G - Maxwell Submittal Log.pdf

PDF 116 KB Posted

Attached to
Keswick and Maxwell Substation Station Service Upgrades
Solicitation number
89503121BWA000028
Issued by

About this file

This submittal log and federal contract opportunity document outline requirements for upgrades to two substations. The submittal log details over 200 items required from the contractor to comply with standards for sitework, concrete, metalwork, electrical equipment, and environmental protections. These include construction schedules, safety plans, testing data, drawings, and as-built documents.

The federal contract opportunity is a competitive small business set-aside IFB to upgrade station service equipment and install foundations, structures, and precast components at the Keswick and Maxwell Substations in Redding and Williams, California. Interested parties can download the solicitation from SAM.gov starting April 16, 2021. Bids are due by specified dates and must be registered in SAM to be eligible for the estimated $750,000-$2.5 million firm-fixed price contract awarded by the Department of Energy Western Area Power Administration.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Title: MAXWELL SUBSTATION STATION SERVICE UPGRADES Award Date:

SUBMITTAL LOG

*Submittal required if item is used in the performance of the contract.

"T"= Submit transmittal sheet only.

"NLT"= No Later Than "NTP"= Notice To Proceed "ASAP"= As Soon As Practicable

Western Location Location Submittal In In

# Standards Project Specifications

STANDARD 1 STANDARD 1

1 Construction Schedule 1.1.4.1. (see project spec)

6 Breakdown of Contract Prices 1.1.6.1. NLT 30 days after NTP

7 Electrical Equipment & Steel Purchase Orders 1.2.3.1.

NLT 10 working days after PO award

10 Safety and Health Program 1.4.1.5.

NLT 10 days prior to start of construction

11 Copies of Certifications, Test Records & Technical Data 1.4.1.10. Prior to use

12 Load Performance Tests 1.4.1.10.(1) Prior to use

13 Crane & Aerial Lift Equipment Annual Inspection Records 1.4.1.10.(2) Prior to use

14 Brake Performance Test 1.4.1.10.(3) Prior to use

15 Test Results of Protective Ground Leads 1.4.1.10.(4) Prior to use

16 Material Safety Data Sheets 1.4.1.10.(5) Prior to use

17 Manufacturer's Load Rating For Hoists and Grips 1.4.1.10.(6) Prior to use

18 Certification of Fabricated Lifting and Rigging Devices 1.4.1.10.(7) & 1.4.11 Prior to use

19 Medical Examiner's Certificate 1.4.1.10.(8) & 1.4.3.3 Prior to use

21 Assurance of Competency in Equipment Operation 1.4.3.4. Prior to use

24 Structure Erection Plan 1.4.8.1. Prior to structure erection

27 Protective Ground Lead Test Results & Certification 1.4.14.3. Prior to use

28 Clearance, Hot Line Order & Special Work Permit Requests 1.4.15.3.

NLT 10 working days prior to starting work

STANDARD 2 STANDARD 2

32 Earth Material Testing Laboratory 2.1.1.2.(1) & 2.7.1.2.(1) 20 days prior to compacting

33 Earth Material Compaction Test Reports 2.1.1.2.(2)& 2.7.1. Immed. after test complete

35 Gravel Surfacing Material Gradation 2.1.1.4 Prior to placing

36 Gravel Surfacing Density & Compaction Test Results 2.1.1.4 NLT 7 days after test complete

STANDARD 3 STANDARD 3

51 Concrete Testing Laboratory 3.1.1.2.(1) & 3.1.1.3.

NLT 20 days prior to concrete placement

52 Concrete Mix Design 3.1.1.2.(2) & 3.1.1.5. NLT 10 days prior to use

53 Fly Ash For Concrete 3.1.1.2.(5) & 3.1.1.4. NLT 20 days prior to use

54 Admixtures and Curing Compound 3.1.1.2.(6) & 3.1.1.4. NLT 10 days prior to use

55 Batch Certificates 3.1.1.2.(7) Provide at delivery

56 Test Reports 3.1.1.2.(8) Immed. upon completing

59 Drawings & Data For Electrical Equip. Foundation Design 3.2.1.2. Prior to installation

60 Approval Drawings For Precast Cable Trench 3.2.1.3. Prior to precasting

61 Approval Drawings For Precast Concrete Pull Boxes 3.2.1.4. Prior to precasting

62 Final Drawings For Precast Cable Trench & Pull Boxes 3.2.1.5. Prior to material shipment

STANDARD 4 STANDARD 4

63 Approval Drawings For Steel Structures & Steel Modifications 4.1.1.2. Prior to fabrication

65 Final Drawings For Steel Structures & Oil Storage Tanks 4.1.1.4. Prior to material shipment

STANDARD 9 STANDARD 9

115 Contractor On-site Test Personnel 9.1.2.2.(2) Prior to working on-site

116 Electrical Test Reports & Documents 9.1.2.2.(3) NLT 7 days after testing

119 Equipment Installation Drawings Including Seismic Qualification Report Table 9-1 & 9.1.3.2. NLT 60 days after NTP

120 Equipment Informational Drawings & Data Table 9-1 & 9.1.3.3. NLT 60 days after NTP

121 Equipment Final Drawings Table 9-1 & 9.1.3.4.(1) NLT 21 days prior to equip.

installation

122 Equipment Parts Identification Lists & Bills of Materials Table 9-1 & 9.1.3.4.(2) NLT 21 days prior to equip.

installation

123 Manufacturer's Operation & Maintenance Instructions Table 9-1 & 9.1.3.4.(3) NLT 21 days prior to equip.

installation

124 Equipment & Oil Test Reports Table 9-1 & 9.1.3.5. Prior to shipping equipment

SUBSTATION – ELECTRICAL

Submittal Item Date Due

GENERAL REQUIREMENTS

SITEWORK

CONCRETE

SUBSTATION METALWORK AND TRANSMISSION LINE LATTICE STRUCTURES

Contract Title: LAWRENCE LIVERMORE SUBSTATION STATION SERVICE UPGRADES Award Date:

SUBMITTAL LOG

*Submittal required if item is used in the performance of the contract.

"T"= Submit transmittal sheet only.

"NLT"= No Later Than "NTP"= Notice To Proceed "ASAP"= As Soon As Practicable

126 Insulated Conductor Data Table 9-1 & 9.1.3.7. NLT 60 days after NTP

127 Revised Wiring Diagrams Table 9-1 & 9.1.3.9.

NLT 60 days after receipt of drawings

128 Contractor's As-Built Equipment Drawings Table 9-1 & 9.1.3.10.(1) NLT 60 days after equip.

checkout

129 As-built Western Drawings Table 9-1 & 9.1.3.10.(2) NLT 60 days after equip.

checkout

130 Test Reports For Ground Tests 9.2.1.3.

NLT 15 days after completion of testing

STANDARD 13 STANDARD 13

179 Recycled Materials Quantity Report 13.2.1. & 13.7.2.

180 Products Containing Recovered Materials Report 13.2.2. & 13.8.3.

182 Spill Prevention Notification & Cleanup Plan 13.2.5. & 13.11.2.

183 Tanker Oil Spill Prevention & Response Plan 13.2.6. & 13.11.3.

187 Lead Paint Notices 13.2.11. & 13.16.

188 Water Pollution Permits 13.2.12. & 13.17.2.

189 PCB Test Reports 13.2.13 & 13.18.2

190 Oil & Oil-Filled Electrical Equipment Receipt 13.2.14. & 13.18.5.

191 Cleanup Work Management Plan 13.2.16. & 13.19.2.

192 Post Cleanup Report 13.2.17. & 13.19.7.

STANDARD 15 STANDARD 15

193 As-Built Drawings 15.2.6.

DRAWINGS

ENVIRONMENTAL QUALITY PROTECTION

CUSTOM ENTRIES BELOW

Submittal List

File details come from the government source that posted it. Updated .