Green Village Amendment Three.pdf
PDF 1 MB Posted
- Attached to
- Green Village Cottages Amendment Four
- Solicitation number
- 33330221RF0010024
- Issued by
-
Smithsonian Institution
About this file
This solicitation requests design-build proposals for the construction of two to six cottages and site infrastructure improvements at the Smithsonian Environmental Research Center. Offerors must be prepared to provide both design and construction services on a firm fixed-price basis. Proposals are due by June 30, 2021, and the contract will be awarded competitively based on evaluation criteria specified in the solicitation. Subcontracting goals are established for small businesses including a minimum of 40% for small businesses overall as well as subsets for small disadvantaged, women-owned, HUB Zone, veteran-owned, and service-disabled veteran-owned small businesses. The Smithsonian Institution will execute the contract with the selected offeror to provide design-build services for this project.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
33330221RF0010024
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
OCON
Washington DC 20013-7012
MRC 1200
P.O. BOX 37012
SMITHSONIAN INSTITUTION
06/16/20210003
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/13/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
A. The Solicitation Number cited above, for the Green Village Cottages and Site
Improvements, located at the Smithsonian Environmental Research Center (SERC), is hereby amended as follows:
A.1. The Davis Bacon Wage Determinations to be used for this project are: MD20210039, Modification No. 4 dated 06/04/2021; and MD20210060 dated 01/01/2021.
A.2. The SI Subcontracting Goals for Small Businesses are as follows: 40%- A minimum of the planned subcontracting dollars to be placed with small business concerns. The following are subsets of the small business goals: 7%- A minimum of dollars to be placed with small disadvantaged businesses (SDB), including Historically Black Universities or
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Willard B. Powell
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
33330221RF0010024/0003
Minority Institutions; 7%- A minimum of dollars to be placed with Women-Owned small businesses
(WOSB); 4%- A minimum of dollars to be placed with HUB Zone (HubSB) small businesses; 4%- A minimum of dollars to be placed with
Veteran-Owned small businesses (VOSB); and 4%- A minimum of dollars to be placed with Service
Disabled Veteran-Owned small businesses (SDVOSB).
A.3. Offerors RFI's and Smithsonian responses are attached hereto.
B.1. The Due Date for Receipt of Proposals remains June 30, 2021 at 12:00 noon.
END OF AMENDMENT THREE
Period of Performance: 05/13/2021 to 06/30/2021
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
RESPONSES TO BIDDER QUESTIONS/ RFP Solicitation:
1282111 SERC Green Village Design-Build
RFI QUESTION RESPONDENT RESPONSE 6/11/21
1 Please confirm if the project is to be complete within 365 days as called for on page
15 paragraph 3.a.1 or 300 days as called for on page 18 paragraph 2.1, or if there is a difference between the two completion dates.
SI-PM/DM
The time for project completion is 365 days.
2 Please confirm that Design Build projects that exceed the scope and complexity of this project will be accepted as relevant
SI-PM/DM
Confirmed.
3 Section 1 Design-Build Team page 10 of solicitation calls for resumes and organizational chart for required team members, the same requirement for resumes and organizational chart is called out in Section 2 Key Team Members for both construction and design team. Please confirm if we are to duplicate the resumes in both sections or if not please confirm which section should reflect resumes and org chart.
SI-PM/DM
The required information can be provided in section 1 and cross-referenced in section 2.
4 Please confirm if the project superintendent can also act as project safety manager and project quality control manager.
SI-CM
Confirmed.
5 Paragraph 2.3.1 Access of the Program Narrative state that the fire truck turn around has been relaxed. Please confirm that the bridged design that was provided with the
RFP meets the requirements for the turn around or if the design builder has to devise a solution that is code compliant.
SI-DM/OSHEM
The information shown in the site improvement plans and narrative has been coordinated with the Anne Arundel County Fire Marshal and provides for an adequate T turn around for fire apparatus.
6 Paragraph 5.2 Ventilation of the Program Narrative state that “the proposed design does not include the mechanical ventilation system required by ASHRAE 62.2 for buildings that are thermally conditioned for more than 876 hours per year”. Please confirm if the Design-Builder is to incorporate this requirement into our design or if this requirement is being waived.
SI-PM/DM
This language will be removed from the Narrative. The Design-Build contractor must determine all applicable ASHRAE requirements as part of their design of the cottages and the requirement for the Cottages to be Passive House certified.
7 Paragraph 6.3.6 Non-Potable Reclaimed Water of the Program Narrative seems to duplicate the section prior covering Potable Water. Please confirm what is covered under Non-Potable section.
SI-
SERC/PM/DM
Section 6.3.6 will be revised as follows:
6.3.6 Non-Potable Reclaimed Water
New 8" DIP reclaimed water lines shall be provided extending from existing DIP reclaimed water.
One reclaimed water line will run from the southwest corner of the site, along the existing woodland parking stalls, and terminate at a fire hydrant positioned to serve the future lodge. The second reclaimed water line will extend from the existing reclaimed water running east-west between the existing dormitory and the proposed cottages. A fire hydrant shall be added off the existing reclaimed water line, near the northwest corner of the dormitory. There shall be a 4" DIP sprinkler line connection to each cottage and one caped to serve the future lodge. Reclaimed
Water is intended to be used for fire protection (sprinkler systems) and gray water purposes
(toilet flushing and exterior hose bibb). Each cottage will require an internal split to provide these services.
8 Please confirm that in the first two cottages (#1& #2) that are to meet ADA code requirements that those requirements only apply to the first floor of each cottage and that the second floor bathrooms don’t need to comply with ADA.
SI-
SERC/PM/DM
Confirmed.
9 There are references to IBC 2015 throughout the Program Narrative except in the electrical section which references IBC 2017. Please confirm that electrical should also follow 2015 IBC.
SI-DM
The latest edition of IBC shall be utilized in the DB development. 2021 edition.
10 In program narrative item 1.2 Cottage: The first two cottages will be ADA accessible on the first level. Does that mean that the plans for the other cottages will be tweaked for non ADA compliant rooms and therefore additional floor plans required?
SI-
SERC/PM/DM
The first two cottages require ADA accessibility on the first level. The remaining cottages do not and therefore the plans may vary. However, it may be more cost effective to exactly replicate all six cottages. Either approach is acceptable.
11 In program narrative item 1.2 Cottage: It states that each pair of cottages should be designed as connected duplexes, however other section indicates single building.
Please confirm if these are to be constructed as Duplexes.
SI-
SERC/PM/DM
The cottages are not required to be duplexes. Cottages shall be designed and sited as individual units constructed in pairs as shown on the site improvement drawings.
12 Floor plans attached are not dated. Please confirm these floor plans are the March
12th plans referenced in the RFP
SI-DM
Confirmed.
13 Floor plans included seem to indicate stacked washer and dryer. There are some commercial stacked washer and dryers available where controls are within reach range, however it is very difficult to actually get the clothes out of the back of the dryer when it is stacked. Should a side by side W/D be provided?
SI-
SERC/PM/DM
Washer and dryer will be provided and installed by SERC. Cottages designs shall accommodate a stacked washer/dryer configuration with all necessary utilities for service.
14 Section 3.1 references porches. Porches are not shown on the plans provided.
Should we assume porches to be included?
SI-
SERC/PM/DM
No porches are required. An exterior deck connecting each pair of cottages shall be provided as indicated on the site improvement plans.
15 Section 2.5.1 of the RFP indicates that, “MDE has been engaged by the SI and A/E of record for the site improvements work and will continue coordinating and obtaining
MDE approvals and permits for the project.” This statement reads as though the
MDE process has been initiated by the Smithsonian and Dewberry and that they will continue to secure permit approvals. Please clarify the work that has been done on the MDE front to date and what work is the responsibility of AE2 (the design/builder’s A/E).
SI-PM/DM
The SI and A/E of record for the site improvements work will obtain MDE approvals and permits for the project and provide such to the DB Contractor. The DB Contractor will be responsible for coordinating MDE inspections and other typical activities during construction. If the DB
Contractor requires revisions to the MDE permit for any reason they will be responsible for any
MDE coordination and permit revisions.
16 Please provide more detail on the design intent and requirements of the “Wetness
Gradient Garden”. Is this intended to be an interpretive feature with signage and other interactive elements?
SI-
SERC/PM/DM
Signage is not required.
RESPONSES TO BIDDER QUESTIONS, RFP Solicitation No. F18R010034 Page 1 of 2
17 Please clarify what is to be priced to comply with MDE’s requirements? Addition of a forebay and maintenance of the existing pond plus three Filterras? There is insufficient time to for AE2 to coordinate with Amanda Malcom or Colin Hiltner and determine the site-specific requirements for the project before bid day. The pricing risk for this should not be borne solely by the design/builder.
SI-
SERC/PM/DM
Bidders should price what is shown on the site improvement drawings and specs. The work shown reflects MDE coordination and input. The DB Contractor will be responsible for construction and any MDE compliance items including inspections and any plan or permit revisions.
18 The roadway grading plan shows an inverted section with trench drains and no curbs.
This is fairly unorthodox for residential construction. Will a more traditional, crowned roadway with curbs and roadside swales be considered? What was the driver for the inverted section/trench drain arrangement?
SI-
SERC/PM/DM
Construction shall be as shown on the site improvement plans and specs.
19 The grading plan shows 6:1 (+/-) grading in and around the cottages, but they are to be slab on grade construction. Slab on grade construction requires a flat pad to be graded in. Some retaining walls are shown on the layout plans, but the grades to not tie into them properly nor do they extend the entire length of the cottages. Is the intent for there to be wall placed along the back of all of the cottages and for that wall to be tied to the building foundation in some fashion?
SI-
SERC/PM/DM
Bidders should price what is shown on the site improvement drawings and specs. The DB
Contractor is responsible for design of the cottages and coordination with the site improvement plans. Design of the cottages should work with the grading design. If in the course of designing the duplex cottages adjustments are needed to the grading plan the DB Contractor shall propose such changes and be responsible for revisions to the site improvement plans. The requirement for the cottages to be duplexes has been removed. Cottages shall be individual dwellings constructed in pairs as shown on the site plans. This aligns with the original concept design. Each pair includes a rear "knee wall" for each cottage duo. A "final grading plan" is attached to show the design intent. A standalone retaining wall was not contemplated with the current grading.
The "knee wall" was used in lieu of a retaining wall to minimize steep slope impacts and clearing.
The knee wall approach allowed grade to be maintained higher on the rear of the cottages and still provide a drainage swale on the back side for conveyance around the cottage duos to provided storm drain inlets.
20 Offsite drainage appears to be an issue with the finished floor elevations of the cottages. What is the design intent as far as waterproofing and routing flows around the buildings to the yard inlets? The grading plan shows flow into the buildings.
SI-PM/DM
Bidders should price what is shown on the site improvement drawings and specs. The DB
Contractor is responsible for design of the cottages and coordination with the site improvement plans. Design of the duplex cottages should strive to work with the current grading design. If in the course of designing the duplex cottages adjustments are needed to the grading plan the DB
Contractor shall propose such changes and be responsible for revisions to the site improvement plans as approved by SI.
21 Are there any clearance requirements for potable water and reclaimed water piping runs? SI-DM
Minimum cover over potable water, reclaimed water and FDC shall be 4 feet. See note 13 on
Sheet C-1-4. Horizontal clearances shall be as shown on the utility plans. Vertical clearances shall be a minimum of 1 ft.
22 There does not appear to be a turnaround area for a fire apparatus provided. Will one be required?
SI-
SERC/PM/DM/
OSHEM
The information shown in the site improvement plans and narrative has been coordinated with the Anne Arundel County Fire Marshal and provides for an adequate T turn around for fire apparatus.
23 Is the intent of the grading plan to balance the earthwork? We note that unit costs are requested for unsuitable soils. Are there earthwork estimated that have been prepared for the concept design?
SI-PM/DM
That is the intent. Earthwork will be optimized to balance as closely as possible. No additional information is available beyond what is shown in the drawings and specs.
24 Please confirm if supply and install of furniture is included in the design-builders number
SI-
SERC/PM/DM
Furniture is not included in the DB contract. Furniture will be procured by SERC.
RESPONSES TO BIDDER QUESTIONS, RFP Solicitation No. F18R010034 Page 2 of 2
T
CONC.
EXISTING BUILDING (TRAILER)
F.F.=53.91'
B.F.=43.42'
OVERHANG
CONC.
12" TREE
18" TREE
20" TREE
18" TREE
18" TREE
24" OAK
12" TREE
TWIN
40" TREE
E D
G E
O F
P A
V E
M
E N
T
GATE
EX. HC SIGNS
GATE
CONC. PORCH
C
O
N
C
S
W
W A
L L
EXISTING
SHED
EX.
BLDG
F.F.=53.92'
EXISTING BUILDING
OVERHANG
EXISTING BUILDING
F.F.=52.66'
18" TREE
12" TREE
TWIN
12" TREE
18" TREE
15" TREE
24" TREE
18" TREE
20" TREE
12" TREE
18" TREE
20" TREE
TWIN
18" TREE
18" TREE
I N
V E
R
T
SIGN
SECURITY
D
I
T
C
H
SIGN
RESEARCH
PARKING
E D
G E
O
F
U
N P
A V
D
R
CONC.
E D
P
A V
E M
E N
WALL
I P
A P
E
D
U
N
P
A
V
E D
U
N P
A V
TRENCH DRAIN
INV EL=50.68'
TOP EL=52.18'
TOP EL=43.37'
RIP RAP
AC
H
E
D
6" PVC
6" PVC
P V
C
8" PVC
15" TREE
EX. WOODLAND PARKING
(ASPHALT)
E
E
E
X
C
M
B
A
N
D
E
X
L
E
C
FUTURE
COTTAGE #2
F U
T U
R
E
C
O
T T
A
F
U
T
U
R
E
C
O
T
T
A
F U
T U
R E
C O
T T
A G
E
F
U
T
U
R
E
C
O
T
T
A
F U
T U
R E
LO
D
G E
F U
T U
R E
C O
T T
A G
E
ES
MH
MH
I
I
I
I
I
ES
I
T R
E N
C H
D R
A
IN
T
D -3
P
E
H
D
P
E
P
E
H
D P
E
H
D
P
E
H
D P
E
H
D P
E
P
E
H
D P
E
ROOF DRAIN
ROOF DRAIN
S
S
I
TR
EN
C H
D R
AIN
(TD
-2)
T R
E N
C H
D R
A
IN
(T D
-1
P
E
FFE = 41.0
0 55
PROPOSED RETAINING WALL
PROPOSED RAILING
PROPOSED BUILDING
PROPOSED DRIVE
EXISTING TREELINE
EXISTING TOPOGRAPHY
EXISTING ASPHALT
EXISTING GRAVEL ROAD
EXISTING BUILDING
EXISTING STORM DRAIN
EXISTING RECLAIMED WATER
LEGEND
EXISTING POTABLE WATER
EXISTING SEWER
EXISTING CLEAN OUT
EXISTING SIGN
EXISTING ELECTRIC HAND HOLE
EXISTING POWER POLE
EXISTING LIGHT POLE
EXISTING TREE
EXISTING TELECOMM
EXISTING COMMUNICATION LINE
EXISTING UNDERGROUND POWER
PROPOSED TOPOGRAPHY
PROPOSED LIMIT OF
DISTURBANCE
PROPOSED SPOT ELEVATION
PROPOSED STORM DRAIN
PROPOSED TREELINE
PROPOSED SIDEWALK
TREE PIT FOR
PROPOSED FILTERRA
UNIT OR SIMILAR SWM
FEATURE (TYP. 3)
NOTE: GRADING IS SUBJECT TO CHANGE THROUGHOUT FINAL
ENGINEERING DESIGN.
CONNECT TO EX.
S/W AT GRADE
CONNECT TO EX.
S/W AT GRADE
CONNECT TO EX.
S/W AT GRADE
NOTE: THIS PLAN IS FOR FINAL GRADING ONLY
Smithsonian Institution
Washington, DC 20024-2520 600 Maryland Avenue S.W. Suite 5001
Smithsonian Facilities
Dewberry Engineers, Inc.
10461 MILL RUN CIRCLE
SUITE 300
OWINGS MILLS, MD 21117
(P) 410.265.9500
WWW.DEWBERRY.COM
Federal Reserve Bank Building
100 North 6th Street
Philadelphia, PA 19106-1590
Tel: 215-923-2020 Fax: 215-574-0952
PROFESSIONAL
CERTIFICATION:
S
T
A
MA
R
Y
L
A
N
D
P
R
O
F
E
S
S
I
O
N
L
G
I
N
E
E
R
N
1 7
G U
R
M
E
I
NG
H
U
N
I A
EXISTING ENHANCED EXTENDED
DETENTION POND
P R
O P
O S
B
U I L
D I N
G P
R O
P O
S E
D
R
E T
A I N
I N
G
W
A L
L P
R O
P O
S E
D
S
I D
E W
A L
K P
R O
P O
S E
D
R
A I L
I N
G
CONNECT TO EX.
ASPH. DRIVE AT
GRADE
X
M
A
X
BEST MANAGEMENT PRACTICES FOR WORKING IN NONTIDAL WETLANDS, WETLAND BUFFERS,
WATERWAYS, AND 100-YEAR FLOODPLAINS
(APPLIES TO EAST SIDE OF LOD, IN AND IMMEDIATELY ADJACENT TO EXISTING WETLAND BUFFER)
1) NO EXCESS FILL, CONSTRUCTION MATERIAL, OR DEBRIS SHALL BE STOCKPILED OR STORED IN
NONTIDAL WETLANDS, NONTIDAL WETLAND BUFFERS, WATERWAYS, OR THE 100-YEAR
FLOODPLAIN.
2) PLACE MATERIALS IN A LOCATION AND MANNER WHICH DOES NOT ADVERSELY IMPACT SURFACE
OR SUBSURFACE WATER FLOW INTO OR OUT OF NONTIDAL WETLANDS, NONTIDAL WETLAND
BUFFERS, WATERWAYS, OR THE 100-YEAR FLOODPLAIN.
3) DO NOT USE THE EXCAVATED MATERIAL AS BACKFILL IF IT CONTAINS WASTE METAL PRODUCTS, UNSIGHTLY DEBRIS, TOXIC MATERIAL, OR ANY OTHER DELETERIOUS SUBSTANCE. IF ADDITIONAL
BACKFILL IS REQUIRED, USE CLEAN MATERIAL FREE OF WASTE METAL PRODUCTS, UNSIGHTLY
DEBRIS, TOXIC MATERIAL, OR ANY OTHER DELETERIOUS SUBSTANCE
4) PLACE HEAVY EQUIPMENT ON MATS OR SUITABLY OPERATE THE EQUIPMENT TO PREVENT
DAMAGE TO NONTIDAL WETLANDS, NONTIDAL WETLAND BUFFERS, WATERWAYS, OR THE
100-YEAR FLOODPLAIN.
5) REPAIR AND MAINTAIN ANY SERVICEABLE STRUCTURE OR FILL SO THERE IS NO PERMANENT
LOSS OF NONTIDAL WETLANDS, NONTIDAL WETLAND BUFFERS, OR WATERWAYS, OR
PERMANENT MODIFICATION OF THE 100-YEAR FLOODPLAIN IN EXCESS OF THAT LOST UNDER
THE ORIGINALLY AUTHORIZED STRUCTURE OR FILL.
6) RECTIFY ANY NONTIDAL WETLANDS, NONTIDAL WETLAND BUFFERS, WATERWAYS, OR 100-YEAR
FLOODPLAIN TEMPORARILY IMPACTED BY ANY CONSTRUCTION.
7) ALL STABILIZATION IN THE NONTIDAL WETLAND AND NONTIDAL WETLAND BUFFER SHALL
CONSIST OF THE FOLLOWING SPECIES: ANNUAL RYEGRASS (LOLIUM MULTIFLORUM), MILLET
(SETARIA ITALICA), BARLEY (HORDEUM SP.), OATS (UNIOLA SP.), AND/OR RYE (SECALE CEREALE).
THESE SPECIES WILL ALLOW FOR THE STABILIZATION OF THE SITE WHILE ALSO ALLOWING FOR
THE VOLUNTARY REVEGETATION OF NATURAL WETLAND SPECIES. OTHER NON-PERSISTENT
VEGETATION MAY BE ACCEPTABLE, BUT MUST BE APPROVED BY THE NONTIDAL WETLANDS AND
WATERWAYS DIVISION. KENTUCKY 31 FESCUE SHALL NOT BE UTILIZED IN WETLAND OR BUFFER
AREAS. THE AREA SHOULD BE SEEDED AND MULCHED TO REDUCE EROSION AFTER
CONSTRUCTION ACTIVITIES HAVE BEEN COMPLETED.
8) AFTER INSTALLATION HAS BEEN COMPLETED, MAKE POST-CONSTRUCTION GRADES AND
ELEVATIONS THE SAME AS THE ORIGINAL GRADES AND ELEVATIONS IN TEMPORARILY IMPACTED
AREAS.
9) TO PROTECT AQUATIC SPECIES, IN-STREAM WORK IS PROHIBITED AS DETERMINED BY THE
CLASSIFICATION OF THE STREAM:
USE I WATERS: IN-STREAM WORK SHALL NOT BE CONDUCTED DURING THE PERIOD MARCH 1
THROUGH JUNE 15, INCLUSIVE, DURING ANY YEAR.
USE III WATERS: IN-STREAM WORK SHALL NOT BE CONDUCTED DURING THE PERIOD
OCTOBER 1 THROUGH APRIL 30, INCLUSIVE, DURING ANY YEAR.
USE IV WATERS: IN-STREAM WORK SHALL NOT BE CONDUCTED DURING THE PERIOD MARCH
1 THROUGH MAY 31, INCLUSIVE, DURING ANY YEAR.
10) STORMWATER RUNOFF FROM IMPERVIOUS SURFACES SHALL BE CONTROLLED TO PREVENT THE
WASHING OF DEBRIS INTO THE WATERWAY.
11) CULVERTS SHALL BE CONSTRUCTED AND ANY RIPRAP PLACED SO AS NOT TO OBSTRUCT THE
MOVEMENT OF AQUATIC SPECIES, UNLESS THE PURPOSE OF THE ACTIVITY IS TO IMPOUND
WATER.
AutoCAD SHX Text
FINAL GRADING PLAN
AutoCAD SHX Text
AutoCAD SHX Text C
AutoCAD SHX Text
AutoCAD SHX Text 3A
AutoCAD SHX Text
CIVIL
AutoCAD SHX Text
ADDRESS
AutoCAD SHX Text
SF PROJECT NUMBER
AutoCAD SHX Text
A/E PROJECT NUMBER
AutoCAD SHX Text
PROJECT TITLE
AutoCAD SHX Text
DRAWING TITLE
AutoCAD SHX Text
DRAWING TYPE
AutoCAD SHX Text
WORKING STAFF
AutoCAD SHX Text
DESIGNED BY
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
CHECKED BY
AutoCAD SHX Text
DISCIPLINE
AutoCAD SHX Text
TYPE
AutoCAD SHX Text
SEQUENCE
AutoCAD SHX Text
SUBMISSION
AutoCAD SHX Text
DATE
AutoCAD SHX Text
BUILDING NAME
AutoCAD SHX Text
SHEET NO.
AutoCAD SHX Text
STAMP
AutoCAD SHX Text
SERC
AutoCAD SHX Text 5/15/2020
AutoCAD SHX Text
100%%% SUBMISSION
AutoCAD SHX Text 1282111
AutoCAD SHX Text 20160482/50088876
AutoCAD SHX Text
EJG
AutoCAD SHX Text
EJG
AutoCAD SHX Text
GSG
AutoCAD SHX Text
OF 20
AutoCAD SHX Text
CONTEES WHARF ROAD EDGEWATER, MD
AutoCAD SHX Text
GREEN VILLAGE SITE INFRASTRUCTURE
AutoCAD SHX Text
ST-TTL.DWG
AutoCAD SHX Text
SCALE : 1"=20'
AutoCAD SHX Text
GRAPHIC SCALE(S)
AutoCAD SHX Text
KEY PLAN
AutoCAD SHX Text 20'
AutoCAD SHX Text 0'
AutoCAD SHX Text 40'
AutoCAD SHX Text 10'
AutoCAD SHX Text
GRAPHIC SCALE
AutoCAD SHX Text 1"=20'
AutoCAD SHX Text I HEREBY CERTIFY THAT THESE DOCUMENTS WERE PREPARED OR APPROVED BY ME, AND THAT I AM DULY LICENSED PROFESSIONAL ENGINEER UNDER THE LAWS OF THE STATE OF MARYLAND, LICENSE NO. 17155, EXPIRATION DATE: 17155, EXPIRATION DATE: , EXPIRATION DATE: NOVEMBER 27, 2020..
AutoCAD SHX Text
REVISION 1
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
REVISION 2
AutoCAD SHX Text
REVISION 3
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
REVISION 4
AutoCAD SHX Text
REVISION 5
AutoCAD SHX Text
REVISION 6
AutoCAD SHX Text
REVISION 7
AutoCAD SHX Text
REVISION 8
AutoCAD SHX Text
REVISION 9
AutoCAD SHX Text
REVISION 10
AutoCAD SHX Text
FOR INFO ONLY
| Green Village RFIs.pdf |
| 2021-06-03 1282111 SERC-GV PreBid RFIs_01_Response |
| 2021-06-02 |
| 2020-06-09_GreenVillage_FinalGrading |
| Sheets and Views |
| Final Grading |
File details come from the government source that posted it. Updated .