This is a Questions and Answers document for federal contract solicitation FA283526Q0019 addressing UPS Connections requirements. The document does not specify response dates, award dates, pricing terms, or set-asides, as these details are contained in other solicitation documents.
The Q&A clarifies key project parameters for contractors bidding on UPS connection work. An As-Built one-line drawing exists but cannot be shared for security reasons, and no UPS load study is currently available. The contractor is responsible for creating their own one-line diagram to verify equipment connections. Current system loading is estimated at 2.6 kVA with approximately 77.4 kVA of spare capacity, though the government notes this data requires contractor verification and additional panelboard data will be provided. The contractor must provide all electrical engineering and design services for review and approval by 66 ABG/CE and 66 ABG/SC project managers; stamped engineering drawings are not required. An Arc Flash Study is a Defense Acquisition Framework requirement but is not currently recommended by the government and is structured as an optional, separately-funded CLIN if needed. Previously, the majority of non-pink panelboards were connected to the primary UPS system.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions: Answers:
Is there an existing one-line diagram and current UPS load study available for review?
Yes, an As-Built one-line drawing exists, however for security purposes it cannot be shared. No, an UPS load study is not available.
Approximately how many racks, devices, branch circuits, and panelboards are anticipated to be connected to the primary UPS?
Previously the majority of all the non-pink panelboards were connected to the UPS. The SOW requests the awarded contractor to create their own one-line diagram to verify the equipment to connect is correct.
What is the current loading percentage and available spare capacity of the existing UPS system?
Current estimated Load kVA is 2.6 (Efficieny 82%) leaving an estimated 77.4 kVA of spare capacity. Data to be verified by the contractor. 66 ABG/CE is gathering additional panelboard data to provide later this week.
Are there existing panel schedules and as-built drawings available
Yes, an As-Built one-line drawing exists, however for security purposes it cannot be shared.
Is an Arc Flash Study required as part of this contract, or will it be determined after review?
The Arc Flash Study is a DAF requirement however CE does not recommend it at this time and is an option CLIN to be funded if required.
Is there an engineer of record for this project, or is the contractor expected to provide all electrical engineering and design services?
The contractor is expected to provide all electrical engineering and design services to the 66 ABG/CE and 66 ABG/SC project managers for review and approval.
Will stamped engineering drawings be required for approval?
No, a stamped engineering drawing is not required.