick.
GROUP 3: Regular Equipment Operator, Crane, Dozer, Loader, Hoist, Straddle Wagon, Mechanic, Grader and Hydro Excavator.
GROUP 4: Air Tugger (single drum), Material Hoist Pump 6" or over, Elevators, Brokk Concrete Breaker.
GROUP 5: Air Compressor, Welder, Generators, Conveyors
GROUP 6: Oiler and fire tender
* ENGI0324-005 09/01/2011
AREA 1: GENESEE, LAPEER, LIVINGSTON, MACOMB, MONROE, OAKLAND,
ST. CLAIR, WASHTENAW AND WAYNE COUNTIES
AREA 2: ALCONA, ALLEGAN, ALPENA, ANTRIM, ARENAC, BARRY, BAY,
BENZIE, BERRIEN, BRANCH, CALHOUN, CASS, CHARLEVOIX, CHEBOYGAN,
CLARE, CLINTON, CRAWFORD, EATON, EMMET, GLADWIN, GRAND
TRAVERSE, GRATIOT, HILLSDALE, HURON, INGHAM, IONIA, IOSCO,
ISABELLA, JACKSON, KALAMAZOO, KALKASKA, KENT, LAKE, LEELANAU,
LENAWEE, MANISTEE, MASON, MECOSTA, MIDLAND, MISSAUKEE,
MONTCALM, MONTMORENCY, MUSKEGON, NEWAYGO, OCEANA, OGEMAW,
OSCEOLA, OSCODA, OTSEGO, OTTAWA, PRESQUE ISLE, ROSCOMMON,
SAGINAW, SANILAC, SHIAWASSEE, ST. JOSEPH, TUSCOLA, VAN BUREN
AND WEXFORD COUNTIES
(Undrground construction (including sewer)
AREA 1:
GROUP 1....................$ 29.48 19.75
GROUP 2....................$ 24.75 19.75
GROUP 3....................$ 24.02 19.75
GROUP 4....................$ 23.45 19.75
AREA 2:
GROUP 1....................$ 27.77 19.75
GROUP 2....................$ 22.88 19.75
GROUP 3....................$ 22.38 19.75
GROUP 4....................$ 22.10 19.75
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Backfiller tamper; Backhoe; Batch plant operator (concrete); Clamshell; Concrete paver (2 drums or larger);
Conveyor loader (Euclid type); Crane (crawler, truck type or pile driving); Dozer; Dragline; Elevating grader;
PAGE 13 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 8 Statewide – Highway – ZONE 1, 2 and 3
Endloader; Gradall (and similar type machine); Grader;
Mechanic; Power shovel; Roller (asphalt); Scraper (self-propelled or tractor drawn); Side boom tractor (type D-4 or equivalent and larger); Slip form paver; Slope paver; Trencher (over 8 ft. digging capacity); Well drilling rig; Concrete pump with boom operator; Hydro Excavator
GROUP 2: Boom truck (power swing type boom); Crusher; Hoist;
Pump (1 or more - 6-in. discharge or larger - gas or diesel- powered or powered by generator of 300 amperes or more - inclusive of generator); Side boom tractor (smaller than type D-4 or equivalent); Tractor (pneu-tired, other than backhoe or front end loader); Trencher (8-ft. digging capacity and smaller);Vac Truck
GROUP 3: Air compressors (600 cfm or larger); Air compressors (2 or more-less than 600 cfm); Boom truck (non-swinging, non- powered type boom); Concrete breaker (self-propelled or truck mounted - includes compressor); Concrete paver (1 drum-l/2 yd. or larger); Elevator (other than passenger);
Maintenance person; Pump (2 or more-4-in. up to 6-in.
discharge-gas or diesel powered - excluding submersible pumps); Pumpcrete machine (and similar equipment); Wagon drill (multiple); Welding machine or generator (2 or more-300 amp. or larger - gas or diesel powered)
GROUP 4: Boiler; Concrete saw (40 hp or over); Curing machine (self-propelled); Farm tractor (with attachment); Finishing machine (concrete); Fire person; Hydraulic pipe pushing machine; Mulching equipment; Oiler; Pumps (2 or more up to 4-in. discharge, if used 3 hours or more a day, gas or diesel powered - excluding submersible pumps); Roller (other than asphalt); Stump remover; Trencher (service);
Vibrating compaction equipment, self-propelled (6 ft. wide or over); End dump operator; Sweeper (Wayne type); Water wagon and Extend-a boom forklift
ENGI0324-006 06/01/2011
AREA 1: GENESEE, MACOMB, MONROE, OAKLAND, WASHTENAW AND WAYNE
COUNTIES
AREA 2: ALCONA, ALGER, ALLEGAN, ALPENA, ANTRIM, ARENAC, BARAGA,
BARRY, BAY, BENZIE, BERRIEN, BRANCH, CALHOUN, CASS, CHARLEVOIX,
CHEBOYGAN, CHIPPEWA, CLARE, CLINTON, CRAWFORD, DELTA,
DICKINSON, EATON, EMMET, GLADWIN, GOGEBIC, GRAND TRAVERSE,
GRATIOT, HILLSDALE, HOUGHTON, HURON, INGHAM, IONIA, IOSCO,
IRON, ISABELLA, JACKSON, KALAMAZOO, KALKASKA, KENT, KEWEENAW,
LAKE, LAPEER, LEELANAU, LENAWEE, LIVINGSTON, LUCE, MACKINAC,
MANISTEE, MARQUETTE, MASON, MECOSTA, MENOMINEE, MIDLAND,
MISSAUKEE, MONTCALM, MONTMORENCY, MUSKEGON, NEWAYGO, OCEANA,
OGEMAW, ONTONAGON, OSCEOLA, OSCODA, OTSEGO, OTTAWA, PRESQUE
ISLE, ROSCOMMON, SAGINAW, ST. CLARE, ST. JOSEPH, SANILAC,
SCHOOLCRAFT, SHIAWASSEE, TUSCOLA, VAN BUREN AND WEXFORD COUNTIES
PAGE 14 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 9
Power equipment operators:
(AIRPORT, BRIDGE & HIGHWAY
CONSTRUCTION)
AREA 1
GROUP 1....................$ 28.41 19.75
GROUP 2....................$ 21.68 19.75
GROUP 3....................$ 22.98 19.75
GROUP 4....................$ 21.12 19.75
GROUP 5....................$ 20.95 19.75
AREA 2
GROUP 1....................$ 28.41 19.75
GROUP 2....................$ 21.53 19.75
GROUP 3....................$ 22.83 19.75
GROUP 4....................$ 20.97 19.75
GROUP 5....................$ 20.65 19.75
FOOTNOTE:
Certified Crane Operator (working on a bridge project) premiums: Swing boom truck operator over 12 tons: $.50 per hour additional. Hydraulic crane operator 75 tons and under: $.75 per hour additional. Hydraulic crane operator over 75 tons: $1.00 per hour additional. Lattice boom crane operator: $1.50 per hour additional.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Asphalt plant operator; Crane operator (does not include work on bridge construction projects when the crane operator is erecting structural components); Dragline operator; Shovel operator; Locomotive operator; Paver operator (5 bags or more); Elevating grader operator; Pile driving operator; Roller operator (asphalt); Blade grader operator; Trenching machine operator (ladder or wheel type); Auto-grader; Slip form paver; Self-propelled or tractor-drawn scraper; Conveyor loader operator (Euclid type); Endloader operator (1 yd. capacity and over);
Bulldozer; Hoisting engineer; Tractor operator; Finishing machine operator (asphalt); Mechanic; Pump operator (6-in.
discharge or over, gas, diesel powered or generator of 300 amp. or larger); Shouldering or gravel distributing machine operator (self- propelled); Backhoe (with over 3/8 yd.
bucket); Side boom tractor (type D-4 or equivalent or larger); Tube finisher (slip form paving); Gradall (and similar type machine); Asphalt paver (self- propelled);
Asphalt planer (self-propelled); Batch plant (concrete-central mix); Slurry machine (asphalt); Concrete pump (3 in. and over); Roto-mill; Swinging boom truck (over 12 ton capacity); Hydro demolisher (water blaster);
Farm-type tractor with attached pan
GROUP 2: Screening plant operator; Washing plant operator;
Crusher operator; Backhoe (with 3/8 yd. bucket or less);
Side boom tractor (smaller than D-4 type or equivalent);
Sweeper (Wayne type and similar equipment); Vacuum truck operator; Batch plant (concrete dry batch)
PAGE 15 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 10
GROUP 3: Grease Truck
GROUP 4: Air compressor operator (600 cu. ft. per min or more); Air compressor operator (two or more, less than 600 cfm); Wagon drill operator; Concrete breaker; Tractor operator (farm type with attachment)
GROUP 5: Boiler fire tender; Oiler; Fire tender; Trencher (service); Flexplane operator; Cleftplane operator; Grader operator (self-propelled fine-grade or form (concrete));
Finishing machine operator (concrete); Boom or winch hoist truck operator; Endloader operator (under 1 yd. capacity);
Roller operator (other than asphalt); Curing equipment operator (self-propelled); Concrete saw operator (40 h.p.
or over); Power bin operator; Plant drier operator (asphalt); Vibratory compaction equipment operator (6 ft.
wide or over); Guard post driver operator (power driven);
All mulching equipment; Stump remover; Concrete pump (under 3-in.); Mesh installer (self- propelled); Tractor operator (farm type); End dump; Skid steer
ENGI0324-007 05/01/2011
ALGER, BARAGA, CHIPPEWA, DELTA, DICKINSON, GOGEBIC, HOUGHTON,
IRON, KEWEENAW, LUCE, MACKINAC MARQUETTE, MENOMINEE, ONTONAGON
AND SCHOOLCRAFT COUNTIES:
(Steel Erection) Compressor, welder and forklift....................$ 23.58 19.45 Crane operator, main boom & jib 120' or longer........$ 27.33 19.45 Crane operator, main boom & jib 140' or longer........$ 27.58 19.45 Crane operator, main boom & jib 220' or longer........$ 27.83 19.45 Mechanic with truck and tools.......................$ 28.33 19.45 Oiler and fireman...........$ 22.28 19.45 Regular operator............$ 26.83 19.45
PREMIUM RATES:
A. Swing boom truck operator over 15 tons-$.50 per hour.
B. Hydraulic crane operator 75 tons and under-$.75 per hour.
C. Hydraulic crane operator over 75 tons-$1.00 per hour.
D. Lattice boom crane operator-$1.50 per hour.
ENGI0324-008 10/01/2010
ALCONA, ALGER, ALLEGAN, ALPENA, ANTRIM, ARENAC, BARAGA, BARRY,
BAY, BENZIE, BERRIEN, BRANCH, CALHOUN, CASS, CHARLEVOIX,
PAGE 16 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 11 Statewide – Highway – ZONE 1, 2 and 3
CHEBOYGAN, CHIPPEWA, CLARE, CLINTON, CRAWFORD, DELTA,
DICKINSON, EATON, EMMET, GENESEE, GLADWIN, GOGEBIC, GRAND
TRAVERSE, GRATIOT, HILLSDALE, HOUGHTON, HURON, INGHAM, IONIA,
IOSCO, IRON, ISABELLA, JACKSON, KALAMAZOO, KALKASKA, KENT,
KEWEENAW, LAKE, LAPEER, LEELANAU, LENAWEE, LIVINGSTON, LUCE,
MACKINAC, MACOMB, MANISTEE, MARQUETTE, MASON, MECOSTA,
MENOMINEE, MIDLAND, MISSAUKEE, MONTCALM, MONTMORENCY, MONROE,
MUSKEGON, NEWAYGO, OAKLAND, OCEANA, OGEMAW, ONTONAGON, OSCEOLA,
OSCODA, OTSEGO, OTTAWA, PRESQUE ISLE, ROSCOMMON, SAGINAW, ST.
CLARE, ST. JOSEPH, SANILAC, SCHOOLCRAFT, SHIAWASSEE, TUSCOLA,
VAN BUREN, WASHTENAW, WAYNE AND WEXFORD COUNTIES
(Sewer Relining)
GROUP 1.....................$ 28.65 11.64
GROUP 2.....................$ 27.12 11.64
SEWER RELINING CLASSIFICATIONS
GROUP 1: Operation of audio-visual closed circuit TV system, including remote in-ground cutter and other equipment used in connection with the CCTV system
GROUP 2: Operation of hot water heaters and circulation systems, water jetters and vacuum and mechanical debris removal systems
ENGI0325-010 05/01/2011
ALGER, BARAGA, CHIPPEWA, DELTA, DICKINSON, GOGEBIC, HOUGHTON,
IRON, KEWEENAW, LUCE, MACKINAC, MARQUETTE, MENOMINEE, ONTONAGON
(Underground Construction) Crane operator, main boom & jib 120' or longer........$ 26.93 19.45 Crane operator, main boom & jib 140' or longer........$ 27.18 19.45 Crane operator, main boom & jib 220' or longer........$ 27.43 19.45
GROUP 1.....................$ 26.43 19.45
GROUP 2.....................$ 23.18 19.45
GROUP 3.....................$ 22.60 19.45
GROUP 4.....................$ 21.66 19.45
Mechanic with truck and tools.......................$ 27.93 19.45
FOOTNOTES: Swing boom truck operator over 15 tons: $.50 per hour additional. Hydraulic crane operator 75 tons and under: $.75 per hour additional. Hydraulic crane operator
PAGE 17 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 12 Statewide – Highway – ZONE 1, 2 and 3 over 75 tons: $1.00 per hour additional. Lattice boom crane operator: $1.50 per hour additional. Crusher pit, shafts and tunnel workers: $2.00 per hour additional.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Regular equipment operator, crane, dozer, front end loader, job mechanic, pumpcrete and squeezecrete, concrete pump, excavator, milling and pulverizing machines, scraper (self-propelled and tractor drawn), welder
GROUP 2: Air track drill, boom truck (non-swing), concrete mixer, material hoist and tugger, pump 6" and over, beltcrete, sweeping machine, trencher, winches, well points and freeze systems
GROUP 3: Air compressor, conveyor, concrete saw, farm tractor (without attachments), fork truck, generator, guard post driver, mulching machine, pumps under 6-in., welding machine and grease person
GROUP 4: Oiler, fire tender, heater operator, brock concrete breaker, elevators (other than passenger), end dumps and skid steer
Crane Operator with main boom and jib 300' or longer shall be paid an additional one dollar and fifty cents ($1.50) per hour above the 220' of boom and jib wage rate.
Crane Operator with main boom and jib 400' or longer shall be paid an additional one dollar and fifty cents ($1.50) per hour above the 300 foot of boom wage rate ($3.00)
ENGI0325-011 10/01/2009
AREA 1: GENESEE, LAPEER, LIVINGSTON, MACOMB, MONROE, OAKLAND,
ST. CLAIR, WASHTENAW AND WAYNE COUNTIES
AREA 2: ALCONA, ALGER, ALLEGAN, ALPENA, ANTRIM, ARENAC, BARAGA,
BARRY, BAY, BENZIE, BERRIEN, BRANCH, CALHOUN, CASS, CHARLEVOIX,
CHEBOYGAN, CHIPPEWA, CLARE, CLINTON, CRAWFORD, DELTA,
DICKINSON, EATON, EMMET, GLADWIN, GOGEBIC, GRAND TRAVERSE,
GRATIOT, HILLSDALE, HOUGHTON, HURON, INGHAM, IONIA, IOSCO,
IRON, ISABELLA, JACKSON, KALAMAZOO, KALKASKA, KENT, KEWEENAW,
LAKE, LEELANAU, LENAWEE, LUCE, MACKINAC, MANISTEE, MARQUETTE,
MASON, MECOSTA, MENOMINEE, MIDLAND, MISSAUKEE, MONTCALM,
MONTMORENCY, MUSKEGON, NEWAYGO, OCEANA, OGEMAW, ONTONAGON,
OSCEOLA, OSCODA, OTSEGO, OTTAWA, PRESQUE ISLE, ROSCOMMON,
SAGINAW, ST. JOSEPH, SANILAC, SCHOOLCRAFT, SHIAWASSEE,
TUSCOLA, VAN BUREN AND WEXFORD COUNTIES
Power equipment operators -hazardous waste removal:
PAGE 18 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 13 Statewide – Highway – ZONE 1, 2 and 3
(AREA 1)
AREA 1: LEVEL A
Engineer when operating crane with boom and jib or leads 140' or longer....$ 34.48 17.80 Engineer when operating crane with boom and jib or leads 220' or longer....$ 34.78 17.80
GROUP 1....................$ 31.83 17.80
GROUP 2....................$ 27.60 17.80
Regular crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operator......$ 32.80 17.80
AREA 1: LEVEL B AND C
Engineer when operating crane with boom and jib or leads 140' or longer....$ 33.53 17.80 Engineer when operating crane with boom and jib or leads 220' or longer....$ 33.83 17.80
GROUP 1....................$ 30.88 17.80
GROUP 2....................$ 26.65 17.80
Regular crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, pwer shovel operator.......$ 31.85 17.80
AREA 1: LEVEL D WHEN
CAPPING LANDFILL
Engineer when operating crane with boom and jib or leads 140' or longer....$ 31.98 17.80 Engineer when operating crane with boom and jib or leads 220' or longer....$ 32.28 17.80
GROUP 1....................$ 29.33 17.80
GROUP 2....................$ 25.10 17.80
Regular crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operator......$ 29.68 17.80
AREA 1: LEVEL D
Engineer when operating crane with boom and jib or leads 140' or longer....$ 32.23 17.80 Engineer when operating crane with boom and jib or leads 220' or longer....$ 32.53 17.80
GROUP 1....................$ 29.58 17.80
GROUP 2....................$ 25.35 17.80
Regular crane operator, PAGE 19 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 14 Statewide – Highway – ZONE 1, 2 and 3 mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operator......$ 30.55 17.80 Power equipment operators -hazardous waste removal:
(AREA 2)
AREA 2: LEVELS B AND C
Regular crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operator......$ 30.14 17.80
AREA 2: LEVEL A
Engineer when operating crane with boom and jib or leads 140' or longer....$ 32.77 17.80 Engineer when operating crane with boom and jib or leads 220' or longer....$ 33.07 17.80
GROUP 1....................$ 30.12 17.80
GROUP 2....................$ 25.72 17.80
Regular crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operator......$ 31.09 17.80
AREA 2: LEVEL D WHEN
CAPPING LANDFILL
Engineer when operating crane with boom and jib or leads 140' or longer....$ 30.27 17.80 Engineer when operating crane with boom and jib or leads 220' or longer....$ 30.57 17.80
GROUP 1....................$ 27.62 17.80
GROUP 2....................$ 23.23 17.80
Regular crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operator......$ 28.59 17.80
AREA 2: LEVEL D
Engineer when operating crane with boom and jib or leads 140' or longer....$ 30.52 17.80 Engineer when operating crane with boom and jib or leads 220' or longer....$ 30.82 17.80
GROUP 1....................$ 27.87 17.80
GROUP 2....................$ 23.48 17.80
Regular crane operator, mechanic, dragline
PAGE 20 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 15 Statewide – Highway – ZONE 1, 2 and 3 operator, boom truck operator and concrete pump with boom operator, power shovel operator......$ 28.84 17.80
AREA 2: LEVELS B AND C
Engineer when operating crane with boom and jib or leads 140' or longer....$ 31.71 17.80 Engineer when operating crane with boom and jib or leads 220' or longer....$ 32.03 17.80
GROUP 1....................$ 29.17 17.80
GROUP 2....................$ 24.78 17.80
HAZARDOUS WASTE REMOVAL CLASSIFICATIONS
Group 1: Backhoe, batch plant operator, clamshell, concrete breaker when attached to hoe, concrete cleaning decontamination machine operator, concrete pump, concrete paver, crusher, dozer, elevating grader, endloader, farm tractor (90 h.p. and higher), gradall, grader,heavy equipment robotics operator, loader, pug mill, pumpcrete machines, pump trucks, roller, scraper (self- propelled or tractor drawn), side boom tractor, slip form paver, slope paver, trencher, ultra high pressure waterjet cutting tool system, vactors, vacuum blasting machine operator, vertical lifting hoist, vibrating compaction equipment (self-propelled), well drilling rig and hydro excavator
GROUP 2: Air compressor, concrete breaker when not attached to hoe, elevator, end dumps, equipment decontamination operator, farm tractor (less than 90 h.p.), forklift, generator, heater, mulcher, pigs (portable reagent storage tanks), power screens, pumps (water), stationary compressed air plant, sweeper, welding machine and water wagon
ENGI0325-012 05/01/2011
AREA 1: MACOMB, MONROE, OAKLAND, ST. CLAIR, WASHTENAW AND WAYNE
COUNTIES
AREA 2: ALCONA, ALGER, ALLEGAN, ALPENA, ANTRIM, ARENAC, BARAGA,
BARRY, BAY, BENZIE, BERRIEN, BRANCH, CALHOUN, CASS, CHARLEVOIX,
CHEBOYGAN, CHIPPEWA, CLARE, CLINTON, CRAWFORD, DELTA,
DICKINSON, EATON, EMMET, GENESEE, GLADWIN, GOGEBIC, GRAND
TRAVERSE, GRATIOT, HILLSDALE, HOUGHTON, HURON, INGHAM, IONIA,
IOSCO, IRON, ISABELLA, JACKSON, KALAMAZOO, KALKASKA, KENT,
KEWEENAW, LAKE, LAPEER, LEELANAU, LENAWEE, LIVINGSTON LUCE,
MACKINAC, MANISTEE, MARQUETTE, MASON, MECOSTA, MENOMINEE,
MIDLAND, MISSAUKEE, MONTCALM, MONTMORENCY, MUSKEGON, NEWAYGO,
OCEANA, OGEMAW, ONTONAGON, OSCEOLA, OSCODA, OTSEGO, OTTAWA,
PRESQUE ISLE, ROSCOMMON, SAGINAW, ST. JOSEPH, SANILAC,
SCHOOLCRAFT, SHIAWASSEE, TUSCOLA, VAN BUREN AND WEXFORD COUNTIES
Power equipment operators -
PAGE 21 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 16 Statewide – Highway – ZONE 1, 2 and 3 gas distribution and duct installation work:
AREA 1
GROUP 1....................$ 26.18 19.70
GROUP 2....................$ 26.05 19.70
GROUP 3....................$ 24.92 19.70
GROUP 4....................$ 24.35 19.70
AREA 2
GROUP 1....................$ 25.27 19.70
GROUP 2-A..................$ 25.17 19.70
GROUP 2-B..................$ 24.95 19.70
GROUP 3....................$ 24.17 19.70
GROUP 4....................$ 23.67 19.70
SCOPE OF WORK: The construction, installation, treating and reconditioning of pipelines transporting gas vapors within cities, towns, subdivisions, suburban areas, or within private property boundaries, up to and including private meter settings of private industrial, governmental or other premises, more commonly referred to as "distribution work," starting from the first metering station, connection, similar or related facility, of the main or cross country pipeline and including duct installation.
AREA 1:
GROUP 1: Backhoe, crane, grader, mechanic, dozer (D-6 equivalent or larger), side boom (D-4 equivalent or larger), trencher(except service), endloader (2 yd.
capacity or greater).
GROUP 2: Dozer (less than D-6 equivalent), endloader (under 2
yd. capacity), side boom (under D-4 capacity), backfiller, pumps (1 or 2 of 6-inch discharge or greater), boom truck (with powered boom), tractor (wheel type other than backhoe or front endloader).
GROUP 3: Tamper (self-propelled), boom truck (with non-powered boom), concrete saw (20 hp or larger), pumps (2 to 4 under 6-inch discharge), compressor (2 or more or when one is used continuously into the second day) and trencher(service).
GROUP 4: Oiler, hydraulic pipe pushing machine, grease person and hydrostatic testing operator.
AREA 2:
GROUP 1: Mechanic, crane (over 1/2 yd. capacity), backhoe (over 1/2 yd. capacity), grader (Caterpillar 12 equivalent or larger)
GROUP 2-A: Trencher(except service), backhoe (1/2 yd.
capacity or less)
GROUP 2-B: Crane (1/2 yd. capacity or less), compressor (2 or more), dozer (D-4 equivalent or larger), endloader (1 yd.
PAGE 22 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 17 Statewide – Highway – ZONE 1, 2 and 3 capacity or larger), pump (1 or 2 six-inch or larger), side boom (D-4 equivalent or larger)
GROUP 3: Backfiller, boom truck (powered), concrete saw (20 hp or larger), dozer (less than D-4 equivalent), endloader (under 1 yd. capacity), farm tractor (with attachments), pump (2 - 4 under six-inch capacity), side boom tractor(less than D-4 equivalent), tamper (self-propelled), trencher service and grader maintenance
GROUP 4: Oiler, grease person and hydrostatic testing operator
IRON0008-007 06/07/2010
ALGER, BARAGA, CHIPPEWA, DELTA, DICKINSON, GOGEBIC, HOUGHTON,
IRON, KEWEENAW, LUCE, MACKINAC MARQUETTE, MENOMINEE, ONTONAGON
Ironworker - pre-engineered metal building erector...........$ 23.70 6.95
IRONWORKER
General contracts $10,000,000 or greater......$ 24.93 21.47 General contracts less than $10,000,000............$ 21.84 21.47
IRON0025-002 09/01/2009
ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, CLARE, CLINTON,
CRAWFORD, GENESEE, GLADWIN, GRATIOT, HURON, INGHAM, IOSCO,
ISABELLA, JACKSON, LAPEER, LIVINGSTON, MACOMB, MIDLAND,
MONTMORENCY, OAKLAND, OGEMAW, OSCODA, OTSEGO, PRESQUE ISLE,
ROSCOMMON, SAGINAW, SANILAC, SHIAWASSEE, ST. CLAIR, TUSCOLA,
WASHTENAW AND WAYNE COUNTIES:
Ironworker - pre-engineered metal building erector Alcona, Alpena, Arenac, Cheboygan, Clare, Clinton, Crawford, Gladwin, Gratiot, Huron, Ingham, Iosco, Isabella, Jackson, Lapeer, Livingston (west of Burkhardt Road), Montmorency, Ogemaw, Oscoda, Otsego, Presque Isle, Roscommon, Sanilac, Shiawassee, Tuscola & Washtenaw (west of U.S. 23).$ 19.88 19.72 Bay, Genesee, Lapeer, Livingston (east of
PAGE 23 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 18 Statewide – Highway – ZONE 1, 2 and 3
Burkhardt Road), Macomb, Midland, Oakland, Saginaw, St. Clair, The University of Michigan, Washtenaw (east of U.S. 23) & Wayne...$ 21.10 20.72
IRONWORKER
Ornamental and Structural...$ 29.26 27.62 Reinforcing.................$ 26.83 24.26
IRON0055-005 07/01/2010
LENAWEE AND MONROE COUNTIES:
Rates Fringes
IRONWORKER
Pre-engineered metal buildings...................$ 23.28 18.30 All other work..............$ 28.00 18.30
IRON0292-003 06/01/2010
BERRIEN AND CASS COUNTIES:
Rates Fringes
IRONWORKER (Including pre-engineered metal building erector).........................$ 25.05 17.21
IRON0340-001 07/01/2011
ALLEGAN, ANTRIM, BARRY, BENZIE, BRANCH, CALHOUN, CHARLEVOIX,
EATON, EMMET, GRAND TRAVERSE, HILLSDALE, IONIA, KALAMAZOO,
KALKASKA, KENT, LAKE, LEELANAU, MANISTEE, MASON, MECOSTA,
MISSAUKEE, MONTCALM, MUSKEGON, NEWAYGO, OCEANA, OSCEOLA,
OTTAWA, ST. JOSEPH, VAN BUREN AND WEXFORD COUNTIES:
IRONWORKER (Including pre-engineered metal building erector).........................$ 20.68 23.92
LABO0005-006 10/01/2010
Rates Fringes
Laborers - hazardous waste abatement: (ALCONA, ALPENA, ANTRIM, BENZIE, CHARLEVOIX, CHEBOYGAN, CRAWFORD, EMMET, GRAND TRAVERSE, IOSCO, KALKASKA, LEELANAU, MISSAUKEE, MONTMORENCY, OSCODA, OTSEGO, PRESQUE ISLE
PAGE 24 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 19 Statewide – Highway – ZONE 1, 2 and 3
AND WEXFORD COUNTIES - Zone 10) Levels A, B or C............$ 18.50 11.49 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 17.50 11.49 Laborers - hazardous waste abatement: (ALGER, BARAGA, CHIPPEWA, DELTA, DICKINSON, GOGEBIC, HOUGHTON, IRON, KEWEENAW, LUCE, MACKINAC, MARQUETTE, MENOMINEE, ONTONAGON AND SCHOOLCRAFT
COUNTIES - Zone 11) Levels A, B or C............$ 22.92 11.54 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 21.92 11.54 Laborers - hazardous waste abatement: (ALLEGAN, BARRY, BERRIEN, BRANCH, CALHOUN, CASS, IONIA COUNTY (except the city of Portland);
KALAMAZOO, KENT, LAKE,
MANISTEE, MASON, MECOSTA,
MONTCALM, MUSKEGON, NEWAYGO,
OCEANA, OSCEOLA, OTTAWA, ST.
JOSEPH AND VAN BUREN COUNTIES
- Zone 9) Levels A, B or C............$ 20.03 11.49 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 19.03 11.49 Laborers - hazardous waste abatement: (ARENAC, BAY, CLARE, GLADWIN, GRATIOT, HURON, ISABELLA, MIDLAND, OGEMAW, ROSCOMMON, SAGINAW
AND TUSCOLA COUNTIES - Zone 8) Levels A, B or C............$ 21.26 11.49 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 20.26 11.49 Laborers - hazardous waste abatement: (CLINTON, EATON
PAGE 25 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 20 Statewide – Highway – ZONE 1, 2 and 3
AND INGHAM COUNTIES; IONIA
COUNTY (City of Portland);
LIVINGSTON COUNTY (west of Oak Grove Rd., including the City of Howell) - Zone 6) Levels A, B or C............$ 21.85 11.49 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 20.85 11.49 Laborers - hazardous waste abatement: (GENESEE, LAPEER
AND SHIAWASSEE COUNTIES -
Zone 7) Levels A, B or C............$ 22.64 11.51 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 21.64 11.51 Laborers - hazardous waste abatement: (HILLSDALE, JACKSON AND LENAWEE COUNTIES
- Zone 4) Levels A, B or C............$ 21.56 11.49 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 20.56 11.49 Laborers - hazardous waste abatement: (LIVINGSTON COUNTY (east of Oak Grove Rd. and south of M-59, excluding the city of Howell); AND WASHTENAW COUNTY - Zone 3) Levels A, B or C............$ 27.21 12.45 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 26.21 12.45 Laborers - hazardous waste abatement: (MACOMB AND WAYNE COUNTIES - Zone 1) Levels A, B or C............$ 26.54 13.97 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 25.54 13.97
PAGE 26 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 21 Statewide – Highway – ZONE 1, 2 and 3
Laborers - hazardous waste abatement: (MONROE COUNTY - Zone 4) Levels A, B or C............$ 27.64 12.56 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 26.64 12.56 Laborers - hazardous waste abatement: (OAKLAND COUNTY and the Northeast portion of LIVINGSTON COUNTY bordered by Oak Grove Road on the West and M-59 on the South - Zone 2) Level A, B, C...............$ 26.54 13.97 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 25.54 13.97 Laborers - hazardous waste abatement: (SANILAC AND ST.
CLAIR COUNTIES - Zone 5) Levels A, B or C............$ 24.35 13.67 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 23.35 13.67
* LABO0259-001 09/01/2011
AREA 1: MACOMB, OAKLAND AND WAYNE COUNTIES
AREA 2: ALCONA, ALGER, ALLEGAN, ALPENA, ANTRIM, ARENAC, BARAGA,
BARRY, BAY, BENZIE, BERRIEN, BRANCH, CALHOUN, CASS, CHARLEVOIX,
CHEBOYGAN, CHIPPEWA, CLARE, CLINTON, CRAWFORD, DELTA,
DICKINSON, EATON, EMMET, GENESEE, GLADWIN, GOGEBIC, GRAND
TRAVERSE, GRATIOT, HILLSDALE, HOUGHTON, HURON, INGHAM, IONIA,
IOSCO, IRON, ISABELLA, JACKSON, KALAMAZOO, KALKASKA, KENT,
KEWEENAW, LAKE, LAPEER, LEELANAU, LENAWEE, LIVINGSTON, LUCE,
MACKINAC, MANISTEE, MARQUETTE, MASON, MECOSTA, MENOMINEE,
MIDLAND, MISSAUKEE, MONROE, MONTCALM, MONTMORENCY, MUSKEGON,
NEWAYGO, OCEANA, OGEMAW, ONTONAGON, OSCEOLA, OSCODA, OTSEGO,
OTTAWA, PRESQUE ISLE, ROSCOMMON, SAGINAW, ST. CLARE, ST.
JOSEPH, SANILAC, SCHOOLCRAFT, SHIAWASSEE, TUSCOLA, VAN BUREN,
WASHTENAW AND WEXFORD COUNTIES
Laborers - tunnel, shaft and caisson:
PAGE 27 OF 89 GS-05P-11-SV-D-0042/01
Wages - Page 22 Statewide – Highway – ZONE 1, 2 and 3
AREA 1
GROUP 1....................$ 21.37 14.58
GROUP 2....................$ 21.48 14.58
GROUP 3....................$ 21.54 14.58
GROUP 4..
This is the start of the file's text. The full file is on GovTribe.