FM66 Replace Base Ops Generator B847.xlsx

XLSX spreadsheet 73 KB Posted

Attached to
Replace Base Ops Generator - B847
Solicitation number
FA302225R0006
Issued by

About this file

This document is a Schedule of Material Submittals for a generator replacement project at Columbus Air Force Base. The project (No. EEPZ248379) involves replacing the Base Ops Generator B847, which includes a 120/208V 125 kW Generator, day tank, fuel pump, and Automatic Transfer Switch. The project requires multiple material and environmental submissions across various disciplines, including general, environmental, architectural, civil, mechanical, electrical, and special systems documentation.

Key submission requirements include work/construction plans, as-built drawings, progress schedules, warranties, safety documentation (like Safety Data Sheets), hazardous waste reports, storm water pollution prevention plans, and specific electrical component documentation for the generator, transfer switch, and fuel systems. The solicitation (FA302225R0006) indicates the project is valued between $100,000 and $250,000, with a site visit scheduled for 12 May 2025 and a mandatory registration deadline of 07 May 2025. Contractors must complete CUI training and obtain special access to locked documentation through SAM.gov to participate in the bidding process.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General

Project No:Project Title:Date:
EEPZ248379Replace Base Ops Generator, B84713-Mar-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
1Work/Construction/phasing PlanBASICX
3As-Built DrawingsBASICX
4Progress ScheduleBASICX
5Guarantees and WarrantiesBASICX
6Superintendent's Qualifications and ExperienceBASICX

AF Form 66 (Substitute) GENERAL Page&Pof&N

SCHEDULE OF MATERIAL SUBMITTALS

Environmental

Project No:Project Title:Date:
EEPZ248379Replace Base Ops Generator, B84713-Mar-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
7Appropriate SDSBASIC
8Hazardous waste reportBASIC
9Hazardous Material Report (AF Form 3000)BASIC
10Recycled Material Report/Construction Debris reportBASIC
11Storm Water Pollution Prevention Plan with Best Management Practices IdentifiedBASIC
12Weekly Inspection Reports for ProjectsBASIC
13State Licenses for workers and supervisors (Asbestos)BASIC
14State license for the firm (Asbestos)BASIC
1510 Day Notification (Demolition and Asbestos)BASIC
16Work PlanBASIC
17Copy of ACM DisposalManifestBASIC

AF Form 66 (Substitute) Environmental Page&Pof &N

SCHEDULE OF MATERIAL SUBMITTALS

Architectural

Project No:Project Title:Date:
EEPZ248379Replace Base Ops Generator, B84713-Mar-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
14NONE

AF Form 66 (Substitute) Architectural Page&Pof&N

Civil

Project No:Project Title:Date:
EEPZ248379Replace Base Ops Generator, B84713-Mar-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
NONE

AF Form 66 (Substitute) CIVIL Page&Pof &N

Mechanical

Project No:Project Title:Date:
EEPZ248379Replace Base Ops Generator, B84713-Mar-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
17NONE

AF Form 66 (Substitute) Mechanical Page&Pof&N

Electrical

Project No:Project Title:Date:
EEPZ248379Replace Base Ops Generator, B84713-Mar-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
18GeneratorXXX
19Automatic Transfer SwitchXXX
20Electrical ComponentsXXX
21Day Tank/Fuel PumpXXX

AF Form 66 (Substitute) Electrical Page&Pof &N

Special Systems

Project No:Project Title:Date:
EEPZ248379Replace Base Ops Generator, B84713-Mar-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
26NONE

AF Form 66 (Substitute) Special Systems Page&Pof &N

Other&Misc

Project No:Project Title:Date:
EEPZ248379Replace Base Ops Generator, B84713-Mar-25
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
26Airfield Waiver
Prepared by CE but contractor must supply:
1. Site Plan/Area of Work
2. Type of Equipment to be used
3. Maximum height of equipment
4. Work Hours (24/7, nights, non-flying, etc).
5. Work Schedule

27 Height of equipment on the airfield

AF Form 66 (Substitute) Other and Misc Page&Pof &N

HAZMAT Tracking Sheet

Contractor Hazardous Materials Usage Tracking Form
Return this form to Contracting/Project Manager with Manufacturers original SDS
EEPZ248379Replace Base Ops Generator, B847Contract #
Start Date:End Date:Cotractor:
Product Name as seen on SDS
Process (How is material used)Part #ManufacturerType of
ContainerSize of ContainerTotal

Quantity

UsedEESOH MSN
1
Process:
2
Process:
3
Process:
4
Process:
5
Process:
6
Process:
7
Process:
8
Process:
9
Process:
10
Process:
11
Process:
12
Process:
13
Process:
14
Process:
15
Process:
16
Process:
17
Process:
18
Process:
19
Process:
20
Process:
21
Process:
22
Process:
23
Process:
24
Process:
25
Process:
26
Process:
27
Process:
28
Process:

File details come from the government source that posted it. Updated .