This document is a set of plans and specifications for a stream crossing at the Vesle Run on the Fort Indiantown Gap facility in Lebanon County, Pennsylvania. The work includes the installation of 10-inch ductile iron water pipe, with associated appurtenances such as fire hydrants and valves, over a total distance of 11,283 linear feet. A mandatory pre-bid conference will be held on June 6, 2024, and bids are due by 2:00 PM on June 26, 2024. Bids must be submitted electronically through the Pennsylvania Supplier Portal.

The estimated range for the general construction work is $1,500,001.00 to $2,000,000.00, with liquidated damages of $500.00 per day. The contract will be awarded through a standard low-bid process, and all potential bidders must attend the pre-bid conference to be eligible to submit a bid. Questions related to the project are due by 4:30 PM EST on June 14, 2024.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EDGE OF WOODS

EDGE OF WOODS

440 441

435436437438439

440441442

EDGE OF ASPHALT

EDGE OF ASPHALT

EDGE OF ASPHALT

0+00 0+200+10 0+30 0+40 0+50 0+60 0+70 0+80 0+90 1+00 1+10 1+20 1+30

SCALECHECKED BY

DRAWING NO.DRAWN BY DATE

REVISIONS

DESCRIPTION DATENO.

Professional's Signature Date

DESIGN PROFESSIONALS:

OFFICE OF FACILITIES AND ENGINEERING

BUREAU OF DESIGN AND PROJECT MANAGEMENT

BUILDING 0-10, CHAPEL ROAD FORT INDIANTOWN GAP

ANNVILLE, LEBANON COUNTY, PENNSYLVANIA

COMMONWEALTH OF PENNSYLVANIA

DEPT. OF MILITARY & VETERANS' AFFAIRS

ANNVILLE, PENNSYLVANIA 17003

PROJECT NO. 42110341

VESLE RUN

STREAM CROSSING

FORT INDIANTOWN GAP

LEBANON COUNTY, PENNSYLVANIA

STREAM CROSSING DETAIL

7/2/24

AS NOTED

C.1.0

CONTRACTOR SHALL FIELD VERIFY

ALL DIMENSIONS.

VARIANCE FROM CONTRACT

DOCUMENTS NOT PERMITTED

WITHOUT BUREAU OF ENGINEERING

AND ARCHITECTURE APPROVAL.

VERIFY SCALE

IF BAR IS NOT ONE (1) INCH LONG,

ADJUST SCALE ACCORDINGLY

BAR IS ONE (1) INCH LONG

ON ORIGINAL DRAWING:

0 1

STANDARD CONSTRUCTION DETAIL #13-2

TYPICAL UTILITY LINE STREAM CROSSING

WITH PUMP BYPASS

STANDARD CONSTRUCTION DETAIL #3-16

PUMPED WATER FILTER BAG

STANDARD CONSTRUCTION DETAIL #3-15

SANDBAG DIVERSION DAM OR COFFERDAM

STANDARD CONSTRUCTION DETAIL #4-1

COMPOST FILTER SOCK

THE AREA OF DISTURBANCE = 7,202 SF, 0.1653 AC

ALL DISTURBED AREAS ARE TO BE COVERED WITH

EROSION MATTING S75BN.

NOT TO SCALE

EROSION BLANKET DETAIL

AutoCAD SHX Text

CLAY PLUG TYP.

AutoCAD SHX Text

SANDBAG DAM

AutoCAD SHX Text

ENERGY DISSPATOR

AutoCAD SHX Text

SANDBAG DAM

AutoCAD SHX Text

PUMP

AutoCAD SHX Text

INTAKE

AutoCAD SHX Text

DISCHARGE

AutoCAD SHX Text

VESLE RUN

AutoCAD SHX Text

FLOW

AutoCAD SHX Text

FLOW

AutoCAD SHX Text

FLOW

AutoCAD SHX Text

%%UVESLE RUN STREAM CROSSING

AutoCAD SHX Text

SCALE: HORIZ.: 1" = 10'

AutoCAD SHX Text

VERT.: 1" = 5'

AutoCAD SHX Text EX. Stream Bed

AutoCAD SHX Text

PROP. WATERLINE

AutoCAD SHX Text 10"D.I.P.

AutoCAD SHX Text

MIN 3'

AutoCAD SHX Text

NOT TO SCALE

AutoCAD SHX Text NOTES: GRUBBING SHALL NOT TAKE PLACE WITHIN 50 FEET OF TOP-OF-BANK UNTIL ALL MATERIALS REQUIRED TO COMPLETE CROSSING ARE ON SITE AND PIPE IS READY FOR INSTALLATION. BYPASS PUMP INTAKE SHALL BE MAINTAINED A SUFFICIENT DISTANCE FROM THE BOTTOM TO PREVENT PUMPING OF CHANNEL BOTTOM MATERIALS. TRENCH PLUGS SHALL BE INSTALLED WITHIN THE TRENCH ON BOTH SIDES OF THE STREAM CHANNEL (STANDARD CONSTRUCTION DETAIL #13-4). WATER ACCUMULATING WITHIN THE WORK AREA SHALL BE PUMPED TO A PUMPED WATER FILTER BAG OR SEDIMENT TRAP PRIOR TO DISCHARGING INTO ANY SURFACE WATER. HAZARDOUS OR POLLUTANT MATERIAL STORAGE AREAS SHALL BE LOCATED AT LEAST 100 FEET BACK FROM THE TOP OF STREAMBANK. ALL EXCESS EXCAVATED MATERIAL SHALL BE IMMEDIATELY REMOVED FROM THE STREAM CROSSING AREA. ALL DISTURBED AREAS WITHIN 50 FEET OF TOP-OF-BANK SHALL BE BLANKETED OR MATTED WITHIN 24 HOURS OF INITIAL DISTURBANCE FOR MINOR STREAMS OR 48 HOURS OF INITIAL DISTURBANCE FOR MAJOR STREAMS UNLESS OTHERWISE AUTHORIZED. APPROPRIATE STREAMBANK PROTECTION SHALL BE PROVIDED WITHIN THE CHANNEL.

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text

TRENCH

AutoCAD SHX Text

SPOIL

AutoCAD SHX Text

TRENCH

AutoCAD SHX Text

SPOIL

AutoCAD SHX Text

STREAM TOP OF BANK

AutoCAD SHX Text

STREAM TOP OF BANK

AutoCAD SHX Text

SEDIMENT BARRIER (TYP.)

AutoCAD SHX Text

TRENCH PLUGS

AutoCAD SHX Text

FLOW

AutoCAD SHX Text

TRENCH

AutoCAD SHX Text 1 inch = ft.

AutoCAD SHX Text

( IN FEET )

AutoCAD SHX Text

GRAPHIC SCALE

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

FILTER BAG

AutoCAD SHX Text

WELL VEGETATED, GRASSY AREA

AutoCAD SHX Text

WELL VEGETATED, GRASSY AREA

AutoCAD SHX Text

FILTER BAG

AutoCAD SHX Text

INTAKE HOSE

AutoCAD SHX Text

PUMP

AutoCAD SHX Text

DISCHARGE HOSE

AutoCAD SHX Text

CLAMPS

AutoCAD SHX Text

CLAMPS

AutoCAD SHX Text

DISCHARGE HOSE

AutoCAD SHX Text

PUMP

AutoCAD SHX Text

INTAKE HOSE

AutoCAD SHX Text

HEAVY DUTY LIFTING STRAPS (RECOMMENDED)

AutoCAD SHX Text

PLAN VIEW

AutoCAD SHX Text

ELEVATION VIEW

AutoCAD SHX Text NOTES: LOW VOLUME FILTER BAGS SHALL BE MADE FROM NON-WOVEN GEOTEXTILE MATERIAL SEWN WITH HIGH STRENGTH, DOUBLE STITCHED "J" TYPE SEAMS. THEY SHALL BE CAPABLE OF TRAPPING PARTICLES LARGER THAN 150 MICRONS. HIGH VOLUME FILTER BAGS SHALL BE MADE FROM WOVEN GEOTEXTILES THAT MEET THE FOLLOWING STANDARDS:

AutoCAD SHX Text A SUITABLE MEANS OF ACCESSING THE BAG WITH MACHINERY REQUIRED FOR DISPOSAL PURPOSES SHALL BE PROVIDED. FILTER BAGS SHALL BE REPLACED WHEN THEY BECOME 1/2 FULL OF SEDIMENT. SPARE BAGS SHALL BE KEPT AVAILABLE FOR REPLACEMENT OF THOSE THAT HAVE FAILED OR ARE FILLED. BAGS SHALL BE PLACED ON STRAPS TO FACILITATE REMOVAL UNLESS BAGS COME WITH LIFTING STRAPS ALREADY ATTACHED. BAGS SHALL BE LOCATED IN WELL-VEGETATED (GRASSY) AREA, AND DISCHARGE ONTO STABLE, EROSION RESISTANT AREAS. WHERE THIS IS NOT POSSIBLE, A GEOTEXTILE UNDERLAYMENT AND FLOW PATH SHALL BE PROVIDED. BAGS MAY BE PLACED ON FILTER STONE TO INCREASE DISCHARGE CAPACITY. BAGS SHALL NOT BE PLACED ON SLOPES GREATER THAN 5%. FOR SLOPES EXCEEDING 5%, CLEAN ROCK OR OTHER NON-ERODIBLE AND NON-POLLUTING MATERIAL MAY BE PLACED UNDER THE BAG TO REDUCE SLOPE STEEPNESS. NO DOWNSLOPE SEDIMENT BARRIER IS REQUIRED FOR MOST INSTALLATIONS. COMPOST BERM OR COMPOST FILTER SOCK SHALL BE INSTALLED BELOW BAGS LOCATED IN HQ OR EV WATERSHEDS, WITHIN 50 FEET OF ANY RECEIVING SURFACE WATER OR WHERE GRASSY AREA IS NOT AVAILABLE. THE PUMP DISCHARGE HOSE SHALL BE INSERTED INTO THE BAGS IN THE MANNER SPECIFIED BY THE MANUFACTURER AND SECURELY CLAMPED. A PIECE OF PVC PIPE IS RECOMMENDED FOR THIS PURPOSE. THE PUMPING RATE SHALL BE NO GREATER THAN 750 GPM OR 1/2 THE MAXIMUM SPECIFIED BY THE MANUFACTURER, WHICHEVER IS LESS. PUMP INTAKES SHALL BE FLOATING AND SCREENED. FILTER BAGS SHALL BE INSPECTED DAILY. IF ANY PROBLEM IS DETECTED, PUMPING SHALL CEASE IMMEDIATELY AND NOT RESUME UNTIL THE PROBLEM IS CORRECTED.

AutoCAD SHX Text

PROPERTY

AutoCAD SHX Text

TEST METHOD

AutoCAD SHX Text

MINIMUM STANDARD

AutoCAD SHX Text

AVG. WIDE WIDTH STRENGTH

AutoCAD SHX Text

ASTM D-4884

AutoCAD SHX Text

60 LB/IN

AutoCAD SHX Text

GRAB TENSILE

AutoCAD SHX Text

ASTM D-4632

AutoCAD SHX Text

205 LB

AutoCAD SHX Text

PUNCTURE

AutoCAD SHX Text

ASTM D-4833

AutoCAD SHX Text

110 LB

AutoCAD SHX Text

MULLEN BURST

AutoCAD SHX Text

ASTM D-3786

AutoCAD SHX Text

350 PSI

AutoCAD SHX Text

UV RESISTANCE

AutoCAD SHX Text

ASTM D-4355

AutoCAD SHX Text 70%

AutoCAD SHX Text

AOS % RETAINED

AutoCAD SHX Text

ASTM D-4751

AutoCAD SHX Text

80 SIEVE

AutoCAD SHX Text 18" DIA. FILTER SOCK SURROUNDING THE BAG. NO LESS THAN 4' BETWEEN THE BAG AND SOCK

AutoCAD SHX Text 4'

AutoCAD SHX Text

NOT TO SCALE

AutoCAD SHX Text

NOT TO SCALE

AutoCAD SHX Text

SANDBAGS

AutoCAD SHX Text

IMPERVIOUS MEMBRANE

AutoCAD SHX Text

2 BAG MIN. HEIGHT ABOVE NORMAL BASE FLOW

AutoCAD SHX Text

WORK AREA

AutoCAD SHX Text

SANDBAG TO HOLD IMPERVIOUS LINER IN PLACE

AutoCAD SHX Text

IMPERVIOUS LINER EXTENDED TO STREAM BOTTOM AND SECURED WITH SANDBAGS

AutoCAD SHX Text

OPTIONAL SANDBAG PLATFORM

AutoCAD SHX Text

SANDBAG (TYP.)

AutoCAD SHX Text

JERSEY BARRIER

AutoCAD SHX Text

NORMAL STREAM FLOW

AutoCAD SHX Text

STACKED SANDBAGS OPTION

AutoCAD SHX Text

JERSEY BARRIER OPTION

AutoCAD SHX Text

SANDBAG DAM

AutoCAD SHX Text

ENERGY DISSPATOR

AutoCAD SHX Text

SANDBAG DAM

AutoCAD SHX Text

PUMP

AutoCAD SHX Text

INTAKE

AutoCAD SHX Text

DISCHARGE

AutoCAD SHX Text

NOT TO SCALE

AutoCAD SHX Text

FLOW

AutoCAD SHX Text

FLOW

AutoCAD SHX Text

DISTURBED AREA

AutoCAD SHX Text

UNDISTURBED AREA

AutoCAD SHX Text

%%USECTION

AutoCAD SHX Text

%%UPLAN VIEW

AutoCAD SHX Text

EXISTING CONTOURS

AutoCAD SHX Text

COMPOST FILTER SOCK

AutoCAD SHX Text 2 IN. x 2 IN. WOODEN STAKES PLACED 10 FT ON CENTER

AutoCAD SHX Text 2 IN. x 2 IN. WOODEN STAKES PLACED 10 FT ON CENTER

AutoCAD SHX Text

COMPOST FILTER SOCK

AutoCAD SHX Text

BLOWN/PLACED FILTER MEDIA

AutoCAD SHX Text

DISTURBED AREA

AutoCAD SHX Text

UNDISTURBED AREA

AutoCAD SHX Text NOTES: SOCK FABRIC SHALL MEET STANDARDS OF TABLE 4.1 OF THE PA DEP EROSION CONTROL MANUAL. COMPOST SHALL MEET THE STANDARDS OF TABLE 4.2 OF THE PA DEP EROSION CONTROL MANUAL. COMPOST FILTER SOCK SHALL BE PLACED AT EXISTING LEVEL GRADE. BOTH ENDS OF THE BARRIER SHALL BE EXTENDED AT LEAST 8 FEET UP SLOPE AT 45 DEGREES TO THE MAIN BARRIER ALIGNMENT. MAXIMUM SLOPE LENGTH ABOVE ANY BARRIER SHALL NOT EXCEED THAT SPECIFIED FOR THE SIZE OF THE SOCK AND THE SLOPE OF ITS TRIBUTARY AREA. TRAFFIC SHALL NOT BE PERMITTED TO CROSS COMPOST FILTER SOCKS. ACCUMULATED SEDIMENT SHALL BE REMOVED WHEN IT REACHES 1/2 THE ABOVE GROUND HEIGHT OF THE BARRIER AND DISPOSED IN THE MANNER DESCRIBED ELSEWHERE IN THE PLAN. COMPOST FILTER SOCKS SHALL BE INSPECTED WEEKLY AND AFTER EACH RUNOFF EVENT. DAMAGED SOCKS SHALL BE REPAIRED ACCORDING TO MANUFACTURER’S SPECIFICATIONS OR REPLACED WITHIN 24 HOURS OF S SPECIFICATIONS OR REPLACED WITHIN 24 HOURS OF INSPECTION. BIODEGRADABLE COMPOST FILTER SOCKS SHALL BE REPLACED AFTER 6 MONTHS; PHOTODEGRADABLE SOCKS AFTER 1 YEAR. POLYPROPYLENE SOCKS SHALL BE REPLACED ACCORDING TO MANUFACTURER’S S RECOMMENDATIONS. UPON STABILIZATION OF THE AREA TRIBUTARY TO THE SOCK, STAKES SHALL BE REMOVED. THE SOCK MAY BE LEFT IN PLACE AND VEGETATED OR REMOVED. IN THE LATTER CASE, THE MESH SHALL BE CUT OPEN AND THE MULCH SPREAD AS A SOIL SUPPLEMENT.

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text NOTES: SEED AND SOIL AMENDMENTS SHALL BE APPLIED ACCORDING TO THE RATES IN THE PLAN DRAWINGS PRIOR TO INSTALLING THE BLANKET. PROVIDE ANCHOR TRENCH AT TOE OF SLOPE IN SIMILAR FASHION AS AT TOP OF SLOPE. SLOPE SURFACE SHALL BE FREE OF ROCKS, CLODS, STICKS, AND GRASS. BLANKET SHALL HAVE GOOD CONTINUOUS CONTACT WITH UNDERLYING SOIL THROUGHOUT ENTIRE LENGTH. LAY BLANKET LOOSELY AND STAKE OR STAPLE TO MAINTAIN DIRECT CONTACT WITH SOIL. DO NOT STRETCH BLANKET. THE BLANKET SHALL BE STAPLED IN ACCORDANCE WITH THE MANUFACTURER'S RECOMMENDATIONS. BLANKETED AREAS SHALL BE INSPECTED WEEKLY AND AFTER EACH RUNOFF EVENT UNTIL PERENNIAL VEGETATION IS ESTABLISHED TO A MINIMUM UNIFORM 70% COVERAGE THROUGHOUT THE BLANKETED AREA. DAMAGED OR DISPLACED BLANKETS SHALL BE RESTORED OR REPLACED WITHIN 4 CALENDAR DAYS.

AutoCAD SHX Text

BLANKET EDGES STAPLED AND OVERLAPPED (4 IN. MIN.)

AutoCAD SHX Text INSTALL BEGINNING OF ROLL IN 6 IN. x 6 IN. ANCHOR TRENCH, STAPLE, BACKFILL AND COMPACT SOIL

AutoCAD SHX Text

STARTING AT TOP OF SLOPE, ROLL BLANKETS IN DIRECTION OF WATER FLOW

AutoCAD SHX Text PREPARE SEED BED (INCLUDING APPLICATION OF LIME, FERTILIZER AND SEED) PRIOR TO BLANKET INSTALLATION

AutoCAD SHX Text REFER TO MANUF. RECOMMENDED STAPLING PATTERN FOR STEEPNESS AND LENGTH OF SLOPE BEING BLANKETED

AutoCAD SHX Text

THE BLANKET SHOULD NOT BE STRETCHED; IT MUST MAINTAIN GOOD SOIL CONTACT

AutoCAD SHX Text OVERLAP BLANKET ENDS 6 IN. MIN. WITH THE UPSLOPE BLANKED OVERLYING THE DOWNSLOPE BLANKET (SHINGLE STYLE). STAPLE SECURELY.