Sheet1

Submittal 1

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT NAMESOLICITATION /CONTRACT NUMBER
GLEN 12-1036Repair Sanitary Sewer Industrial Area
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERCERTIFICATE OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTTEST RESULTSREQUIRED SUBMISSION DATEDATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVALREMARKS
GENERAL
1Project Specific MSDS SheetsXNTP + 7If required
2Form-3064 Contract Progress ScheduleXNTP + 22Revised weekly if deviation > 3 days
3Form-3065 Contract Progress ReportXAs RequiredAs Required
4Stormwater Pollution Prevention Plan1NTP + 14Including erosion control measures
5Monthly Solid Waste ReportingXMonthly
6Fire Hydrant Connection RequestX10 Days Prior
7Current Backflow Preventer CertificationXX10 Days Prior
8Health, Safety, and Environment Plan(s)1NTP + 14
9Contractor's QA/QC Plan1NTP + 14
10Weekly Look-Ahead SchedulesXWeeklyClearly detailing planned actions
11Requested Outages and ClosuresXNTP + 21
12Form 103 BCE Work Clearance Request1NTP + 1Coordinated by contractor
13Camera Letter and Security/Access RequestsXNTP + 1
14Meeting MinutesXFollowing DayKick-Off and all construction meetings
15Traffic Control Plan(s)11NTP + 34
CIVIL
16Select Fill Sieve and Chemical Analysis1NTP + 14
17Grinder Pump and Controls1111NTP + 14
18Soil Compaction Test ResultsXXNTP + 14
19Pressure and Gravity Flow Pipe11NTP + 14
20Valve and Check Valve11
21Concrete Mix Design1NTP + 14per ACI 318
22Cement Chemical Analysis1NTP + 14
23Concrete Aggregate Chemical Analysis1NTP + 14
24Concrete Aggregate Sieve Analysis1NTP + 14
25Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion Joints1NTP + 14
26Concrete Crack Control Joint Layout1NTP + 14Clearly dimensioned drawing
27Slump Test results & Concrete Truck Tickets (per truck)XXFollowing Day
287-Day Concrete Compressive Strength TestXXTest + 3
2928-Day Concrete Compressive Strength TestXXTest + 3
CLOSEOUT
29O&M Maintainance data, manuals and Manufacturer's Warranties1NTP + 90
30Draft DD 13541NTP + 90Accurate and complete
31As Built Drawings Submittal1NTP + 90On disc, per current AEC standard

&L&9Project Submittal Form AF-66