RFIs Master B847 Replace Base Ops Generator Answers.pdf
PDF 62 KB Posted
- Attached to
- Replace Base Ops Generator - B847
- Solicitation number
- FA302225R0006
About this file
This document is a Request for Information (RFI) for the B847 Replace Base Ops Generator project at Columbus Air Force Base, Solicitation #FA302225R0006. The RFI contains 21 detailed questions and answers addressing critical aspects of the generator replacement project, including project requirements, technical specifications, and logistical considerations.
Key details include the requirement to replace a 120/208V 125 kW Generator, day tank, fuel pump, and Automatic Transfer Switch, with specific stipulations such as mandatory separate supervision and QAQC roles, underground fuel piping outside the equipment yard, and coordination of generator downtime with the government. Electrical engineering requirements include certification of electrical load studies by a licensed electrical engineer, with the contractor responsible for tests per UFC 3-540-01 and manufacturer specifications. The existing generator will be salvaged and relocated within the base, and all work must be coordinated in advance, with power interruptions limited to after-hours or weekends. The project is valued between $100,000 and $250,000 and requires contractors to complete CUI training and obtain special document access.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA302225R00060001 SF 30.pdf | ||
| RFIs Master B847 Replace Base Ops Generator _ Answers.pdf | ||
| Contractors CUI Training Slides.pptx | PPTX presentation | |
| MFR Contractor CUI Training Acknowledgment for Solicitations.pdf | ||
| Wage Determination DBA MS20250045.pdf | ||
| EAL Form.docx | DOCX document | |
| FM66 Replace Base Ops Generator B847.xlsx | XLSX spreadsheet | |
| Solicitation - FA302225R0006.pdf | ||
| Design Build SOW EEPZ248379 Replace Base Ops Generator B847.pdf | ||
| Appendix A - Cost Breakdown.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFIs – B847 Replace Base Ops Generator Solicitation #FA302225R0006
1. In executing this project, can one superintendent fulfill the supervision, safety, and QAQC roles?
Supervision and QAQC roles must be two separate individuals.
2. Are contractors required to issue a contract specific QA/QC Plan?
No.
3. Are contractors required to issue a contract specific Safety Plan?
No.
4. Is this project tax exempt?
No.
5. Will a polishing system be required for the generator fuel system?
No, however old fuel will be drained from storage tank. The contractor shall provide new fuel for testing the generator and refill storage tank before turn over to government.
6. Does CAFB have any base specific requirements which exceed the sound attenuation requirements for the generator enclosure found in the UFCs?
No.
7. Will emergency temporary backup power will be required during the construction phase, specifically during the period between the demolition of the existing generator and the installation and commissioning of the new generator?
No, however generator down time will have to be coordinated in advance with the government.
8. It is assumed the existing generator foundation is sized properly and has the capacity to support the new generator. Please confirm. Yes
9. Can the new generator be installed outside of the existing equipment yard?
No.
10. If the existing fuel piping cannot be reused, can the AFB confirm whether the new fuel piping is required to follow the same underground routing as the existing design, or if an above-ground routing alternative would be acceptable?
Underground piping must be used outside of the equipment yard.
11. Concerning the electrical load study cited in the SOO: Must the study be surveyed, performed, and certified by a licensed electrical engineer?
It must be certified by a licensed electrical engineer.
12. Will either an Electrical Coordination Study or Protective Device Coordination Study be required for this project, and if so, must they be performed and certified by a licensed electrical engineer?
RFIs – B847 Replace Base Ops Generator Solicitation #FA302225R0006
The contractor will be responsible for tests required in UFC 3-540-01 and the manufacturer.
13. Will a Short Circuit Analysis is required for this project, and if so, must it be performed and certified by a licensed electrical engineer?
The contractor will be responsible for tests required in UFC 3-540-01 and the manufacturer.
14. Will an Arc Flash Study be required for this project, and if so, must it be performed and certified by a licensed electrical engineer?
The contractor will be responsible for tests required in UFC 3-540-01 and the manufacturer.
15. If any of the previously mentioned studies are required, is ETAP software acceptable?
Follow UFC and manufacturer requirements for required testing.
16. Existing Generator is to be salvaged and relocated elsewhere on the base. Is the existing generator in working order, or is the building currently without emergency power?
Existing generator is in working order.
17. Must the existing generator fluids (crankcase oil and fuel) be drained prior to transporting genset on base?
Yes.
18. Existing conductors to/from existing generator, existing automatic transfer switch, and existing power panel are in working order, sized properly, and can be reused.
Please confirm.
Refer to SOW 2.2.2 and 2.2.3
19. Is a Geotechnical report for the area available? If so, can it be provided?
There is no geotechnical report available.
20. 2.2.4 Demolish the existing day tank and fuel pump. Is this the tank beside the generator or the larger holding tank?
The tank beside the generator.
21. 2.2.5 Due to the critical nature of the facility interruptions to power shall only during afterhours or on weekends. This work shall be coordinated with the Government in advance. Can this building be without a backup generator power during the week (5 days) to allow cleanup and removal of old transfer switch and components? Normal power will be available during this time.
Yes, however generator down time will have to be coordinated in advance with the government.