This solicitation requests proposals for design-build services to construct two to six cottages and site infrastructure improvements at the Smithsonian Environmental Research Center. The Smithsonian Institution seeks a contractor to be singularly responsible for satisfying the terms of the resulting firm fixed-price contract. Offerors must meet all requirements set forth in the solicitation documents, including cost and schedule proposals, to be considered for selection and subsequent contract execution for this project located at 647 Contees Wharf Road in Edgewater, Maryland. Evaluation will be conducted in accordance with FAR Subpart 15 using the stated criteria.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SF Project No. 128211

S P E C I F I C A T I O N S

TABLE OF CONTENTS

DIVISION 1 GENERAL REQUIREMENTS

010000 Supplementary Conditions for Construction

PROJECT SUMMARY AND INFORMATION

1. Project Information

2. Summary of Work

3. Contract Time for Completion

4. Schedule of Options for Proposal

5. Schedule of Unit Prices

6. Bidder/Offeror Examination of Site

7. Availability of Documents

SPECIAL PROJECT REQUIREMENTS

8. Units of Measure

9. Non-Public, Tenant and Secured Spaces

10. Museum Artifacts and Scientific Research Materials

11. Protection of Historic Properties

12. Commitment to Sustainability

13. Commissioning

CONTRACTOR USE OF PREMISES

14. Hours of Work, Workdays and Government Holidays

15. Conditions Affecting Contractor’s Work

16. Contractor Deliveries, Hauling and Access

17. Dress and Deportment

18. Contractor Parking

19. Eating, Drinking, Smoking and Illegal Substance Abuse

PROJECT COORDINATION

20. Coordination of Trades

21. Quality Control

22. Permits, Licenses and Fees

23. Utility Service Interruptions and New Connections

24. Smithsonian-Furnished Items Installed by the Contractor

25. Salvage

26. Cutting, Patching and Matching Existing Work

PROTECTION OF THE SITE DURING CONSTRUCTION

27. Protection of the Site

28. Protection of Flora, Fauna and Central Computer Controller Irrigation

System

29. Debris Control and Daily Cleanup

30. Dust and Air Quality Control

31. Noise Control

32. Vermin, Pest and Rodent Control

33. Drilling, Welding andTorchCutting

TEMPORARY CONSTRUCTION FACILITIES

34. Contractor Field Offices, Trailers and Sheds

35. Staging, Storage and Work Areas

36. Sanitary Facilities

37. Temporary Utility Services and Extensions

38. Scaffolding and Platforms

39. Project Signs

MEETINGS

40. Preconstruction Meeting

41. Pre-Condition Survey of the Site

42. Project Meetings

SUBMISSIONS

43. Submittal Definitions

44. Submittals and Reviews

45. Criteria for Product Selection

46. ProgressPhotographs

47. Contractor Correspondence and Daily Reports

SAFETY, HEALTH AND FIRE PROTECTION

48. Jobsite Safety

49. Toxic and Hazardous Substances

50. Personal Protective Equipment

51. Barriers, Barricades and Walkways

52. Existing Fire Protection Systems

SECURITY REQUIREMENTS

53. General Security Requirements

54. Identification Badges

55. Access and Property Control at the Museum Support Center

56. Security of Temporary Openings

57. Existing Building Alarm Systems

58. Security Guard Duty Charges

SCHEDULES AND PAYMENTS

59. Schedule of Values

60. Scheduling & Payments / Bar Chart

61. Scheduling & Payments / Critical Path Method

62. Assignment of Claims

PROJECT CLOSEOUT REQUIREMENTS

63. Project Closeout

64. Substantial Completion

65. Final Completion and Acceptance

017419 Construction Waste Management and Disposal

(The following divisions are to be completed by the Design-Build Team for the Cottages)

DIVISION 2 EXISTING CONDITIONS

DIVISION 3 CONCRETE

DIVISION 4 MASONRY

DIVISION 5 METALS

DIVISION 6 WOOD,PLASTICS AND COMPOSITES

DIVISION 7 THERMAL AND MOISTURE PROTECTION

DIVISION 8 OPENINGS

DIVISION 9 FINISHES

DIVISION 10 SPECIALTIES

DIVISION 11 EQUIPMENT

DIVISION 12 FURNISHINGS

DIVISION 13 SPECIAL CONSTRUCTION

DIVISION 14 CONVEYING EQUIPMENT

DIVISIONS 15-20 RESERVED

DIVISION 21 FIRE SUPPRESSION

DIVISION 22 PLUMBING

DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING

DIVISION 24 RESERVED

DIVISION 25 INTEGRATED AUTOMATION

DIVISION 26 ELECTRICAL

DIVISION 27 COMMUNICATIONS

DIVISION 28 ELECTRONIC SAFETY AND SECURITY

DIVISION 29 RESERVED

DIVISION 30 RESERVED

DIVISION 31 EARTHWORK

DIVISION 32 EXTERIOR IMPROVEMENTS

DIVISION 33 UTILITIES

Appendix XX

END OF TABLE OF CONTENTS

• Civil/Site Work, including demolition, paving, site utilities, stormwater & drainage improvements

• Domestic Water

• Reuse/Fire Protection Water

• Sanitary Sewer

• Electrical

• Mechanical

• Plumbing

• Smithsonian Security Systems

• Telecommunication Systems

• Fire Alarm Systems

• Slab on Grade

• Exterior shell

• Roofing

• Interior partitions

• Modular Pre-Fabricated Construction

• Passive House Design mailto:cwsod@collinswharfsod.com

NOT USED

SF Project No. 1282111

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 1

SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for the following:

1. Salvaging nonhazardous demolition and construction waste.

2. Recycling nonhazardous demolition and construction waste.

3. Disposing of nonhazardous demolition and construction waste.

B. Related Requirements:

1. Section 024119 "Selective Demolition" for disposition of waste resulting from partial demolition of site improvements and for disposition of hazardous waste.

2. Section 044313 "Anchored Stone Masonry Veneer" for disposal requirements for excess stone and stone waste.

3. Section 311000 "Site Clearing" for disposition of waste resulting from site clearing and removal of above- and below-grade improvements.

1.3 DEFINITIONS

A. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.

B. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations.

C. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.

D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.

E. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.

F. Salvage and Reuse: Recovery of demolition or construction waste and subsequent incorporation into the Work.

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 2

1.4 PERFORMANCE REQUIREMENTS

A. General: Practice efficient waste management in the use of materials in the course of the Work.

Use all reasonable means to divert construction and demolition waste from landfills and incinerators. Facilitate recycling and salvage of materials including the following:

1. Demolition Waste:

a. Asphalt paving.

b. Copper wiring.

c. Lighting fixtures.

d. Switchgear and panelboards.

e. Transformers.

f. Topsoil.

2. Construction Waste:

a. Masonry and CMU.

b. Lumber.

c. Metals.

d. Piping.

e. Electrical conduit.

f. Packaging: Regardless of salvage/recycle goal indicated in "General" Paragraph above, salvage or recycle 100 percent of the following uncontaminated packaging materials:

1) Paper.

2) Cardboard.

3) Boxes.

4) Plastic sheet and film.

5) Polystyrene packaging.

6) Wood crates.

7) Plastic pails.

1.5 ACTION SUBMITTALS

A. Waste Management Plan: Submit plan within 10 days of date established for the Notice to

Proceed.

1.6 INFORMATIONAL SUBMITTALS

A. Waste Reduction Calculations: Before request for Substantial Completion, submit calculated end-of-Project rates for salvage, recycling, and disposal as a percentage of total waste generated by the Work. Use Form CWM-7 for construction waste and Form CWM-8 for demolition waste reporting.

B. Qualification Data: For waste management coordinator.

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 3

1.7 QUALITY ASSURANCE

A. Waste Management Coordinator Qualifications: Experienced firm, with a record of successful waste management coordination of projects with similar requirements, that employs a LEED-

Accredited Professional, certified by the USGBC, as waste management coordinator.

B. Regulatory Requirements: Comply with hauling and disposal regulations of authorities having jurisdiction.

C. Waste Management Conference: Conduct conference at Project site to comply with requirements in Section 010000.40 "Meetings- Pre-Construction" Review methods and procedures related to waste management including, but not limited to, the following:

1. Review and discuss waste management plan including responsibilities of waste management coordinator.

2. Review requirements for documenting quantities of each type of waste and its disposition.

3. Review and finalize procedures for materials separation and verify availability of containers and bins needed to avoid delays.

4. Review procedures for periodic waste collection and transportation to recycling and disposal facilities.

5. Review waste management requirements for each trade.

1.8 WASTE MANAGEMENT PLAN

A. General: Develop a waste management plan according to ASTM E 1609 and requirements in this Section. Plan shall consist of waste identification and waste reduction work plan. Indicate quantities by weight or volume, but use same units of measure throughout waste management plan.

B. Waste Identification: Indicate anticipated types and quantities of demolition, site-clearing, and construction waste generated by the Work. Use Form CWM-1 for construction waste and

Form CWM-2 for demolition waste. Include estimated quantities and assumptions for estimates.

C. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Use Form CWM-3 for construction waste and

Form CWM-4 for demolition waste. Include points of waste generation, total quantity of each type of waste, quantity for each means of recovery, and handling and transportation procedures.

1. Salvaged Materials for Reuse: For materials that will be salvaged and reused in this

Project, describe methods for preparing salvaged materials before incorporation into the

Work.

2. Salvaged Materials for Sale: For materials that will be sold to individuals and organizations, include list of their names, addresses, and telephone numbers.

3. Salvaged Materials for Donation: For materials that will be donated to individuals and organizations, include list of their names, addresses, and telephone numbers.

4. Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept. Include names, addresses, and telephone numbers.

5. Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility.

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 4

6. Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location where materials separation will be performed.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 PLAN IMPLEMENTATION

A. General: Implement approved waste management plan. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract.

1. Comply with operation, termination, and removal requirements in Section 010000.34-37

"Temporary Construction Facilities."

B. Waste Management Coordinator: Engage a waste management coordinator to be responsible for implementing, monitoring, and reporting status of waste management work plan.

C. Training: Train workers, subcontractors, and suppliers on proper waste management procedures, as appropriate for the Work.

1. Distribute waste management plan to everyone concerned within two days of submittal return.

2. Distribute waste management plan to entities when they first begin work on-site. Review plan procedures and locations established for salvage, recycling, and disposal.

D. Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

1. Designate and label specific areas on Project site necessary for separating materials that are to be salvaged, recycled, reused, donated, and sold.

2. Comply with Section 010000.27-32 "Protection of the Site During Construction" for controlling dust and dirt, environmental protection, and noise control.

3.2 SALVAGING DEMOLITION WASTE

A. Salvaged Items for Reuse in the Work: Salvage items for reuse and handle as follows:

1. Sort and stockpile salvaged items.

2. Store or stockpile items in a secure area within specified project limits until installation.

3. Protect items from damage during transport and storage.

4. Install salvaged items to comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make items functional for use indicated.

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 5

B. Salvaged Items for Sale and Donation: Permitted on Project site.

C. Salvaged Items for Owner's Use: Salvage items for Owner's use and handle as follows:

1. Sort and stockpile salvaged items.

2. Store or stockpile items in a secure area as designated by the COTR.

3. Transport items to Owner's storage area on-site as designated by COTR.

4. Protect items from damage during transport and storage.

D. Electrical Devices: BGE/Verizon to remove and/or relocate their own equipment and cabling;

contractor to coordinate with COTR and BGE/Verizon as noted in Utility Plans.

3.3 RECYCLING WASTE, GENERAL

A. General: Recycle paper and beverage containers used by on-site workers.

B. Recycling Incentives: Revenues, savings, rebates, tax credits, and other incentives received for recycling waste materials shall accrue to Contractor.

C. Preparation of Waste: Prepare and maintain recyclable waste materials according to recycling or reuse facility requirements. Maintain materials free of dirt, adhesives, solvents, petroleum contamination, and other substances deleterious to the recycling process.

D. Procedures: Separate recyclable waste from other waste materials, trash, and debris. Separate recyclable waste by type at Project site to the maximum extent practical according to approved construction waste management plan.

1. Provide appropriately marked containers or bins for controlling recyclable waste until removed from Project site. Include list of acceptable and unacceptable materials at each container and bin.

2. Stockpile processed materials on-site without intermixing with other materials. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.

3. Stockpile materials away from construction area. Do not store within drip line of remaining trees.

4. Store components off the ground and protect from the weather.

5. Remove recyclable waste from Owner's property and transport to recycling receiver or processor.

3.4 RECYCLING DEMOLITION WASTE

A. Asphalt Paving: Break up and transport paving to asphalt-recycling facility.

3.5 RECYCLING CONSTRUCTION WASTE

A. Packaging:

1. Cardboard and Boxes: Break down packaging into flat sheets. Bundle and store in a dry location.

2. Polystyrene Packaging: Separate and bag materials.

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 6

3. Pallets: As much as possible, require deliveries using pallets to remove pallets from

Project site. For pallets that remain on-site, break down pallets into component wood pieces and comply with requirements for recycling wood.

4. Crates: Break down crates into component wood pieces and comply with requirements for recycling wood.

B. Wood Materials:

1. Clean Cut-Offs of Lumber: Grind or chip into small pieces.

2. Clean Sawdust: Bag sawdust that does not contain painted or treated wood.

a. Comply with requirements in Section 329300 "Plants" for use of clean sawdust as organic mulch.

3.6 DISPOSAL OF WASTE

A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.

1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn waste materials.

C. Disposal: Remove waste materials from Owner's property and legally dispose of them.

3.7 ATTACHMENTS

A. Form CWM-1 for construction waste identification.

B. Form CWM-2 for demolition waste identification.

C. Form CWM-3 for construction waste reduction work plan.

D. Form CWM-4 for demolition waste reduction work plan.

E. Form CWM-7 for construction waste

F. Form CWM-8 for demolition waste.

END OF SECTION 017419

02-Specs_Div1LgProj_2021-01-15
1. PROJECT INFORMATION
2. SUMMARY OF WORK
3. CONTRACT TIME FOR COMPLETION
4. SCHEDULE OF OPTIONS FOR BID
5. SCHEDULE OF UNIT PRICES – NOT USED
6. BIDDER EXAMINATION OF SITE
7. AVAILABILITY OF DOCUMENTS
8. UNITS OF MEASURE
9. NON-PUBLIC, TENANT AND SECURED SPACES
10. SCIENTIFIC RESEARCH MATERIALS
11. PROTECTION OF HISTORIC PROPERTIES – NOT USED
13. COMMISSIONING- NOT USED
14. HOURS OF WORK, WORKDAYS AND GOVERNMENT HOLIDAYS
15. CONDITIONS AFFECTING CONTRACTOR'S WORK
16. CONTRACTOR DELIVERIES, HAULING AND ACCESS
17. DRESS AND DEPORTMENT
18. CONTRACTOR PARKING
19. EATING, DRINKING, SMOKING AND ILLEGAL SUBSTANCE ABUSE
20. COORDINATION OF TRADES
21. QUALITY CONTROL
22. PERMITS, LICENSES & FEES
23. UTILITY SERVICE INTERRUPTIONS AND NEW CONNECTIONS
24. SMITHSONIAN-FURNISHED ITEMS INSTALLED BY THE CONTRACTOR
25. SALVAGE
26. CUTTING, PATCHING AND MATCHING EXISTING WORK
27. PROTECTION OF THE SITE
28. PROTECTION OF FLORA AND FAUNA
29. DEBRIS CONTROL AND DAILY CLEANUP
30. DUST AND AIR QUALITY CONTROL
31. NOISE CONTROL
32. VERMIN, PEST AND RODENT CONTROL - NOT USED
33. DRILLING, WELDING AND TORCH CUTTING
34. CONTRACTOR FIELD OFFICES, TRAILERS AND SHEDS
35. STAGING, STORAGE AND WORK AREAS
36. SANITARY FACILITIES
37. TEMPORARY UTILITY SERVICES AND EXTENSIONS
38. SCAFFOLDING AND PLATFORMS
38.1. The Contractor shall erect temporary scaffolding in accordance with OSHA 29 CFR 1926.451 and ANSI A10.8. The Contractor shall provide landing platforms with stairways or ladders for proper access and egress to all work areas.
38.2. For all frame scaffolding greater than 4 m in height, the Contractor shall submit working drawings to the COTR a minimum of ten (10) working days in advance of scaffolding erection. Working drawings submitted by the Contractor shall be certifie...
38.3. During non-working hours, the Contractor shall close and lock the scaffolding with a physical barrier to prevent access by unauthorized persons.
39. PROJECT SIGNS
40. PRECONSTRUCTION MEETING
41. PRE-CONDITION SURVEY OF THE SITE
42. PROJECT MEETINGS
43. SUBMITTAL DEFINITIONS
44. SUBMITTALS AND REVIEWS
45. CRITERIA FOR PRODUCT SELECTION
46. PROGRESS PHOTOGRAPHS
47. CONTRACTOR CORRESPONDENCE AND DAILY REPORTS
48. JOBSITE SAFETY
49. TOXIC AND HAZARDOUS SUBSTANCES
50. PERSONAL PROTECTIVE EQUIPMENT
51. BARRICADES, BARRIERS AND WALKWAYS
52. EXISTING FIRE PROTECTION SYSTEMS
53. GENERAL SECURITY REQUIREMENTS
54. IDENTIFICATION BADGES
55. ACCESS AND PROPERTY CONTROL AT THE MUSEUM SUPPORT CENTER
56. SECURITY OF TEMPORARY OPENINGS - NOT USED
57. EXISTING BUILDING ALARM SYSTEMS
58. SECURITY GUARD DUTY CHARGES
59. SCHEDULE OF VALUES
60. SCHEDULING & PAYMENTS / BAR CHART- NOT USED
61. SCHEDULING & PAYMENTS / CRITICAL PATH METHOD
62. ASSIGNMENT OF CLAIMS
63. PROJECT CLOSEOUT
64. SUBSTANTIAL COMPLETION
65. FINAL COMPLETION AND ACCEPTANCE
017419 FL - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL_RFP
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Salvaging nonhazardous demolition and construction waste.
2. Recycling nonhazardous demolition and construction waste.
3. Disposing of nonhazardous demolition and construction waste.
B. Related Requirements:
1. Section 024119 "Selective Demolition" for disposition of waste resulting from partial demolition of site improvements and for disposition of hazardous waste.
2. Section 044313 "Anchored Stone Masonry Veneer" for disposal requirements for excess stone and stone waste.
3. Section 311000 "Site Clearing" for disposition of waste resulting from site clearing and removal of above- and below-grade improvements.
1.3 DEFINITIONS
A. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
B. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations.
C. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.
D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
E. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.
F. Salvage and Reuse: Recovery of demolition or construction waste and subsequent incorporation into the Work.
1.4 PERFORMANCE REQUIREMENTS
A. General: Practice efficient waste management in the use of materials in the course of the Work. Use all reasonable means to divert construction and demolition waste from landfills and incinerators. Facilitate recycling and salvage of materials incl...
1. Demolition Waste:
a. Asphalt paving.
b. Copper wiring.
c. Lighting fixtures.
d. Switchgear and panelboards.
e. Transformers.
f. Topsoil.
2. Construction Waste:
a. Masonry and CMU.
b. Lumber.
c. Metals.
d. Piping.
e. Electrical conduit.
f. Packaging: Regardless of salvage/recycle goal indicated in "General" Paragraph above, salvage or recycle 100 percent of the following uncontaminated packaging materials:
1) Paper.
2) Cardboard.
3) Boxes.
4) Plastic sheet and film.
5) Polystyrene packaging.
6) Wood crates.
7) Plastic pails.
1.5 ACTION SUBMITTALS
A. Waste Management Plan: Submit plan within 10 days of date established for the Notice to Proceed.
1.6 INFORMATIONAL SUBMITTALS
A. Waste Reduction Calculations: Before request for Substantial Completion, submit calculated end-of-Project rates for salvage, recycling, and disposal as a percentage of total waste generated by the Work. Use Form CWM-7 for construction waste and Fo...
B. Qualification Data: For waste management coordinator.
1.7 QUALITY ASSURANCE
A. Waste Management Coordinator Qualifications: Experienced firm, with a record of successful waste management coordination of projects with similar requirements, that employs a LEED-Accredited Professional, certified by the USGBC, as waste management...
B. Regulatory Requirements: Comply with hauling and disposal regulations of authorities having jurisdiction.
C. Waste Management Conference: Conduct conference at Project site to comply with requirements in Section 010000.40 "Meetings- Pre-Construction" Review methods and procedures related to waste management including, but not limited to, the following:
1. Review and discuss waste management plan including responsibilities of waste management coordinator.
2. Review requirements for documenting quantities of each type of waste and its disposition.
3. Review and finalize procedures for materials separation and verify availability of containers and bins needed to avoid delays.
4. Review procedures for periodic waste collection and transportation to recycling and disposal facilities.
5. Review waste management requirements for each trade.
1.8 WASTE MANAGEMENT PLAN
A. General: Develop a waste management plan according to ASTM E 1609 and requirements in this Section. Plan shall consist of waste identification and waste reduction work plan. Indicate quantities by weight or volume, but use same units of measure th...
B. Waste Identification: Indicate anticipated types and quantities of demolition, site-clearing, and construction waste generated by the Work. Use Form CWM-1 for construction waste and Form CWM-2 for demolition waste. Include estimated quantities and ...
C. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Use Form CWM-3 for construction waste and Form CWM-4 for demolition waste. Include points of waste generation, ...
1. Salvaged Materials for Reuse: For materials that will be salvaged and reused in this Project, describe methods for preparing salvaged materials before incorporation into the Work.
2. Salvaged Materials for Sale: For materials that will be sold to individuals and organizations, include list of their names, addresses, and telephone numbers.
3. Salvaged Materials for Donation: For materials that will be donated to individuals and organizations, include list of their names, addresses, and telephone numbers.
4. Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept. Include names, addresses, and telephone numbers.
5. Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility.
6. Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location where materials separation will be performed.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 PLAN IMPLEMENTATION
A. General: Implement approved waste management plan. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract.
1. Comply with operation, termination, and removal requirements in Section 010000.34-37 "Temporary Construction Facilities."
B. Waste Management Coordinator: Engage a waste management coordinator to be responsible for implementing, monitoring, and reporting status of waste management work plan.
C. Training: Train workers, subcontractors, and suppliers on proper waste management procedures, as appropriate for the Work.
1. Distribute waste management plan to everyone concerned within two days of submittal return.
2. Distribute waste management plan to entities when they first begin work on-site. Review plan procedures and locations established for salvage, recycling, and disposal.
D. Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Designate and label specific areas on Project site necessary for separating materials that are to be salvaged, recycled, reused, donated, and sold.
2. Comply with Section 010000.27-32 "Protection of the Site During Construction" for controlling dust and dirt, environmental protection, and noise control.
3.2 SALVAGING DEMOLITION WASTE
A. Salvaged Items for Reuse in the Work: Salvage items for reuse and handle as follows:
1. Sort and stockpile salvaged items.
2. Store or stockpile items in a secure area within specified project limits until installation.
3. Protect items from damage during transport and storage.
4. Install salvaged items to comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make items functional for use indicated.
B. Salvaged Items for Sale and Donation: Permitted on Project site.
C. Salvaged Items for Owner's Use: Salvage items for Owner's use and handle as follows:
1. Sort and stockpile salvaged items.
2. Store or stockpile items in a secure area as designated by the COTR.
3. Transport items to Owner's storage area on-site as designated by COTR.
4. Protect items from damage during transport and storage.

D. Electrical Devices: BGE/Verizon to remove and/or relocate their own equipment and cabling; contractor to coordinate with COTR and BGE/Verizon as noted in Utility Plans.

3.3 RECYCLING WASTE, GENERAL
A. General: Recycle paper and beverage containers used by on-site workers.
B. Recycling Incentives: Revenues, savings, rebates, tax credits, and other incentives received for recycling waste materials shall accrue to Contractor.
C. Preparation of Waste: Prepare and maintain recyclable waste materials according to recycling or reuse facility requirements. Maintain materials free of dirt, adhesives, solvents, petroleum contamination, and other substances deleterious to the recy...
D. Procedures: Separate recyclable waste from other waste materials, trash, and debris. Separate recyclable waste by type at Project site to the maximum extent practical according to approved construction waste management plan.
1. Provide appropriately marked containers or bins for controlling recyclable waste until removed from Project site. Include list of acceptable and unacceptable materials at each container and bin.
2. Stockpile processed materials on-site without intermixing with other materials. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
3. Stockpile materials away from construction area. Do not store within drip line of remaining trees.
4. Store components off the ground and protect from the weather.
5. Remove recyclable waste from Owner's property and transport to recycling receiver or processor.
3.4 RECYCLING DEMOLITION WASTE
A. Asphalt Paving: Break up and transport paving to asphalt-recycling facility.
3.5 RECYCLING CONSTRUCTION WASTE
A. Packaging:
1. Cardboard and Boxes: Break down packaging into flat sheets. Bundle and store in a dry location.
2. Polystyrene Packaging: Separate and bag materials.
3. Pallets: As much as possible, require deliveries using pallets to remove pallets from Project site. For pallets that remain on-site, break down pallets into component wood pieces and comply with requirements for recycling wood.
4. Crates: Break down crates into component wood pieces and comply with requirements for recycling wood.
B. Wood Materials:
1. Clean Cut-Offs of Lumber: Grind or chip into small pieces.
2. Clean Sawdust: Bag sawdust that does not contain painted or treated wood.
a. Comply with requirements in Section 329300 "Plants" for use of clean sawdust as organic mulch.
3.6 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn waste materials.
C. Disposal: Remove waste materials from Owner's property and legally dispose of them.
3.7 ATTACHMENTS
A. Form CWM-1 for construction waste identification.
B. Form CWM-2 for demolition waste identification.
C. Form CWM-3 for construction waste reduction work plan.
D. Form CWM-4 for demolition waste reduction work plan.
E. Form CWM-7 for construction waste
F. Form CWM-8 for demolition waste.