Keyes Road Over Wilder Brook Culvert Replacement Project

This is a project manual and invitation to bid issued by the City of Gardner, Massachusetts Department of Community Development and Planning for the construction of the Keyes Road Over Wilder Brook Culvert Replacement project (Bid Number 2027-011). The project involves furnishing all labor, equipment, and materials to complete phased demolition of an existing 8-foot diameter corrugated metal pipe culvert, demolition of existing road surface and sidewalk, bank stabilization, dewatering, dredging, roadway grading, water main relocation, installation of a new 24-foot span 3-sided rigid frame bridge structure, installation of hot mix asphalt walkway and berm, streambed restoration, roadway paving, and related work. The project includes numerous line items with estimated quantities, including clearing and grubbing (0.3 acres), unclassified excavation (460 cubic yards), bridge excavation (900 cubic yards), riprap placement (325 tons), dense graded crushed stone (100 cubic yards), superpave paving courses, curb and guardrail installation, and traffic control elements. Sealed bids will be received until 1:00 p.m. on October 29, 2026, at the City of Gardner Purchasing Agent's office. A voluntary pre-bid meeting is scheduled for October 14, 2026, at 10:00 a.m. at the project site near West Street and Keyes Road. An award notice will be issued within 30 days of bid opening, and the successful bidder must execute the contract within 10 days of receiving the Notice of Award. The contract time for substantial completion is November 30, 2027, with final completion by December 31, 2027.

The estimated project value is $1,930,000, and bidders must be prequalified by the Massachusetts Department of Transportation (MassDOT) in the Bridge Construction category to be eligible for award. Bid security in the form of a bid bond, certified check, or cashier's check equal to five percent of the total bid amount is required, with the successful bidder required to furnish performance and payment bonds for 100 percent of the contract price. Liquidated damages are assessed at $1,000 per calendar day for failure to complete work within the specified timeframe. The project is funded through the Massachusetts Department of Transportation's Community Culvert Grant and is subject to applicable federal, state, and local regulations, including MGL Chapter 30, Section 39M. Prevailing wage requirements apply under both Massachusetts General Laws (Chapter 149, Sections 26-27D) and federal Davis-Bacon wage decisions, with contractors required to comply with the greater of the two wage schedules. The City of Gardner is exempt from state sales tax, and bidding documents are available for $100 non-refundable charge or online registration through the city website.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual Volume 1 of 1

53 Southampton Road Westfield, MA 01085

Keyes Road Over Wilder Brook Culvert Replacement

City Of Gardner

October 2026

MATT

WZOREK

CIVIL

52674No.

10/06/2026

DANIEL S.

HOLMES

CIVIL

56624No.

10/06/2026

G-0384-60/10/6/26 TOC-1 Table of Contents

Keyes Road Over Wilder Brook Culvert Replacement Project

City of Gardner

Table of Contents

Section Title Number of Pages

Division 0 – Bidding and Contract Requirements

00100 Advertisement for Bids 2

00200 Information for Bidders 3

00300 Geotechnical Data 1

00410 Form for General Bid 13

A. Gardner Department of Development and Planning

Qualification Statement

00430 Bid Bond 2

00520 Agreement 2

00610 Performance Bond 3

00615 Payment Bond 3

00700 General Conditions 25

00800 Supplementary Conditions 10

A. Gardner Conservation Commission Order of Conditions 24

B. MassDEP 401 Water Quality Certification 12

C. Massachusetts State Prevailing Wage Rates 31

D. Federal Davis Bacon Wage Rates 5

Division 1 – General Requirements

01110 Summary of Work 4

01140 Work Restrictions

A. Construction Laydown Figure

01270 Measurement and Payment 1

01310 Coordination 5

01320 Construction Photographs 1

01325 Scheduling of Construction 3

01330 Submittal Procedures 11

01450 Quality Control 2

01451 Independent Testing Services

01520 Construction Facilities 1

01550 Traffic Regulation 2

01560 Temporary Barriers 1

01570 Temporary Controls 4

01600 Product Requirements 3

01630 Product Substitution During Construction 2

01720 Field Engineering 2

01725 Preservation and Restoration of Project Features 3

01770 Closeout Procedures 4

Division 2 – Special Provisions

INVITATION TO BID

00100-1

CITY OF GARDNER

DEPARTMENT OF COMMUNITY DEVELOPMENT AND PLANNING

The City of Gardner, acting herein through the City of Gardner’s Department of Community Development and Planning (DCDP), is soliciting bids for the construction of the Keyes Road Over Wilder Brook Culvert

Replacement project, Bid Number: 2027-011, located on Keyes Road in Gardner, MA. Sealed general bids will be received by the City of Gardner, Purchasing Agent at 95 Pleasant Street, Room 217, Gardner

Massachusetts 01440 until 1:00 p.m. local time on October 29, 2026 at which time and place said bids shall be publicly opened and read.

The bid openings will be recorded and then posted on the City of Gardner, MA YouTube page. A link will be emailed to all recorded holders on the morning of the bid opening. Bids submitted after this time will not be accepted.

Envelopes containing proposals should be clearly marked on the outside:

BID FOR KEYES ROAD OVER WILDER BROOK CULVERT REPLACEMENT

Bid Number 2027-011

The project includes furnishing all labor, equipment and materials required to complete the Keyes Road over Wilder Brook Culvert Replacement Project. The project includes, but is not limited to phased demolition of the existing 8’ diameter CMP culvert, demolition of the existing road surface and sidewalk, bank stabilization and grading, dewatering, dredging, roadway grading, water main relocation, installation of a new 24-foot span 3-sided rigid frame bridge structure, installation of new HMA walkway and HMA berm, streambed restoration, roadway paving and other work, appurtenances, and incidental items as set forth in the contract documents.

All bids for this project are subject to the provisions of Massachusetts General Laws Chapter 30, Section

39M, as amended.

MassDOT prequalification of contractors with the class of work as Bridge – Construction for the project with an estimated value of $1,930,000 will be required.

Bidding Documents may be obtained by registering on the City of Gardner website via the following link:

http://www.gardner-ma.gov/bids.aspx. Hard copies may also be obtained for $100.00 non-refundable printing charge from the City of Gardner Purchasing Department, 95 Pleasant Street, Gardner, Massachusetts 01440 between the hours of 8:00 a.m. and 4:30 p.m., Monday through Thursday and between the hours of 8:00 a.m. and 1:00 p.m. on Fridays, City recognized holidays excluded.

A voluntary pre-bid meeting will be held at the site on Wednesday, October 14, 2026 at 10:00 a.m.

Attendees to meet at the project site near the corner of West Street and Keyes Road, Gardner, MA 01440.

Minimum Wage Rates as determined by the Commissioner of Department of Labor and Workforce

Development under the provision of the Massachusetts General Laws, Chapter 149, Sections 26 to 27D, as http://www.gardner-ma.gov/bids.aspx

00100-2 amended, and federal Davis-Bacon wage decisions apply to this project. It is the responsibility of the contractor, before bid opening, to request if necessary, any additional information on Minimum Wage Rates for those trades people who may be employed for the proposed work under this contract. Bidders are required to comply with the greater of federal Davis-Bacon wage decisions or state minimum wage schedules as established by the Commissioner of Department of Labor and Workforce Development.

Bid security in the form of a bid bond, certified or cashier’s check, payable to the City of Gardner, is required in a dollar amount of not less than five percent (5%) of the total bid amount. A performance bond and labor and materials bond for 100% of the total contract price, issued by a satisfactory surety company shall be required by the successful bidder.

The City of Gardner reserves the right to reject any and all bids, to accept proposals deemed to be in the best interest of the City, and to waive any informalities or irregularities in the bids received. Bids may not be withdrawn within 30 days of the bid opening.

By: Joshua Cormier, Director of Purchasing

INFORMATION FOR BIDDERS

00112 - 1

1 Project Site

The Project is the Keyes Road Over Wilder Brook Culvert Replacement, located at Wilder Brook on Keyes

Road, Gardner, Worcester County, Massachusetts.

2 Inspection of Site

By submitting a bid, the Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to the conformation and conditions of the ground; the immediate and adjacent environs; access and egress; local ordinances, policies and regulations; and the identification of any discrepancies in the contract documents affecting the contract bid price, all as a result of a pre-bid visit and careful review of the bid documents.

Any failure of the Contractor to take the actions described and acknowledged in this paragraph shall not relieve the Contractor from responsibility for properly estimating the difficulty and cost of successfully performing all work in accordance with the Contract Documents without additional cost to the City of

Gardner Department of Community Development and Planning (hereinafter Owner, or City, or Awarding

Authority).

The Owner assumes no responsibility for any conclusions or interpretations made by the Contractor based upon the information made available by the Owner.

3 Prequalification Statements

In accordance with the City of Gardner’s requirements, prospective bidders must complete and submit a

Qualification Statement for this project. Qualification forms are included in Section 00410.

Bidders must be pre-qualified by the Massachusetts Department of Transportation (MassDOT) Bridges –

Construction category of work to bid on the above project. An award will not be made to a contractor who is not pre-qualified by MassDOT Highway Division prior to the opening of proposals.

4. Bid Deposit

All proposals must be accompanied by a bid deposit in the amount of five percent (5%) of the value of the bid, and shall be in the form of a bid bond, or a certified or cashier’s check issued by a responsible bank or trust company, payable to the City of Gardner, in the name of which the Contract for work is executed. Bid bonds shall be (a) in a form satisfactory to the City, (b) with a surety company qualified to do business in the Commonwealth and satisfactory to the City, and (c) conditioned upon the faithful performance by the principal of the agreements contained in the bid. The bid deposit must be enclosed in the same envelope with the proposal.

00112 - 2

Bid deposits will be returned to respective bidders within five (5) working days after proposals are opened;

except those of the three (3) lowest responsible and eligible general bidders, which the City will hold until the successful bidder has executed the Contract. Thereafter, all remaining deposits, including that of the successful bidder, will be returned upon the expiration of the time prescribed for making an award. See applicable provisions of MGL c. 30 § 39M, which may apply.

5 Award of Contract

The Notice of Award of a Contract, after approval by the awarding authority, shall be within thirty (30) days, Saturdays, Sundays and legal holidays excluded, and shall be in written form signed by the DCDP

Assistant Director. The notice shall bind the successful bidder to execute the Contract and furnish

Performance and Payment bonds, and be responsible for liquidated damages provided in the General

Conditions. The rights and obligations provided by the Contract shall become effective and binding upon the parties only upon formal execution. See applicable provisions of MGL c. 149 § 44A-H, and/or MGL c.

149 § 29, which may apply.

6. Time for Executing Contract and Liquidated Damages for Failure to Execute

The successful bidder shall execute and deliver to the Owner of the Contract, and all required Bonds and insurance certifications, within ten (10) days of receipt of Notice of Award. Failure or refusal of the successful bidder to execute and deliver the Contract and Bonds required within ten (10) days shall result in forfeiture of the bid deposit to the Owner as liquidated damages for such failure or refusal. The bid deposit shall become the property of the Owner for liquidated damages provided the amount of bid deposit does not exceed the difference between bid price and bid price of next lowest responsible bidder; and provided further that, in case of death, disability, bona fide clerical or mechanical error of a substantial nature, or other similar unforeseen circumstances affecting the general bidder, in the opinion of the Owner, said bid deposit shall be returned to such bidder.

7 Prices

In the event of discrepancy between the prices quoted in the proposal in words and those quoted in figures, the words shall control. The prices are to include the furnishing of all materials, plant, equipment, tools and other facilities, and the performance of all labor services necessary or proper for the completion of the work, including all delivery and/or freight costs FOB work site.

8. Sales Tax Exemption

The City of Gardner is exempt from State Sales Tax under the Sales Act, Chapter 14 of the Acts of 1966 and all amendments thereto. All purchases of supplies and materials in relation to the project are therefore exempt. This should be considered when forming contract prices. The City of Gardner Tax Exempt

Number is E-046-001-389.

9. All Contracts Subject to Appropriation

The execution of a Contract is subject to adequate financial appropriation for the Project as advertised. The lack of adequate financial appropriation by the Owner, or granting agency, for the Project shall constitute grounds to reject all bids, or those bids which exceed the financial limitations imposed by the Owner.

00112 - 3

10. Changes in Quantities of Work

A. Site Conditions – MGL c. 30 § 39N is incorporated herein and made a part of this Contract to the extent required by law.

B. Quantities – The City reserves the right to modify the scope of work including, but not limited to, estimated quantities, provided that the total price for all such modifications does not exceed 25% of the total Contract price, or as otherwise required by law.

The Contract shall be awarded to the lowest eligible and responsible bidder. The lowest bidder shall be the bidder with the lowest base bid plus a total of the alternates, if included in the project, selected by the Owner in the order presented.

11. Addenda

If it becomes necessary to revise any part of this Invitation to Bid or if additional data are necessary to enable an exact interpretation of provisions, such addenda will be provided to all bidders who have requested the bid documents. No addenda will be issued within the immediate three (3) business days prior to the bidding deadline. If an addendum is issued, all bidders shall acknowledge receipt of each addenda on their bid submission.

12. Questions During Bidding Period

Any questions during the bidding period as to the interpretation of the Invitation to Bid, form of proposal, form of Contract, plans, specifications or form of performance and payment bonds, must be received by the

City not less than five (5) days prior to the date set for receipt of bids. Written inquires should be directed to: The Department of Community Development and Planning, Manca Annex, 115 Pleasant Street, Room

201, Gardner, MA 01440. Attn: Jason Stevens, Director.

The Owner will forward, via certified mail, return receipt requested, via confirmed facsimile, or email to all prospective bidders at the address given by them, interpretations of all questions raised in accordance with this section, which in the Owner’s opinion, require such interpretation. The Owner’s response shall be issued not less than two days prior to the date set for receipt of bids. Oral representations shall not bind the

Owner.

13. Competence

No Contract shall be awarded except to responsible, established bidders capable of performing the class of work contemplated. Before the awarding of the Contract, any bidder may be required to show that it has the necessary facilities, experience, ability and financial resources to perform the work in a satisfactory manner and within the time stipulated. The bidder may be required to furnish the Owner with statements as to its experience and financial status. The bidder agrees upon request of the Owner to furnish in confidence such information as will enable it to judge the financial responsibility of the bidder and any listed subcontractors.

G-0384-060 _9/30/26 00300-1 Geotechnical Data

SECTION 00300

GEOTECHNICAL DATA

PART 1 GENERAL

1.1 SUMMARY

A. For the preparation of Bidding Documents, Engineer has relied upon the following reports and tests of subsurface and latent physical conditions of the site. The locations of all geotechnical explorations are shown on the Drawings.

1. Soil boring data (Sheet No. 11 of the Drawings)

a. The subsurface data are not guaranteed as to accuracy or completeness, nor are they a part of the Contract Documents.

b. Bidders are cautioned that the subsurface data have been utilized for general design purposes only. No explicit or implicit representation is made as to the nature of the materials which may be encountered below the surface of the ground.

c. The making available of this subsurface data to Bidders is not intended to relieve them from their responsibility to familiarize themselves with the subsurface and other site conditions.

PART 2 PRODUCTS – NOT USED

PART 3 EXECUTION – NOT USED

END OF SECTION

J:\G\G0384 GARDNER\T60 - KEYES ROAD CULVERT REPLACEMENT\DESIGN\SPECIFICATIONS\DIVISION 0\00300 - GEOTECHNICAL DATA.DOCX

G-0384-060 _10/6/26 00410-1 Form for General Bid

SECTION 00410

FORM FOR GENERAL BID

PROJECT IDENTIFICATION:

Keyes Road Over Wilder Brook Culvert Replacement

IFB 2027-011

TABLE OF ARTICLES

1. Bid Recipient

2. Bidder’s Acknowledgements

3. Bidder’s Representations

4. Bidder’s Certifications

5. Basis of Bid

6. Time of Completion

7. Attachments to This Bid

8. Bid Submittal

ARTICLE 1 BID RECIPIENT

1.1 This Bid is submitted to:

City of Gardner

Purchasing Agent

95 Pleasant Street - Room 217

Gardner, Massachusetts 01440

1.2 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2 BIDDER’S ACKNOWLEDGEMENTS

2.1 Bidder accepts all of the terms and conditions of the Advertisement for Bids and Instructions to

Bidders, including without limitation, those dealing with the disposition of Bid deposit. The Bid will remain subject to acceptance for 30 days after the bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

2.2 The Work under this Contract shall be subject to the provisions of Chapter 30, Section 39M of the Massachusetts General Laws.

ARTICLE 3 BIDDER’S REPRESENTATIONS

G-0384-060 _10/6/26 00410-2 Form for General Bid

3.1 In submitting this Bid, Bidder represents, as set forth in the Agreement, that:

A. Bidder has examined and carefully studied the Bidding Documents, and any data and reference items identified in the Bidding Documents and hereby acknowledges the receipt of all Addenda.

B. Bidder has visited the Site, conducted a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfied itself as to the general, local and

Site conditions that may affect cost, progress, and performance of the Work.

C. Bidder is familiar with and has satisfied itself as to all federal, state and local Laws and

Regulations that may affect cost, progress and performance of the Work.

D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the

Supplementary Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings.

E. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and any Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs.

F. Bidder agrees, based on the information and observations referred to in the preceding paragraph, that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price bid and within the times required and in accordance with the other terms and conditions of the Bidding Documents.

G. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

H. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and confirms that the written resolution thereof by Engineer is acceptable to Bidder.

I. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work.

J. The submission of this Bid constitutes an incontrovertible representation by Bidder that

Bidder has complied with every requirement of this Article, and that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

K. Bidder is aware that the estimated quantities on the Bid form are subject to Article 13.03 of the General Conditions (Section 00700).

G-0384-060 _10/6/26 00410-3 Form for General Bid

ARTICLE 4 BIDDER’S CERTIFICATION

4.1 Bidder hereby certifies that he is able to furnish labor that can work in harmony with all other elements of labor employed or to be employed in the work, that all employees to be employed at the Site will have successfully completed a course in construction safety and health approved by the United States Occupational Safety and Health Administration that is at least 10 hours in duration at the time the employee begins work and who shall furnish documentation of successful completion of said course with the first certified payroll report for each employee, and that Bidder will comply fully with all laws and regulations applicable to awards made subject to MGL Chapter 30, Section 39M.

4.2 Bidder certifies that, under penalty of perjury, Bidder is not presently debarred from doing public construction work in the Commonwealth under the provisions of MGL Chapter 29, Section 29F or any other applicable debarment provisions of any other chapter of the General

Laws or any rule or regulation promulgated thereunder; and is not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency.

4.3 Bidder hereby certifies under the penalties of perjury, to the best of Bidder’s knowledge and belief, that Bidder has filed all State tax returns and paid all State taxes required by law.

4.4 Bidder certifies under penalties of perjury that this Bid is in all respects bona fide, fair and made without collusion or fraud with any other person. As used herein the word “person” shall mean any natural person, joint venture, partnership, corporation or other business or legal entity.

4.5 Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;

4.6 Bidder certifies that Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;

4.7 Bidder certifies that Bidder has not solicited or induced any individual or entity to refrain from bidding; and

4.8 Bidder certifies that Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this paragraph:

A. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process;

B. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of the Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;

C. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and

D. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

G-0384-060 _10/6/26 00410-4 Form for General Bid

ARTICLE 5 BASIS OF BID

5.1 Bidder will complete the Work in accordance with the Contract Documents for the following price(s):

G-0384-060 _10/6/26 00410-5 Form for General Bid

Item

Number

Item Name and Unit Bid Prices

Written in Words and Figures

Estimated Quantity Total Amount of Item

(in figures)

101 Clearing and Grubbing, per acre, the price of:

x 0.3 A =

113.1 Demolition of Culvert No 1., per lump sum, the

price of:

lump sum =

120.1 Unclassified Excavation, per cubic yard, the price

of:

x 460 c.y. =

140 Bridge Excavation, per cubic yard, the price of:

x 900 c.y. =

144 Class B Rock Excavation, per cubic yard, the price x 25 c.y. =

150 Ordinary Borrow, per cubic yard, the price of:

x 225 c.y. =

151 Gravel Borrow, per cubic yard, the price of:

x 300 c.y. =

G-0384-060 _10/6/26 00410-6 Form for General Bid

151.2 Gravel Borrow for Backfilling Structures and

Pipes, per cubic yard, the price of:

x 450 c.y. =

170 Fine Grading and Compacting – Subgrade Area, per square yard, the price of:

x 900 s.y. =

302.12 12-inch Ductile Iron Water Pipe (rubber gasket) per linear foot, the price of:

x 130 l.f. =

345.61 6-inch Temporary Service Pipe, per lump sum, the

350.12 12-inch Gate and Gate Box, each, the price of:

x 2 each =

373.12 12-Inch Water Pipe Insulation, per linear foot, the x 70 l.f. =

376 Hydrant Assembly, each, the price of:

x 2 each =

G-0384-060 _10/6/26 00410-7 Form for General Bid

402 Dense Graded Crushed Stone for Sub-Base, per cubic yard, the price of:

x 100 c.y. =

415.2 Pavement Fine Milling, per square yard, the price

x 75 s.y. =

440 Calcium Chloride for Roadway Dust Control, per pound, the price of:

x 1350 lb =

450.23 Superpave Surface Course – 12.5 (SSC- 12.5), per

ton, the price of:

x 100 ton =

450.32 Superpave Intermediate Course – 19.0 (SIC –

19.0), per ton, the price of:

x 150 ton =

452 Asphalt Emulsion for Tack Coat, per gallon, the x 60 gal =

453 HMA Joint Adhesive, per linear foot, the price of:

x 950 l.f. =

472 Temporary Asphalt Patching, per ton, the price of:

x 150 ton =

G-0384-060 _10/6/26 00410-8 Form for General Bid

482.3 Sawcutting Asphalt Pavement, per linear foot, the

x l50 l.f. =

509 Granite Transition Curb for Pedestrian Curb

Ramps – Straight, per linear foot, the price of:

x 20 l.f. =

509.1 Granite Transition Curb for Pedestrian Curb

Ramps – Curved, per linear foot, the price of:

x 10 l.f.=

570.2 Hot Mix Asphalt Curb – Type 2, per linear foot, the price of:

x 170 l.f. =

580 Curb Removed and Reset, per linear foot, the price x 30 l.f. =

620.12 Guardrail TL-2 (Single Faced), per linear foot, the

X 175 l.f. =

620.32 Guardrail – Curved TL-2 (Single Faced), per

linear foot, the price of:

x 175 l.f. =

G-0384-060 _10/6/26 00410-9 Form for General Bid

627.82 Guardrail Tangent End Treatment TL-2, each, the

x 4 each =

628.24 Transition to Bridge Rail, each, the price of:

x 4 each =

702 Hot Mix Asphalt Sidewalk or Driveway, per ton, x 30 ton =

748 Mobilization, per lump sum, the price of:

*not to exceed 3% of total bid amount

*lump sum =

751 Loam for Road Sides, per cubic yard, the price of:

x 150 c.y. =

765 Seeding, per square yard, the price of:

x 1000 s.y. =

767.121 Sediment Control Barrier, per linear foot, the price

x 300 l.f. =

769 Pavement Milling Mulch Under Guardrail, per linear foot, the price of:

x 350 l.f. =

G-0384-060 _10/6/26 00410-10 Form for General Bid

816.81 Temporary Traffic Control Signal, per lump sum, 850 Traffic Controls for Construction Operations, per lump sum, the price of:

866.106 6-inch Reflectorized White Line (Thermoplastic), x 500 l.f.=

866.112 12-inch Reflectorized White Line (Thermoplastic), x 200 l.f.=

867.106 6-inch Reflectorized Yellow Line (Thermoplastic), x 500 l.f. =

880. Traffic Police for Construction Operations, the price of:

Thirty-Five Thousand Dollars and Zero Cents

($35,000.00 )

Allowance =

$35,000.00_________

953.1 Temporary Support of Excavation, per lump sum, G-0384-060 _10/6/26 00410-11 Form for General Bid

983.1 Riprap, per ton, the price of:

x 325 ton =

983.4 Streambed Material, per cubic yard, the price of:

x 100 c.y. =

991.1 Control of Water- Structure No G-01-025 (CD5), per lump sum, the price of:

995.01 Bridge Structure – Bridge No G-01-025 (CD5), each, the price of:

x 1 each =

998.1 Monthly Price Adjustment for HMA Mixtures, the

One Thousand Dollars and Zero Cents

($1,000.00 )

$1,000.00__________

998.2 Monthly Price Adjustment for Diesel Fuel, the

998.3 Monthly Price Adjustment for Gasoline, the price

G-0384-060 _10/6/26 00410-12 Form for General Bid

998.4 Monthly Price Adjustment for Portland Cement,

998.5 Utility Pole Relocation, allowance, the price of:

Twenty-Five Thousand Dollars and Zero Cents

($25,000.00 ) allowance =

$25,000.00_________

TOTAL AMOUNT OF BID – Items 101 through 998.5 dollars

(words)

(figures)

5.2 This Bid includes Addenda numbered .

ARTICLE 6 TIME OF COMPLETION

6.1 Bidder agrees that the Work will be substantially completed and ready for final payment in accordance with paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

6.2 Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within the times as stated in the Agreement.

ARTICLE 7 ATTACHMENTS TO THIS BID

7.1 The following documents are attached to and made a condition of this Bid:

A. Bid deposit in the amount of dollars ($ ), consisting of a bid bond in the amount of five percent of the total amount of Bid

B. Evidence of authority to sign

C. List of Project References

D. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such license within the time for acceptance of Bids

E. Evidence of Bidder's qualifications in accordance with Article 3 of Section 00112 –

Information for Bidders

F. City of Gardner Department of Community Development and Planning “Qualification

Statement”

G. MBE/WBE participation forms

ARTICLE 8

G-0384-060 _10/6/26 00410-13 Form for General Bid

BID SUBMITTAL

BIDDER: [Indicate correct name of bidding entity]

By:

[Signature]

[Printed name]

(If Bidder is a corporation, a limited liability company, a partnership, or a joint venture, attach evidence of authority to sign.)

Attest:

[Signature]

[Printed name]

Title:

Submittal Date:

Address for giving notices:

Telephone Number:

Fax Number:

Contact Name and e-mail address:

Bidder’s License No.:

(where applicable)

END OF SECTION

\\TIGHEBOND.COM\DATA\DATA\PROJECTS\G\G0384 GARDNER\T60 - KEYES ROAD CULVERT REPLACEMENT\DESIGN\SPECIFICATIONS\DIVISION

0\00410 - FORM FOR GENERAL BID.DOCX

“QUALIFICATION STATEMENT”

Submit this form with your bid. Answer all questions. Responses must be clear and comprehensive. If necessary, attach separate sheets for answers. The party who will submit the bid for the firm must sign this form. This statement must be notarized. Bidders may submit additional supporting information if they desire.

1. Name of Bidder.

2. Location of permanent main office.

3. When was the firm organized?

4. How many years have you been engaged in the contracting business under your present firm or trade name?

5. Describe the general character of work performed by your company.

6. List the contracts your firm has on hand stating for each contract: name and address of the client and name of the person supervision for the client; contract value; the start and stop dates.

7. List at least three (3) similar contracts recently completed by your firm, stating for each contract:

name and address of client and name of person supervision for client; contract value; and the month and year completed.

8. Have you ever failed to complete any contract awarded to you? Yes No

If so, explain where and why.

9. Have you ever defaulted on a contract: Yes No

If so, explain where and why.

10. Describe your experience in construction work similar in nature and scope to this project.

11. Describe the background and experience of the principal members of your organization, including the officers.

12. Identify the employee who will be responsible for managing this project.

13. List the major equipment your firm has available for this contract.

14. Credit available:

15. Provide a bank reference (name and address of institution, name of supervising person for the bank)

16. Will you provide a detailed financial statement and furnish such other information as the City of

Gardner, Department of Community Development and Planning may reasonably request?

Yes No

The undersigned certifies under the law of perjury that the information provided in this Qualification

Statement is true, complete and correct. The undersigned hereby authorizes and requests any person, firm or corporation to furnish any information requested by the City of Gardner, Department of

Community Development and Planning to verify the information provided in this Qualification

Statement.

By: ________________________________________________________ Date: ___________

Type or print name and title: ___________________________________________________________

COMMONWEALTH / STATE OF _________________________

_____________________ County, SS.

On this _________ day of ___________, 20__, before me, the undersigned notary public, personally appeared __________________ (name of document signer), proved to me through satisfactory evidence of identity, which was/were _______________________, to be the person whose name is signed on the preceding or attached document, and acknowledge to me that (he) (she) signed it voluntarily and for its stated purpose.

Notary Public

My Commission Expires:

PENAL SUM FORM

EJCDC® C-430, Bid Bond (Penal Sum Form). Published 2013.

Prepared by the Engineers Joint Contract Documents Committee.

BID BOND

Any singular reference to Bidder, Surety, Owner or other party shall be considered plural where applicable.

BIDDER (Name and Address):

SURETY (Name, and Address of Principal Place of Business):

OWNER (Name and Address):

BID

Bid Due Date:

Description (Project Name— Include Location):

BOND

Bond Number:

Date:

Penal sum $

(Words) (Figures) Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth below, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

BIDDER SURETY

(Seal) (Seal)

Bidder’s Name and Corporate Seal Surety’s Name and Corporate Seal

By: By:

Signature Signature (Attach Power of Attorney)

Print Name Print Name

Title Title

Attest: Attest:

Signature Signature

Note: Addresses are to be used for giving any required notice.

Provide execution by any additional parties, such as joint venturers, if necessary.

PENAL SUM FORM

EJCDC® C-430, Bid Bond (Penal Sum Form). Published 2013.

Prepared by the Engineers Joint Contract Documents Committee.

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond. Payment of the penal sum is the extent of Bidder’s and Surety’s liability. Recovery of such penal sum under the terms of this Bond shall be Owner’s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder shall occur upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation shall be null and void if:

3.1 Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or

3.2 All Bids are rejected by Owner, or

3.3 Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).

4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.

5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions shall not in the aggregate exceed 120 days from the Bid due date without Surety’s written consent.

6. No suit or action shall be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety and in no case later than one year after the Bid due date.

7. Any suit or action under this Bond shall be commenced only in a court of competent jurisdiction located in the state in which the Project is located.

8. Notices required hereunder shall be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United States Registered or Certified Mail, return receipt requested, postage pre-paid, and shall be deemed to be effective upon receipt by the party concerned.

9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby.

10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond shall be deemed to be included herein as if set forth at length.

If any provision of this Bond conflicts with any applicable statute, then the provision of said statute shall govern and the remainder of this Bond that is not in conflict therewith shall continue in full force and effect.

11. The term “Bid” as used herein includes a Bid, offer, or proposal as applicable.

AGREEMENT FORM

00500-1

AGREEMENT

BY AND BETWEEN

THE CITY OF GARDNER

AND

CONTRACTOR

THIS AGREEMENT made this _______ day of _______, 2026, by and between the City of

Gardner, located at 95 Pleasant Street, Gardner, MA 01440, hereinafter call the “Owner”, acting herein through the City of Gardner’s Department of Community Development and Planning, and

________________, located at ________________ hereinafter called the “Contractor”, WITNESSETH, that the Owner and the Contractor, for the consideration hereafter named, agree as follows:

Article 1. SCOPE OF WORK:

The Contractor shall furnish all labor, tools, equipment and materials necessary to perform the Work required under the terms and conditions of the Contract Documents for the Keyes Road Over Wilder

Brook Culvert Replacement.

Article 2. TIME OF COMPLETION:

The Contractor shall commence work under this Contract on the date specified in the written “Notice to Proceed” from the Owner and shall bring the work to Substantial Completion by November 30, 2027 and ready for final payment by December 31, 2027. Damages for delays in the performance of the Work shall be as specified within the General Conditions of the Contract Documents.

Article 3. THE CONTRACT SUM:

The Owner shall pay the Contractor in current funds for the performance of the Work, subject to additions and deductions by Change Order(s), the Contract Sum of $_______________.

Article 4. THE CONTRACT DOCUMENTS:

The following, together with this Agreement, form the Contract Documents and all are as fully a part of the Contract as if attached to this Agreement or repeated herein: Advertisement, Bidding

Documents, Contract Forms, Conditions of the Contract, and Specifications as enumerated in the

Table of Contents; the Drawings as enumerated in the List of Contract Drawings; Addenda;

Modifications issued after execution of the Contract; and other documents enumerated under Section

2.6 of the General Conditions.

AGREEMENT FORM

00500-2

Terms used in this Agreement which are defined in the Conditions of the Contract, shall have the meanings designated in those Conditions.

By signing this Agreement, the Contractor certifies under the penalties of perjury that it has complied with all laws of the Commonwealth relating to taxes.

IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed as of the date first above written:

CONTRACTOR CITY OF GARDNER

By: ________________________________ By: _________________________________

Michael J. Nicholson, Mayor

By: _________________________________

Joshua L. Cormier, Purchasing Director

Atty. Vincent Pusateri, II, City Solicitor

Jason Stevens, Director of Community

Development and Planning

CERTIFIED AS TO AUTHORITY OF THE

MAYOR AND AVAILABILITY OF FUNDS

IN THE AMOUNT OF

Karen Butler, City Auditor

(If a corporation, attach to each signed Contract a notarized copy of the corporate vote authorizing the signatory to sign this Contract, and the executed tax attestation.)

EJCDC® C-610, Performance Bond

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 1 of 3

PERFORMANCE BOND

CONTRACTOR (name and address):

SURETY (name and address of principal place of business):

OWNER (name and address):

CONSTRUCTION CONTRACT

Effective Date of the Agreement:

Amount:

Description (name and location):

BOND

Bond Number:

Date (not earlier than the Effective Date of the Agreement of the Construction Contract):

Amount:

Modifications to this Bond Form: None See Paragraph 16

Surety and Contractor, intending to be legally bound hereby, subject to the terms set forth below, do each cause this Performance Bond to be duly executed by an authorized officer, agent, or representative.

CONTRACTOR AS PRINCIPAL SURETY

(seal) (seal) Contractor’s Name and Corporate Seal Surety’s Name and Corporate Seal

Signature Signature (attach power of attorney)

Notes: (1) Provide supplemental execution by any additional parties, such as joint venturers. (2) Any singular reference to

Contractor, Surety, Owner, or other party shall be considered plural where applicable.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 2 of 3

1. The Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to the Owner for the performance of the Construction Contract, which is incorporated herein by reference.

2. If the Contractor performs the Construction Contract, the Surety and the Contractor shall have no obligation under this Bond, except when applicable to participate in a conference as provided in Paragraph 3.

3. If there is no Owner Default under the Construction Contract, the Surety’s obligation under this Bond shall arise after:

3.1 The Owner first provides notice to the Contractor and

the Surety that the Owner is considering declaring a Contractor Default. Such notice shall indicate whether the Owner is requesting a conference among the Owner, Contractor, and Surety to discuss the Contractor’s performance. If the Owner does not request a conference, the Surety may, within five (5) business days after receipt of the Owner’s notice, request such a conference. If the Surety timely requests a conference, the Owner shall attend. Unless the Owner agrees otherwise, any conference requested under this Paragraph 3.1 shall be held within ten (10) business days of the Surety’s receipt of the Owner’s notice. If the Owner, the Contractor, and the Surety agree, the Contractor shall be allowed a reasonable time to perform the Construction Contract, but such an agreement shall not waive the Owner’s right, if any, subsequently to declare a Contractor Default;

3.2 The Owner declares a Contractor Default, terminates

the Construction Contract and notifies the Surety; and

3.3 The Owner has agreed to pay the Balance of the

Contract Price in accordance with the terms of the Construction Contract to the Surety or to a contractor selected to perform the Construction Contract.

4. Failure on the part of the Owner to comply with the notice requirement in Paragraph 3.1 shall not constitute a failure to comply with a condition precedent to the Surety’s obligations, or release the Surety from its obligations, except to the extent the Surety demonstrates actual prejudice.

5. When the Owner has satisfied the conditions of Paragraph 3, the Surety shall promptly and at the Surety’s expense take one of the following actions:

5.1 Arrange for the Contractor, with the consent of the

Owner, to perform and complete the Construction Contract;

5.2 Undertake to perform and complete the Construction

Contract itself, through its agents or independent contractors;

5.3 Obtain bids or negotiated proposals from qualified

contractors acceptable to the Owner for a contract for performance and completion of the Construction Contract, arrange for a contract to be prepared for execution by the Owner and a contractor selected with the Owners concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the bonds issued on the Construction Contract, and pay to the Owner the amount of damages as described in Paragraph 7 in excess of the Balance of the Contract Price incurred by the Owner as a result of the Contractor Default; or

5.4 Waive its right to perform and complete, arrange for

completion, or obtain a new contractor, and with reasonable promptness under the circumstances:

5.4.1 After investigation, determine the amount for

which it may be liable to the Owner and, as soon as practicable after the amount is determined, make payment to the Owner; or

5.4.2 Deny liability in whole or in part and notify the

Owner, citing the reasons for denial.

6. If the Surety does not proceed as provided in Paragraph 5 with reasonable promptness, the Surety shall be deemed to be in default on this Bond seven days after receipt of an additional written notice from the Owner to the Surety demanding that the Surety perform its obligations under this Bond, and the Owner shall be entitled to enforce any remedy available to the Owner. If the Surety proceeds as provided in Paragraph 5.4, and the Owner refuses the payment or the Surety has denied liability, in whole or in part, without further notice the Owner shall be entitled to enforce any remedy available to the Owner.

7. If the Surety elects to act under Paragraph 5.1, 5.2, or 5.3, then the responsibilities of the Surety to the Owner shall not be greater than those of the Contractor under the Construction Contract, and the responsibilities of the Owner to the Surety shall not be greater than those of the Owner under the Construction Contract. Subject to the commitment by the Owner to pay the Balance of the Contract Price, the Surety is obligated, without duplication for:

7.1 the responsibilities of the Contractor for correction of defective work and completion of the Construction Contract;

7.2 additional legal, design professional, and delay costs resulting from the Contractor’s Default, and resulting from the actions or failure to act of the Surety under Paragraph 5; and

7.3 liquidated damages, or if no liquidated damages are specified in the Construction Contract, actual damages caused by delayed performance or non-performance of the Contractor.

8. If the Surety elects to act under Paragraph 5.1, 5.3, or 5.4, the Surety’s liability is limited to the amount of this Bond.

9. The Surety shall not be liable to the Owner or others for obligations of the Contractor that are unrelated to the Construction Contract, and the Balance of the Contract Price shall not be reduced or set off on account of any such unrelated obligations. No right of action shall accrue on this Bond to any person or entity other than the Owner or its heirs, executors, administrators, successors, and assigns.

10. The Surety hereby waives notice of any change, including changes of time, to the Construction Contract or to related subcontracts, purchase orders, and other obligations.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 3 of 3

11. Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located and shall be instituted within two years after a declaration of Contractor Default or within two years after the Contractor ceased working or within two years after the Surety refuses or fails to perform its obligations under this Bond, whichever occurs first. If the provisions of this paragraph are void or prohibited by law, the minimum periods of limitations available to sureties as a defense in the jurisdiction of the suit shall be applicable.

12. Notice to the Surety, the Owner, or the Contractor shall be mailed or delivered to the address shown on the page on which their signature appears.

13. When this Bond has been furnished to comply with a statutory or other legal requirement in the location where the construction was to be performed, any provision in this Bond conflicting with said statutory or legal requirement shall be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement shall be deemed incorporated herein. When so furnished, the intent is that this Bond shall be construed as a statutory bond and not as a common law bond.

14. Definitions

14.1 Balance of the Contract Price: The total amount payable

by the Owner to the Contractor under the Construction Contract after all proper adjustments have been made including allowance for the Contractor for any amounts received or to be received by the Owner in settlement of insurance or other claims for damages to which the Contractor is entitled, reduced by all valid and proper payments made to or on behalf of the Contractor under the Construction Contract.

14.2 Construction Contract: The agreement between the

Owner and Contractor identified on the cover page, including all Contract Documents and changes made to the agreement and the Contract Documents.

14.3 Contractor Default: Failure of the Contractor, which has not been remedied or waived, to perform or otherwise to comply with a material term of the Construction Contract.

14.4 Owner Default: Failure of the Owner, which has not

been remedied or waived, to pay the Contractor as required under the Construction Contract or to perform and complete or comply with the…