FSN_Flight School Next Process Presentation.pptx
PPTX presentation 2 MB Posted
- Attached to
- U. S. Army Initial Entry Rotary-Wing Flight Training Next Generation – Request For Information (RFI)
- Solicitation number
- Not on record
About this file
This document is a PowerPoint presentation providing an overview of the Flight School Next (FSN) procurement process for the U.S. Army's Initial Entry Rotary-Wing (IERW) Flight Training at Fort Novosel, Alabama.
The presentation outlines the key steps in the procurement planning, market research, and solicitation and award phases. It indicates the Army is considering a Government-Owned, Contractor-Operated (GOCO) or Contractor-Owned, Contractor-Operated (COCO) solution to reduce costs, gain efficiencies, and maintain or increase training quality. The presentation highlights the issuance of a prior Request for Information (RFI) with a Statement of Objectives, which seeks industry input on solutions and methodologies to transform the IERW training program. Responses to the RFI are due by December 6, 2024. The presentation also notes the decision authority rests with the Chief of Staff of the Army, who will determine whether to proceed with a GOCO, COCO, or no-go approach.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Flight School Next (FSN) Process Version Number 1 As of 14NOV2024 Michael A. Metje, Contracting Officer U.S. Army Contracting Command-Redstone Arsenal Distribution Statement A- Approved for public release; distribution is unlimited; as submitted under ACC-RSA Public Release Authorization 2024-.
Procurement Orientation Completion & Closeout – 5 Steps Contract Management – 100’s of Steps Procurement Planning – 3 Steps
Market Research – 14 Steps Solicitation & Award – 25 Steps We are here!
Where in Market Research?
Perform Market Research
Issue RFI with Statement of Objectives
Host Site Visit
Engage with Q&A
Perform IWP Analysis
Complete Independent Government Estimations (IGE)
Submit Draft to legal and USAACE for concurrence
Draft Recommendation to Chief of Staff of the Army
Receive Industry White Papers (IWP) Due: 12/6/24
Compile Market Research Results & IGE
Finalize Recommendation by incorporating changes
Submit to Chief of Staff of the Army (CSA)
Panel Interviews and Committee Meetings
CSA provides decision: GoCo, CoCo, or NoGo
Chief of Staff of the Army Decision
CSA Decision Document
GoCo
CoCo
NoGo
CSA Decision & Contracting Direction
GoCo
USAACE Revises Procurement Plan
ACC-RSA Initiates Acquisition Planning
CoCo
USAACE Revises Procurement Plan
NoGo
FSN Disapproved
Conclude Strategic Planning
What happens next?
FSN Solicitation Process begins 25 Steps
FSN Close-Out
Conclude Strategic Planning
Questions?
michael.a.metje.civ@army.mil
Answers https://sam.gov image13.jpeg image14.png image15.png image16.png image17.png image20.png image21.svg
.MsftOfcThm_Accent2_Fill_v2 { fill:#8AB833;
image1.png image2.png image4.png image5.png image9.png image10.png image11.png
File details come from the government source that posted it. Updated .