GeotechnicalReport.pdf
PDF 5 MB Posted
- Attached to
- Animal Shelter Renovation and Addition
- Solicitation number
- 2026-ITB-359
- Issued by
- New Haven County, Connecticut
About this file
This is a Geotechnical Engineering Report prepared by Down To Earth Consulting, LLC for the City of New Haven, Connecticut, documenting subsurface conditions and foundation recommendations for proposed building additions at 81 Fournier Street. The report is based on two test borings (B-1 and B-2) drilled on May 26, 2023, which characterized soil conditions to depths of 17 to 22 feet below grade. The proposed additions comprise approximately 450 to 1,655 square feet of single-story structures with slab-on-grade construction, including associated parking areas, sidewalks, drainage structures, utilities, and landscape improvements. The site subsurface profile consists of uncontrolled fill (5 to 7 feet thick) overlying natural sand deposits, with groundwater encountered at approximately 7 to 10 feet below grade.
The report recommends supporting the building additions on conventional, shallow spread footings bearing on undisturbed natural sand deposits or compacted granular fill, with exterior footings at minimum 42 inches below proposed grade and interior footings at 18 inches below slab level. A maximum allowable bearing pressure of four kips per square foot is specified, with anticipated settlements less than one inch total and less than one-half inch differential settlement. Slab-on-grade construction requires a six-inch crushed stone base course with damp-proofing but no sub-slab drains, as groundwater is expected to remain below slab elevation. The report provides detailed material specifications for compacted granular fill, sand and gravel backfill, crushed stone, and geotextile fabric, along with compaction requirements ranging from 90 to 95 percent of maximum dry density depending on placement location. Field observations by the geotechnical engineer are recommended during excavation, footing preparation, and fill placement to ensure compliance with specifications and to address variations in actual subsurface conditions encountered during construction.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2 7 S i e m o n C o m p a n y D r i v e - S u i t e N o . 3 6 3 W e s t W a t e r t o w n , C o n n e c t i c u t 0 6 7 9 5
( 2 0 3 ) 6 8 3 - 4 1 5 5
GEOTECHNICAL ENGINEERING REPORT
PROPOSED BUILDING ADDITIONS
81 FOURNIER STREET
NEW HAVEN, CONNECTICUT
Prepared for:
City of New Haven 200 Orange Street, 5th Floor
New Haven, Connecticut 06510
Prepared by:
Down To Earth Consulting, LLC 27 Siemon Company Drive - Suite No. 363 West
Watertown, Connecticut 06795
File No. 0063-022.00
June 2023
June 9, 2023 File No. 0063-022.00
Zach Shapiro, P.E.
City of New Haven 200 Orange Street 5th Floor New Haven, Connecticut 06510
Via email: ZShapiro@newhavenct.gov
Re: Geotechnical Engineering Report 81 Fournier Street Building Additions
New Haven, Connecticut
Dear Mr. Shapiro:
Down To Earth Consulting, LLC (DTE) is pleased to submit this geotechnical engineering report for the proposed building additions that will be located at 81 Fournier Street in New Haven, Connecticut. We appreciate this opportunity to work with you. Please call if you have any questions.
Sincerely, Down To Earth Consulting, LLC
Daniel F. LaMesa, P.E.
Principal
81 Fournier Street Building Additions New Haven, Connecticut
File No. 0063-022.00 – June 12, 2023 Page No. i
TABLE OF CONTENTS
1.0 INTRODUCTION
2.0 TEST BORINGS
3.0 SUBSURFACE CONDITIONS
3.1 SUBSURFACE PROFILE
3.1.1 Fill
3.1.2 Natural Sand Deposits
3.2 GROUNDWATER
4.0 GEOTECHNICAL RECOMMENDATIONS
4.1 FOUNDATIONS
4.1.1 Foundation Type and Bearing Strata
4.1.2 Footing Levels and Sizes
4.1.3 Allowable Bearing Pressures and Settlement Estimates
4.2 SLAB-ON-GRADE
4.2.1 Subgrade
4.2.2 Drainage and Damp-Proofing
4.3 RETAINING WALLS
4.4 SEISMIC DESIGN
5.0 MATERIALS RECOMMENDATIONS
5.1 ON-SITE MATERIALS
5.2 COMPACTED GRANULAR FILL
5.3 SAND AND GRAVEL
5.4 CRUSHED STONE
5.5 PROCESSED AGGREGATE
5.6 GEOTEXTILE FABRIC
5.7 PLACEMENT AND COMPACTION REQUIREMENTS
6.0 CONSTRUCTION RECOMMENDATIONS
6.1 FOOTING PREPARATION
6.2 TEMPORARY EXCAVATIONS
6.3 TEMPORARY GROUNDWATER CONTROL
7.0 REVIEW OF FINAL DESIGN, PLANS, AND SPECIFICATIONS
8.0 CONSTRUCTION QUALITY CONTROL
9.0 LIMITATIONS
APPENDICES
APPENDIX 1 – FIGURES
APPENDIX 2 – BORING LOGS
APPENDIX 3 – LIMITATIONS
Page No. 1
1.0 INTRODUCTION
This report provides geotechnical design and construction recommendations for the proposed building additions that will be located at 81 Fournier Street in New Haven, Connecticut. Refer to Figures 1 and 2 (in Appendix 1) for the approximate site and proposed addition locations, respectively.
We understand two single-story additions will be constructed off the western and eastern ends of the existing animal shelter building. The proposed structures will be about 450 to 1,655 square feet with slabs-on-grade (i.e., no basement) that generally matches the first-floor level of the existing building. Foundation and slab loads were not available at the time this report was prepared. Associated parking areas, sidewalks, drainage structures, utilities, and landscape areas will also be constructed.
Our geotechnical engineering services included: reviewing project plans, drilling test borings, characterizing subsurface conditions within the project limits, performing geotechnical engineering analyses, and providing geotechnical design and construction recommendations for the proposed additions. Our services were performed in accordance with our May 16, 2023 proposal.
Our recommendations are based on allowable stress design methods and the 2021 International Building Code with 2022 Connecticut Supplements (Building Code).
2.0 TEST BORINGS
We observed and logged two test borings (B-1 and B-2) drilled by our subcontractor Associated Borings Co., Inc. on May 26, 2023. Boring locations are depicted on Figure 2 (Appendix 1) and the logs are included in Appendix 2. Borings were located in the field by taping/pacing from existing site features and should be considered approximate.
The borings were drilled to explore the soil and groundwater conditions in the project area. Hollow-stem auger drilling methods were used to advance borings to depths of approximately 17 to 22 feet below existing grades. All borings were terminated in natural soil.
Representative soil samples were obtained for soil classification by split barrel sampling procedures in general accordance with ASTM D-1586. The split-spoon sampling procedure utilizes a standard 2-inch O.D. split-barrel sampler that is driven into the bottom of the boring with a 140-pound hammer falling a distance of 30 inches. The number of blows required to advance the sampler the middle 12-inches of a normal 24-inch penetration is recorded as the Standard Penetration Resistance Value (N). The blows (i.e., “N-Value”) are indicated on the boring logs at their depth of occurrence and provide an indication of the relative consistency of the material.
Groundwater levels were measured using a weighted tape in open drill holes or inferred from wet soil samples during drilling.
Page No. 2
3.0 SUBSURFACE CONDITIONS
3.1 SUBSURFACE PROFILE
The generalized subsurface profile, as inferred from the subsurface data, consists of Fill over Natural Sand Deposits. The following is a more detailed description of the major subsurface materials encountered at the site:
3.1.1 Fill
Uncontrolled Fill was encountered at each boring location. This stratum extended down about 5 to 7 feet below existing site grades and typically consisted of loose, gray/brown, fine to coarse sand with varying amounts (0 to 20%) of silt and trace (0 to 10%) gravel.
The thickness, character, and consistency of the Fill will vary between boring locations. Samples obtained from this stratum generally did not have foreign (e.g. asphalt, concrete, etc.) or deleterious (e.g. organics) materials and in some areas appeared to be reworked native soil.
3.1.2 Natural Sand Deposits
Natural Sand Deposits were encountered below the uncontrolled Fill. This material generally consisted of loose to medium dense, gray/reddish brown, fine to coarse sand with trace amounts of silt.
3.2 GROUNDWATER
Groundwater was encountered at about 7 to 10 feet below grade during drilling. Groundwater levels measured in the boreholes may not have had sufficient time to stabilize and should be considered approximate. Groundwater levels will vary depending on factors such as temperature, season, precipitation, construction activity, and other conditions, which may be different from those at the time of these measurements.
4.0 GEOTECHNICAL RECOMMENDATIONS
We offer the following geotechnical design recommendations based on the subsurface conditions encountered at the site, available project information, and proposed construction.
4.1 FOUNDATIONS
4.1.1 Foundation Type and Bearing Strata
We recommend supporting the proposed building additions on conventional, shallow spread footings. The footings should bear on undisturbed Natural Sand Deposits, or on Structural Fill (hereinafter specified as Compacted Granular Fill, CGF) over Natural Sand. Actual bottom of unsuitable bearing material elevations will vary across the site and should be verified during construction excavation by a DTE representative.
Page No. 3
When CGF is used beneath the footings (e.g., in fill areas), we recommend that it be placed one foot beyond the edge of the footings and at a one horizontal to one vertical slope away and down from the bottom outside edge of the footings. Crushed Stone can be used in place of CGF as it is much easier to compact.
4.1.2 Footing Levels and Sizes
Exterior footings (and footings in unheated areas) should be constructed at a minimum frost depth of 42-inches below proposed site grades. Interior footings, in heated areas, should be constructed at a minimum depth of 18-inches below proposed top of slab-on-grade level.
The minimum footing width should be 2 feet.
4.1.3 Allowable Bearing Pressures and Settlement Estimates
We recommend a maximum allowable design bearing pressure of four kips per square foot (ksf) for footings bearing on the recommended bearing materials. Based on the recommended bearing strata and anticipated loads, we anticipate that footings will undergo less than one inch of total settlement and less than a half inch of differential settlement. Settlements will occur as the loads are applied and are expected to be complete at the end of construction.
DTE should be provided the final foundation loads and geometries once they are available to confirm the above recommended bearing capacity and settlement estimates.
4.2 SLAB-ON-GRADE
4.2.1 Subgrade
We recommend placing the at-grade slab over a minimum six-inch-thick base course layer of compacted Crushed Stone placed over the surface of natural Sand and/or the existing Fill that has been improved with surface densification under the observation of a qualified Geotechnical Engineer. This procedure consists of removing all surficial organic and debris materials and compacting the surface with a minimum of four passes with a 20-ton vibratory drum roller having a minimum dynamic force of 6,000 lbs. per foot of drum width. Areas exhibiting instability shall receive additional compaction and/or be over-excavated and replaced with Compacted Granular Fill (CGF), as recommended by the Geotechnical Engineer. Modifications to this procedure may be required if the subgrade is saturated or groundwater table is too high.
The subgrade modulus for the recommended subgrades and base course is 250 pounds per cubic inch.
4.2.2 Drainage and Damp-Proofing
Groundwater appears to be below the proposed slab level, thus, sub-slab drains are not required.
Damp-proofing of the slabs is recommended. Slab damp-proofing must be installed between the slab and base course, and consist of not less than 6-mil polyethylene with joints lapped at least 6-inches.
Page No. 4
4.3 RETAINING WALLS
We recommend backfilling earth retaining structures with compacted Sand and Gravel and installing footing drains. Walls that are free to rotate at the top and are not braced should be designed to resist an equivalent active static horizontal fluid earth pressure equal to 35 pcf (based on φ’ = 34°, c = 0, Ka = 0.28, and ɣ = 125 pcf). Braced retaining walls should be designed to resist an equivalent at-rest static horizontal fluid earth pressure equal to 55 pcf (based on φ’ = 34°, c = 0, Ko = 0.44, and ɣ = 125 pcf). This assumes level backfill soils and no unbalanced hydrostatic pressures, seismic forces, or surcharge loads (e.g., vehicles).
Due to the limited expected wall movement and depth of footings, we do not recommend the use of passive earth pressures against the base of walls. We recommend a maximum coefficient of friction of 0.45 between foundations and the recommending bearing strata.
4.4 SEISMIC DESIGN
The site class is “D” per the Building Code. Based on the standard penetration test results, visual soil classification, and design peak ground acceleration at this locale, the site soils are not susceptible to liquefaction.
5.0 MATERIALS RECOMMENDATIONS
5.1 ON-SITE MATERIALS
Based on our visual soil classifications, some site soils may be reusable as Compacted Granular Fill (CGF) if they meet the requirements in Section 5.2. Site soils can be reused as General Fill outside the building and deeper than 12-inches below pavement if the material does not contain organics or significant amounts (less than 2%) of debris materials. The elevated fines (i.e., soil particles passing the No. 200 sieve) content of some site soils could make them difficult to place and compact. Success in using these materials will depend on their moisture content and prevailing weather conditions when they are excavated, placed, and compacted.
Topsoil and soil with organics should only be reused in landscaped areas for planting grass and other vegetation.
5.2 COMPACTED GRANULAR FILL
Compacted Granular Fill (CGF) for use as structural fill below footings and other structures shall consist of inorganic soil free of clay, loam, ice and snow, tree stumps, roots, and other organic matter; graded within the following limits:
Sieve Size Percent finer by weight
4-inches 100%
No. 10 30 - 100
No. 40 10 - 90
No. 200 0 - 12
Page No. 5
5.3 SAND AND GRAVEL
Sand and Gravel for use as retaining wall backfill and below slabs shall consist of hard, durable sand and gravel; free of ice, clay, shale, roots, sod, rubbish, and other organic matter; graded within the following limits:
2-inches 100%
1/2-inch 50 - 85
No. 4 40 - 75
No. 40 10 - 35
No. 200 0 - 5
5.4 CRUSHED STONE
Crushed Stone for use around drains or below foundations and slabs shall consist of sound, tough, durable, rock that is graded within the following:
5/8-inches 100%
1/2-inch 85 - 100
3/8 inch 15 - 45
No. 4 0 - 15
No. 8 0 - 5
5.5 PROCESSED AGGREGATE
Processed Aggregate Base for use as pavement base shall consist of inorganic soil free of clay, loam, ice and snow, tree stumps, roots, and other organic matter; graded within the following limits:
Sieve Size Percent finer by weight
2 1/2-inches 100%
2-inch 95 - 100
3/4-inch 50 - 75
1/4-inch 25 - 45
No. 40 5 - 20
No. 100 2 - 12
5.6 GEOTEXTILE FABRIC
Geotextile fabric placed around crushed stone pipe bedding or used as a separation fabric for crushed stone and soil material should meet the following criteria:
Page No. 6
Property Criteria Test Method Grab Strength min. 80lbs ASTM D4632 Static (CBR) Puncture min. 50lbs ASTM D6241 Trapezoid Tear min. 25lbs ASTM D4533 Apparent Opening Size No. 70-100 U.S. Sieve Size ASTM D4751
Fabric should be needle-punched non-woven material. Seams should be overlapped a minimum of six inches. During stone placement, the stone drop height should not exceed three feet and equipment traffic should be kept off the fabric until at least 6 to 12 inches of material is placed.
5.7 PLACEMENT AND COMPACTION REQUIREMENTS
The required degree of compaction shall be based on a maximum dry density as determined by a Modified Proctor (ASTM D1557). The degree of compaction for fill placed in various areas shall be as follows:
Placement areas Minimum degree of compaction
1. Below foundations (footings) 95%
2. Below slabs and Pavement 92%
3. Against foundation and retaining walls 92%
4. Landscaped areas 90%
Crushed stone is considered to be self-compacting, and would negate the need to run laboratory proctor testing and have field density testing of in-place lifts. The crushed stone should be plate compacted to “chink up” the working surface in lifts. We recommend placing Crushed Stone in maximum 12-inch lifts and compacting the lifts with a minimum of four passes with a vibratory plate compactor weight of a minimum of 1,000 pounds and with a minimum centrifugal force of 10,000 pounds. Recommended loose lift thickness for granular fill and the minimum number of passes of compaction equipment are summarized on the table below.
Extra care should be used when compacting adjacent to walls. Hand-operated rollers or plate compactors weighing not more than 250 pounds should be used within a lateral distance of 5 feet of walls. Where walls are buried on both sides, backfill and compaction should proceed on both sides of the wall so that the difference in top of fill on either side of the wall does not exceed 2 feet.
Page No. 7
Maximum
Loose Lift Thickness Minimum
Number of Passes
Compaction
Method
Maximum Stone Size
Below Structures
Less Critical Areas
Below Structures
Less Critical Areas
Hand-operated vibratory plate or light roller in confined areas 4” 6” 8” 6 4
Hand-operated vibratory drum rollers weighing at least 1,000# 6” 8” 10” 6 4
Light vibratory drum roller, minimum dynamic force
3,000# per ft. of drum width 6” 10” 14” 6 4
Medium vibratory drum roller, minimum dynamic force 5,000# per ft. of drum width
8” 12” 18” 6 4
Large vibratory drum roller, minimum dynamic force
8,000# per ft. of drum width 10” 16” 24” 6 4
6.0 CONSTRUCTION RECOMMENDATIONS
6.1 FOOTING PREPARATION
The existing Fill and buried structures (e.g. utilities) are not suitable for support of conventional, shallow foundations and must be excavated in its entirety from the proposed foundation areas.
Actual bottom of unsuitable bearing soil elevations will vary across the site and should be verified during construction excavation by a DTE representative.
We recommend the use of smooth edged excavator buckets or clips (not back-bladed) to make the final excavation to help protect the subgrade. The base of footing excavations should be free of debris materials, organics, water, ice, and loose and frozen soils prior to placing concrete.
Should the materials at bearing level become disturbed, the affected materials should be removed and/or repaired prior to placing concrete. Concrete should be placed as soon as possible after excavation so that excessive weathering of bearing materials does not occur. A four-inch-thick layer of compacted Crushed Stone can be used below foundations to protect footing subgrades during construction and facilitate dewatering (as needed).
6.2 TEMPORARY EXCAVATIONS
The Fill and natural site soils are classified as OSHA Class “C” soil and can be cut at a maximum one vertical to one and a half horizontal (1V:1.5H) slope up to a maximum excavation depth of 20 feet. These maximum slope and excavation depths assume no surcharge load (i.e., stockpiles, construction equipment, etc.) at the top of the excavations or groundwater seepage.
Page No. 8
If excavations cannot be sloped in accordance with OSHA requirements, a temporary excavation support system will be required. The system should be chosen and installed by the contactor and designed by a Professional Engineer registered in the Connecticut.
6.3 TEMPORARY GROUNDWATER CONTROL
We expect that temporary groundwater/storm water control can largely be accomplished by means of shallow trenches and sumps, and grading the excavation to low points. The construction dewatering system means and methods should be chosen by the contractor and designed by a Professional Engineer registered in the State of Connecticut. This should include providing a discharge water management plan that avoids endangering public health and nearby property and meets applicable local, state, and environmental regulations.
7.0 REVIEW OF FINAL DESIGN, PLANS, AND SPECIFICATIONS
When project plans and specifications are available they should be provided to DTE for review of conformance with our geotechnical recommendations. If any changes are made to the proposed building, the recommendations provided in this report will need to be verified by DTE for applicability.
8.0 CONSTRUCTION QUALITY CONTROL
We recommend that DTE make field observations of excavations and foundation preparation to monitor compliance with our recommendations and project specifications. Specifically, we recommend field observation of footing subgrades, removal of unsuitable materials, Fill placement and compaction, and existing Fill improvement (e.g., surface densification) to monitor compliance with project specifications.
9.0 LIMITATIONS
This report is subject to the limitations included in Appendix 3.
APPENDIX 1 -
FIGURES
SITE
AutoCAD SHX Text
AREA PLAN PROPOSED BUILDING ADDITIONS 81 FOURNIER STREET NEW HAVEN, CONNECTICUT
AutoCAD SHX Text
REVIEWED BY: DFL
AutoCAD SHX Text
DRAWN BY: MF
AutoCAD SHX Text 2,000'
AutoCAD SHX Text 2,000'
AutoCAD SHX Text 1,000'
AutoCAD SHX Text
AutoCAD SHX Text
SCALE 1"= 2,000'
AutoCAD SHX Text
DATE: 6/10/2023
AutoCAD SHX Text
FIGURE NO. 1
AutoCAD SHX Text
PROJECT NO. 0063-022.00
AutoCAD SHX Text
REFERENCE: USGS TOPOGRAPHIC QUADRANGLE: NEW HAVEN, CT
AutoCAD SHX Text
27 SIEMON COMPANY DRIVE, SUITE 363W
WATERTOWN, CONNECTICUT 06795
DESIGNED BY
AutoCAD SHX Text
CHECKED BY
AutoCAD SHX Text
APPROVED BY
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
NO.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text
DRWN.
AutoCAD SHX Text
APPVD
AutoCAD SHX Text
CHKD
AutoCAD SHX Text
PROPOSED BUILDING ADDITIONS 81 FOURNIER STREET NEW HAVEN, CONNECTICUT
AutoCAD SHX Text 6/12/2023
AutoCAD SHX Text
AutoCAD SHX Text
FILE NO.
AutoCAD SHX Text
AS NOTED
AutoCAD SHX Text
FIGURE NO.
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
DATE
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
OTHERS
AutoCAD SHX Text
MF
AutoCAD SHX Text
DFL
AutoCAD SHX Text
DFL
AutoCAD SHX Text
DWG. TITLE.
AutoCAD SHX Text
SITE AND EXPLORATION LOCATION PLAN
AutoCAD SHX Text 0063-022.00
AutoCAD SHX Text 20'
AutoCAD SHX Text 20'
AutoCAD SHX Text 10'
AutoCAD SHX Text
AutoCAD SHX Text
SCALE 1"= 20'
AutoCAD SHX Text
%%ULEGEND
AutoCAD SHX Text
TEST BORING NO. AND LOCATION
AutoCAD SHX Text B-1
AutoCAD SHX Text B-2
AutoCAD SHX Text NOTES: 1) BASE MAP DEVELOPED FROM AN ELECTRONIC FILE PROVIDED BY CITY OF NEW HAVEN ENTITLED 'ANIMAL SHELTER, 81 FROUNIER STREET, NEW HAVEN, CT 06511'. DATED APRIL 23, 2023, ORIGINAL SCALE 1/8"=1'-0". 2) BORINGS WERE COMPLETED BY ASSOCIATED BORING COMPANY AND OBSERVED BY DOWN TO EARTH CONSULTING, LLC. 3) THE LOCATIONS OF THE EXPLORATIONS WERE DETERMINED BY TAPING AND VISUAL ESTIMATES FROM EXISTING SITE FEATURES. THESE LOCATIONS SHOULD BE CONSIDERED ACCURATE ONLY TO THE DEGREE IMPLIED BY THE METHOD USED.
AutoCAD SHX Text B-1
AutoCAD SHX Text
27 SIEMON COMPANY DRIVE, SUITE 363W
WATERTOWN, CONNECTICUT 06795
APPENDIX 2 -
TEST BORING LOGS
PROJECT BORING NO.
SHEET 1 of 1
FILE NO.
CHKD. BY
Boring Co. Boring Location See Boring Location Plan Driller Ground Surface El. Datum Logged By Date Start Date End
Hammer Type: Groundwater Readings (from ground surface)
Sampler Size: Date Time Depth (ft) Elev. Stabilization Time
Type Drill Rig: 5/26/23 -
Drilling Method:
D
E
P Casing
T Blows REC/PEN DEPTH
H (ft) (inches) (feet)
2 1/23 1 to 3
4 6/24 3 to 5
6 9/24 5 to 7
8 12/24 7 to 9
11 10/24 10 to 12
16 11/24 15 to 17
21 24/24 20 to 22
1. S denotes split-barrel sampler. 7. WH denotes weight of hammer
2. ST denotes 3-inch O.D. undisturbed sample. 8. WR denotes weight of rods
3. UO denotes 3-inch Osterberg undisturbed sample. 9. PP denotes Pocket Penetrometer.
4. PEN denotes penetration length of sampler. 10. FVST denotes field vane shear test.
5. REC denotes recovered length of sample. 11. RQD denotes Rock Quality Designation.
6. SPT denotes Standard Penetration Test. 12. C denotes core run number.
SAND
B-1
PROPOSED BUILDING ADDITIONS
81 FOURNIER STREET 0063-022.00
NEW HAVEN, CONNECTICUT DFL
Donut hammer driven by cathead with 30 inch drop
1-3/8" I.D. Split Spoon
Truck Mounted CME 55 7 - After 15 min.
Associated Borings Company Jaime Lloret Not Available Not Available
Mateusz Fekieta 5/26/2023 5/26/2023
3.25-inch I.D. Hollow-Stem Augers
SAMPLE INFORMATION SAMPLE DESCRIPTION STRATA
Type BLOWS PER
FILL
S-1 2-3-3-2
Core Time
& No. 6 INCHES (min./ft)
Loose, dark brown, fine to medium SAND, some Silt, trace fine Gravel
6-9-9-8 Medium dense, grayish brown, fine to medium SAND, trace Silt
S-2 2-5-5-7 Loose, dark brown, fine to medium SAND, little Silt, trace fine Gravel
S-3
S-4 5-6-6-7 Medium dense, grayish brown to red-brown, fine to coarse SAND, trace Silt
S-5 4-5-4-4
S-6 2-2-4-4
2-5-5-2S-7
Little = 10 to 20%
Over 50 - Very Dense 16 to 30 - Very Stiff Over 30 - Hard
FIELD NOTES: 1) Stratification lines represent approximate boundaries between soil types, transitions may be gradual.
SPT N-Values SPT N-Values Proportions
Loose, red-brown, fine to coarse SAND, trace fine Gravel, trace Silt
Loose, red-brown, fine to coarse SAND, trace Silt
Loose, red-brown, fine to coarse SAND, trace Silt
END OF EXPLORATION AT 22 FEET BELOW GROUND SURFACE
2) Water level readings have been made at times and under conditions stated, fluctuations may occur due to other factors.
11 to 30 - Medium Dense 5 to 8 - Medium Stiff Some = 20 to 35%
31 to 50 - Dense 9 to 15 - Stiff And = 35 to 50%
SYMBOL KEY
0 to 4 - Very Loose 0 to 2 - Very Soft Trace = 0 to 10%
5 to 10 - Loose 3 to 4 - Soft
0063-022.00 Boring Logs Page 1 of 2 Down to Earth Consulting, LLC
PROJECT BORING NO.
SHEET 1 of 1
FILE NO.
CHKD. BY
Boring Co. Boring Location See Boring Location Plan Driller Ground Surface El. Datum Logged By Date Start Date End
Hammer Type: Groundwater Readings (from ground surface)
Sampler Size: Date Time Depth (ft) Elev. Stabilization Time
Type Drill Rig: 5/26/23 -
Drilling Method:
D
E
P Casing
T Blows REC/PEN DEPTH
H (ft) (inches) (feet)
2 6/24 1 to 3
4 7/24 3 to 5
6 2/24 5 to 7
8 12/24 7 to 9
11 9/24 10 to 12
16 18/24 15 to 17
1. S denotes split-barrel sampler. 7. WH denotes weight of hammer
2. ST denotes 3-inch O.D. undisturbed sample. 8. WR denotes weight of rods
3. UO denotes 3-inch Osterberg undisturbed sample. 9. PP denotes Pocket Penetrometer.
4. PEN denotes penetration length of sampler. 10. FVST denotes field vane shear test.
5. REC denotes recovered length of sample. 11. RQD denotes Rock Quality Designation.
6. SPT denotes Standard Penetration Test. 12. C denotes core run number.
FILL
END OF EXPLORATION AT 17 FEET BELOW GROUND SURFACE
SAND
Over 50 - Very Dense 16 to 30 - Very Stiff Over 30 - Hard
FIELD NOTES: 1) Stratification lines represent approximate boundaries between soil types, transitions may be gradual.
2) Water level readings have been made at times and under conditions stated, fluctuations may occur due to other factors.
11 to 30 - Medium Dense 5 to 8 - Medium Stiff Some = 20 to 35%
31 to 50 - Dense 9 to 15 - Stiff And = 35 to 50%
SYMBOL KEY
0 to 4 - Very Loose 0 to 2 - Very Soft Trace = 0 to 10%
5 to 10 - Loose 3 to 4 - Soft Little = 10 to 20%
SPT N-Values SPT N-Values Proportions
Medium dense, red-brown, fine to coarse SAND, trace Silt S-6 5-5-6-6
S-5 6-6-5-5 Medium dense, red-brown, fine to coarse SAND, trace Silt
S-4 7-6-8-8 Medium dense, red-brown, fine to medium SAND, trace Silt
S-3 4-5-5-5 Loose, red-brown, fine to coarse SAND, trace Silt
S-2 4-4-5-4 Loose, brown/red-brown, fine to medium SAND, trace Silt
S-1 5-5-3-4 Loose, dark brown, fine to medium SAND, some Silt, trace (-) Roots
Type BLOWS PER Core Time
& No. 6 INCHES (min./ft)
3.25-inch I.D. Hollow-Stem Augers
SAMPLE INFORMATION SAMPLE DESCRIPTION STRATA
B-2
PROPOSED BUILDING ADDITIONS
81 FOURNIER STREET 0063-022.00
NEW HAVEN, CONNECTICUT DFL
Donut hammer driven by cathead with 30 inch drop
1-3/8" I.D. Split Spoon
Truck Mounted CME 55 10 - During drilling
Associated Borings Company Jaime Lloret Not Available Not Available
Mateusz Fekieta 5/26/2023 5/26/2023
0063-022.00 Boring Logs Page 2 of 2 Down to Earth Consulting, LLC
APPENDIX 3 -
LIMITATIONS
LIMITATIONS
Explorations
1. The analyses and recommendations submitted in this report are based in part upon the data obtained from subsurface explorations by others. The nature and extent of variations between these explorations may not become evident until construction. If variations then appear evident, it will be necessary to reevaluate the recommendations of this report.
2. The generalized soil profile described in the text is intended to convey trends in subsurface conditions.
The boundaries between strata are approximate and idealized and have been developed by interpretations of widely spaced explorations and samples; actual soil transitions are probably more erratic. For specific information, refer to the boring logs.
3. Water level readings have been made in the drill holes at times and under conditions stated on the boring logs. These data have been reviewed and interpretations have been made in the text of this report. However, it must be noted that fluctuations in the level of the groundwater may occur due to variations in rainfall, temperature, and other factors occurring since the time measurements were made.
Review
4. In the event that any changes in the nature, design or location of the proposed structure are planned, the conclusions and recommendations contained in this report shall not be considered valid unless the changes are reviewed and conclusions of this report modified or verified in writing by DTE. It is recommended that this firm be provided the opportunity for a general review of final design and specifications in order that earthwork and foundation recommendations may be properly interpreted and implemented in the design and specifications.
Construction
5. It is recommended that this firm be retained to provide soil engineering services during construction of the earthworks and foundation phases of the work. This is to observe compliance with the design concepts, specifications, and recommendations and to allow design changes in the event that subsurface conditions differ from those anticipated prior to start of construction.
Use of Report
6. This report has been prepared for the exclusive use of the City of New Haven, Connecticut for specific application to the project noted in this geotechnical report in accordance with generally accepted soil and foundation engineering practices. No other warranty, express or implied, is made.
7. This soil and foundation engineering report has been prepared for this project by DTE. This report is for design purposes only and is not sufficient to prepare an accurate bid. Contractors wishing a copy of the report may secure it with the understanding that its scope is limited to design considerations only.
8. This report may contain comparative cost estimates for the purpose of evaluating alternative foundation schemes. These estimates may also involve approximate quantity evaluations. It should be noted that quantity estimates may not be accurate enough for construction bids. Since DTE has no control over labor and materials cost and design, the estimates of construction costs have been made on the basis of experience. DTE does not guarantee the accuracy of cost estimates as compared to contractor's bids for construction costs.
File details come from the government source that posted it. Updated .