GAT - Government Acceptance Test Procedures_Flight Simulator Curved Screen.pdf

PDF 223 KB Posted

Attached to
Flight Simulator Curved Screen
Solicitation number
FA813924Q0036
Issued by

About this file

This document is the Government Acceptance Test (GAT) Procedures for a curved screen flight simulator. The GAT outlines a series of 29 verification steps to ensure the screen meets the technical requirements specified in the Performance Work Statement (PWS), such as viewing angles, screen movement, blending light sources, and software compatibility.

The related federal contract opportunity is for a "Flight Simulator Curved Screen" with a CLIN 0001 description of providing the screen in accordance with the PWS. The contract is being competed by the Department of the Air Force Materiel Command Air Force Sustainment Center. The requirement has a delivery timeframe of not to exceed 26 weeks after receipt of order. Offerors must be registered in SAM, have a passing NIST SP 800-171 assessment, and submit quotations that conform to all solicitation requirements to be considered for the award.

View the file

Other files

File Type Posted
Combined Synopsis Solicitation Amendment FA813924Q00360001 SF 30.pdf PDF
QandA_CSS FA813924Q0036 Questions and Answers_10 Oct 2024.pdf PDF
QandA_CSS FA813924Q0036 Questions and Answers_8 Oct 2024.pdf PDF
QandA_CSS FA813924Q0036 Questions and Answers_7 Oct 2024.pdf PDF
CSS-Combined Synopsis-Solicitation_FA813924Q0036.pdf PDF
PWS - Performance Work Statement_Flight Simulator Curved Screen_23 Apr 2024.pdf PDF
12139 CDRL A001 - BOM Bill of Materials - signed_Redacted.pdf PDF
12139 CDRL A007 - Acceptance Test Procedures (ATP) - DID DI-NDTI-80566.pdf PDF
Service Contract Act WD 2015-5315 - Rev 24_22 Jul 2024.pdf PDF
12139 Brand Name Justification_signed 28 Aug 2024_Redacted.pdf PDF
12139 CDRL A001 - BOM Bill of Materials - DID DI-PSSS-81656.pdf PDF
12139 CDRL A005 - Instruction Blending Warping - DID DI-TMSS-81675.pdf PDF
12139 CDRL A005 - Instructions for Blending and Warping - signed_Redacted.pdf PDF
GFP - Government Furnished Property_flight Simulator Curved Screed_GFPFA813924Q0036_4.pdf PDF
12139 CDRL A002 - IMS Integrated Master Schedule - DID DI-IPSC-82297.pdf PDF
12139 CDRL A004 - StatementCertificate of Volatility - signed_Redacted.pdf PDF
12139 CDRL A006 - Contractors Personnel Roster - DID DI-MGMT-81834.pdf PDF
12139 CDRL A007 - Acceptance Test Procedures (ATP) - signed_Redacted.pdf PDF
QPL - Qulified Parts List_Flight Simulator Curved Screen_Redacted.pdf PDF
12139 CDRL A002 - IMS Integrated Master Schedule - signed_Redacted.pdf PDF
12139 CDRL A003 - CAD Computer Aided Design - DID DI-MISC-81489.pdf PDF
12139 CDRL A003 - CAD Computer Aided Design - signed_Redacted.pdf PDF
12139 CDRL A004 - StatementCertificate of Volatility - DID DI-MISC-80508.pdf PDF
12139 CDRL A006 - Contractors Personnel Roster - signed_Redacted.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Government Acceptance Test (GAT) Procedures

Step PWS Reference Control Action Expected Result Actual Result/Notes

3.2.3.2 / 3.2.3.2.5 /

3.2.3.2.7

Inspect the visual display screen and confirm that the screen is cylindrical with no deformities.

The custom screen is in the shape of a cylinder with no joints or fillers.

2 3.2.3.2.1a Verify the screen has a 180-degree horizontal viewing angle via inspection of technical drawings.

The screen has 180-degree horizontal viewing angle from design eye point.

3 3.2.3.2.1b Verify the physical screen matches the technical drawing in this regard. Drawing matches physical implementation.

4 3.2.3.2.2a Verify the screen has a 25-degree upward viewing from design eye point via inspection of technical drawings

The screen has a 25-degree upward viewing angle from design eye point.

5 3.2.3.2.2b Verify the physical screen matches the technical drawing in this regard. Drawing matches physical implementation.

6 3.2.3.2.3a Verify the screen has a 15-degree downward viewing from design eye point via inspection of technical drawings

Screen has a 15-degree downward viewing from design eye point via inspection of technical drawings

7 3.2.3.2.3b Verify the physical screen matches the technical drawing in this regard. Drawing matches physical implementation.

8 3.2.3.2.4 Verify the screen can resist movement. Press frame and make sure it doesn't move easily.

Ensure frame is sturdy and resists movement

9 3.2.3.2.6

Verify a black space around the reflective area to absorb projector over scan.

There is a black bezel area.

3.2.3.3 / 3.2.3.3.2 /

3.2.3.3.5

Verify there is a automated shutter control and associated blinders for blending light sources. USAF representative shall take view out of calibration and have Contractor demonstrate it can be recalibrated.

Screen automatically recalibrates once procedure is intitated.

11 3.2.3.3.1

Verify the Automated Shutter control prevents bright banding while transition from Day to Night and Night to Day. Image generation will be set to different times to test.

There is no bright banding before or after transitions.

12 3.2.3.4a

Verify that no addional tools other than that was delivered will be required for calibration during calibration.

All tools and software required are included

Using the Quantum 3D Image Generator, display the “Uniform White” test pattern.

All display channels are showing an all white pattern.

Using the IG interface, apply the “Mapped Dot Pattern” on each visual channel.

To confirm the visual has been calibrated geometrically, inspect the pattern for geometric alignment between the projectors.

The test pattern has been warped to provide a seamless display with no misregistration in the overlap areas.

Using the IG interface, apply the “Uniform Field” test pattern at 100% brightness to all visual display channels.

The Green and Magenta lines are corretly over-laid creating white

To confirm the visual has been calibrated in color and intensity, inspect the visual for any distracting differences in color or luminance between each channel.

Project color bands of different colors that extend across multiple

No distracting color or luminance differences are observed.

17 3.2.3.4b

Verify all software delivered is activated without experiation date. All software delivered is activated without experiation date.

18 3.2.4.1

Verify all hardware was delivered as new unless prior authorization was granted.

All items where new prior to install.

3.2.4.2 /

CDRL A001

Bill of Material was delivered in ASM Y14.100 and included all required information.

Visually inspect documentation.

20 3.2.4.1/3.2.4.2

Verify BOM deliverables are free of propriatry markings. BOM deliverables should have minimum government data rights for activities the government funded.

21 3.2.4.3

Verify that all items delivered are operating as inteneded. All hardware is detected and responding to applicable protocols.

Verify that Image Generator recognizes the Projectors correctly through Hardware Manager.

Drivers installed correctly with no alerts.

Verify through Display Manager that each projector shows expected display modes (Resolution and Frequency)

Full resolution and Frequency available as described in Barco Manual.

24 DFARS

Verify CAD deliverables are free of over-restrictive data rights. CAD deliverables should have minimum government data rights for activities the government funded.

3.2.4.4.3 /

CDRL A003

Verify CAD Drawings conform to ASME Y14.100 Drawings contain all information required conforming to ASME 14.100?

3.2.4.4.4 /

CDRL A003

Verify CAD Drawings are free of Macros and Advanced Features. CAD Drawings can be opened in Edge, Chrome and Adobe Reader with full functionality.

3.2.4.6 /

CDRL A004 /

Verify all electronics items have Cerfitifacte of Volitility and Manuals. All documentation was provided

28 CDRL A005

Verify documentation was provided to perform Calibrations. Perform calibration with delivered documentation

29 CDRL A007

Did Vendor provide a sufficient ATP to verify design? Compare ATP to our PWS to verify completeness.

Has all task in ATP been completed.