This is a Statement of Work (SOW) for Uninterruptible Power Supply (UPS) Connections at Hanscom Air Force Base, prepared by the 66th Air Base Group Communications and Information Division dated June 26, 2026.
The project objective is to connect all required data center equipment in Building 1435 to the primary building UPS system while ensuring minimal operational disruption. The contractor must inventory existing equipment, identify items not connected to the primary UPS, and develop a comprehensive connection plan. All equipment except those powered by designated pink circuits must be connected to and supported by the primary UPS. The on-site installation phase is estimated at approximately two weeks, with a total project duration not to exceed sixteen weeks from contract award to final acceptance. The contractor shall provide subject matter expertise specific to the EATON platform (Model 93PM-L-120). Pre-installation requirements include conducting a load study, detailed inventory, and one-line diagrams; performing UPS electrical load and sizing studies verifying NEC compliance; and obtaining Civil Engineering (CE) and Communications Division (SC) approvals. The contractor must also conduct a site survey to assess current and expected UPS loads and address power, communication, NEC, Unified Facilities Criteria (UFC), Unified Facilities Guide Specifications (UFGS), and Occupational Safety and Health Administration (OSHA) standards.
Installation requirements include minimizing downtime through phased approaches with outages scheduled during pre-approved after-duty hours (Friday evenings and weekends), coordinating with CE and SC, ensuring proper grounding per NEC standards, and configuring non-protected power breaker panels to be supported by Protected Power infrastructure. The contractor must maintain clean work areas, secure all underfloor components above grade using waterproof materials, paint receptacles and feed boxes to match corresponding breaker box colors, and exclude all pink-circuit systems from the scope. Post-installation deliverables include labeling all breaker boxes and circuits, demonstrating NEC compliance, obtaining CE and SC acceptance, providing as-built designs and reports, and conducting comprehensive testing and commissioning with load bank testing at 25%, 50%, and 75% design loads. All work must comply with Buy American Act provisions, and comprehensive safety protocols including OSHA compliance, site-specific safety plans, personal protective equipment requirements, fall protection, and hazardous materials handling must be observed. Government points of contact include CE and SC project managers, with normal working hours 7:30 a.m. to 4:15 p.m. Monday through Friday.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1759 UPS connection - QA--20260722.pdf | ||
| Wage Determination Middlesex County June 2026.pdf | ||
| Solicitation - FA283526Q0019.pdf | ||
| FY26_B1435 UPS Connections_Bid Schedule.xlsx | XLSX spreadsheet | |
| SF1449 Cover Letter B1435 UPS Connections.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
For
Uninterruptible Power Supply (UPS) Connections
66th Air Base Group Communications and Information Division
(66ABG/SC)
Buildings 1435
Hanscom AFB, MA 01731
Date: 26 June 2026 Prepared by:
66ABG/SC
Controlled Unclassified Information
• PURPOSE
The purpose of this project is to connect all required data center equipment in Building 1435 (B1435) to the primary building Uninterruptible Power Supply (UPS). This effort includes the installation of dedicated power sources for all designated equipment within Rooms
, located at Building 1435, Hanscom AFB, MA 01731.
• SCOPE/OBJECTIVE
• The vendor is expected to inventory the equipment in the B1435 data center, determine the equipment not connected to the primary UPS, and provide a plan to connect the equipment to the primary UPS. All equipment, except those powered by the designated pink circuits, must be connected and supported by the primary UPS.
• The objective is to seamlessly connect the B1435 primary UPS to the existing data center infrastructure while ensuring minimal disruption to ongoing operations, and to complete the on-site installation phase of the project in approximately two (2) weeks.
The contractor shall provide subject matter expertise and support services specific to the EATON platform
• PRE-INSTALLATION REQUIREMENTS
• Prior to execution of contracted work, the contractor shall:
o Provide all proposed work to meet Hanscom Base Civil Engineering (CE) and Communications Division (SC) approval.
o Conduct a load study, a detailed inventory and provide a one-line diagram of every piece of equipment to be placed on UPS power. The load study, inventory and one-line diagram will be provided to the CE project managers for review and approval.
Load study: Perform an UPS electrical load & sizing requirements study to verify UPS integration with Data Center equipment. All findings must ensure NEC compliance and include the following:
Load & Capacity: Perform load calculations and verify UPS capacity against current demand and future spare requirements.
Infrastructure Sizing: Size all UPS feeder conductors and conduits based on calculated amperage and voltage drop.
Overcurrent Protection: Verify ratings and coordination for: UPS Input/Output breakers, Maintenance Bypass/Interlocks, and associated Panelboard Main/Feeder breakers.
o The contractor shall provide a proposal plan focused on minimizing downtime through a phased approach and scheduling any necessary outages or service interruptions during pre-approved, after-duty-hours, including weekends, maintenance windows. The plan should detail the specific procedures for transferring loads (e.g., temporary power, make-before-break switching) to achieve seamless integration.
o The contractor shall coordinate downtime, outages, and service interruptions with CE and SC project managers.
o The contractor shall ensure proper grounding of all servers, breaker boxes, racks and support equipment per regulations within National Electrical Code (NEC), Unified Facilities Criteria (UFC), and Unified Facilities Guide Specifications (UFGS).
The contractor shall reconfigure non-protected power breaker panels to be supported by the Protected Power (PP) infrastructure by connecting the non-protected power breaker panels to the UPS.
o The contractor shall cordon off open flooring to prevent falls; yield to SC personnel if mission access is required.
o The contractor shall maintain clean and orderly work areas daily.
"The contractor shall perform any electrical work requiring a power outage during pre-approved after-duty hours, which are defined as Friday evenings and weekends.
This work must be coordinated with and receive mandatory approvals from CE and SC at least one month in advance, as it impacts the operational data center.
o The contractor shall ensure underfloor equipment is installed at least six inches above grade; use waterproof materials for any whips or feeds requiring floor contact.
o The contractor shall provide the necessary materials to secure all installed components under the raised floor, ensuring that all wiring is elevated and securely attached to the raised floor stilt gridwork. No conductors shall rest directly on the subfloor unless an approved exception is granted.
o The contractor shall paint all receptacles and feed boxes to match the color of their corresponding breaker boxes; revise existing color assignments as needed to maintain unique identification.
o The contractor shall not perform work on, or provide power to, any existing pink colored electrical receptacles within the facility. All existing electrical panelboards (breaker boxes) dedicated to the pink-circuit system are strictly excluded from the scope of this installation.
o If required, the contractor shall acquire and use materials appropriate for securing cables and wires off the concrete subfloor or above the drop ceiling in compliance with applicable code requirements, including those for raised flooring and drop ceiling plenums.
o The contractor shall coordinate with CE and SC prior to any soldering, welding, or spark-producing work; fire alarms will be disabled during these operations.
• All products/equipment must comply with the Buy American Act provisions.
• SUBMITTALS
• The contractor shall provide allsubmittals electronically via DoD Safe. Contractor must request a drop link at least 3 workdays prior to due date.
• SAFETY
• The contractor shall comply with all applicable safety standards and practices, including
OSHA and local regulations. Specific requirements include:
o OSHA Compliance: Adhere to Occupational Safety and Health Administration standards for construction activities, including but not limited to fall protection, electrical safety, and hazard communication.
o Site Safety Plan: Develop and submit a site-specific safety plan to Civil Engineering
(CE) prior to commencement of work.
o Personal Protective Equipment (PPE): Ensure all personnel are equipped with appropriate PPE (hard hats, safety glasses, gloves, hearing protection, respiratory protection as required).
o Fall Protection: Cordon off, open flooring and elevated work areas; provide guardrails, harnesses, or other fall protection systems.
o Fire Safety: Coordinate with CE and SC prior to any soldering, welding, or spark-producing work; disable fire alarms during such operations and restore immediately after.
o Dust and Air Quality Control: Maintain dust generation at an absolute minimum to prevent impact on server equipment and personnel health.
o Hazardous Materials Handling: Follow EPA, OSHA, and state guidelines for testing, handling, and disposal of hazardous materials (lead paint, asbestos, mold, PCBs).
o Emergency Procedures: Establish and communicate emergency response protocols, including evacuation routes, fire suppression, and medical response with the B1435 Facility Managers.
o Training and Awareness: B1435 will provide safety training and daily briefings to all personnel on site.
o Housekeeping: Maintain clean and orderly work areas daily to reduce hazards and ensure safe access.
• MEASUREMENTS AND DESIGNS
• The contractor shall:
o All measurements and specifications shall be verified during the site survey after contract award and prior to design development.
o Document all verified measurements to ensure dimensional accuracy and eliminate conflicts.
o Bring any discrepancies between field conditions and design documents to the immediate attention of the Project Manager.
o Incorporate verified measurements into all design drawings, specifications, and construction documents.
o Ensure final design submissions reflect actual field conditions and are coordinated across architectural, mechanical, electrical, and plumbing disciplines.
• SPECIFIC DESIGN REQUIREMENTS
• Future Growth Capacity o The final connected load shall not exceed 80 percent, per National Electrical Code (NEC) Article 620 critical load calculation, of the UPS's total rated capacity. This ensures the system can accommodate future expansion without immediate upgrades.
• Cost Estimating o Provide a cost estimate with all design submissions. The cost estimate shall mirror the bid schedule.
• TESTING & COMMISSIONING – UPS CONNECTIONS
• The contractor shall perform comprehensive testing and commissioning of all UPS connections to verify redundancy, safety, and operational readiness:
o Testing: Submit a detailed testing plan to CE and SC for approval prior to commissioning activities. Verify that both the main power and the UPS connections support the connected equipment independently. Demonstrate seamless transfer between main power, Automatic Transfer Switch (ATS), UPS, and backup generator without power interruption to mission-critical equipment.
The plan will test the UPS under various load percentages (25%, 50%, 75% of the design load). The contractor must provide a load bank for testing.
Test the UPS management monitoring and alerting.
o Safety Checks: Perform arc flash, grounding, and breaker coordination tests in compliance with NEC and National Fire Protection Association (NFPA) standards.
o Documentation: Provide test results, updated one-line diagrams, and commissioning reports to CE and SC.
o Final Acceptance: Obtain written approval from CE and SC confirming that the UPS data center connections meet all design, safety, and operational requirements.
• SUPPLEMENTAL GUIDES
• National Electrical Code (NEC): https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70
• Unified Facilities Criteria (UFC): https://www.wbdg.org/dod/ufc
• Unified Facilities Guide Specifications (UFGS): https://www.wbdg.org/dod/ufgs
(END OF DOCUMENT)