FDEP_Approval_DW0302J_Plans_and_Specs_Review_Checklist_tlo_evm.pdf
PDF 364 KB Posted
- Solicitation number
- 26-35
- Issued by
- Bay County, Florida
About this file
This is a Drinking Water Plans and Specifications Review Checklist prepared by the Florida Department of Environmental Protection (FDEP) for Bay County's Water Treatment Plant (WTP) Resiliency Project. The project involves the installation of new filters and appurtenances for the existing water treatment plant located at 3400 Transmitter Road, Panama City, Florida. Specifically, the work includes construction of three (3) additional sand gravity type filters at the facility. The contract submission deadline is 2:00 pm on Thursday, June 4, 2026, with public opening of submissions to follow immediately. The project completion time is specified as 432 days. The checklist confirms that all required permits, including environmental permits and Army Corps of Engineers permits, have been received, though the selected contractor will be responsible for providing any remaining permits. All work is contained within the existing county-owned site.
This project represents the final phase of an already-approved loan agreement and is funded through grant sources. The FDEP review confirms that the design documents contain no ineligible items, are consistent with planning documentation recommendations, and include the most current FDEP Supplementary Conditions. The contract specifications clearly define formal advertising and bid opening procedures, bid evaluation methods including additives and deducts, "or equal" clauses for equipment and materials, bond requirements for bidding and performance, and procedures for issuing changes to bidding and contract documents. The checklist was approved on April 17, 2026, by Project Manager Timothy L. Owens and Program Administrator Eric V. Meyers, with an effective date of December 2025.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRINKING WATER PLANS & SPECIFICATIONS REVIEW CHECKLIST
Project Sponsor:
Contract Title:
Brief summary of contract work:
Project Number:
Contract #:
Have plans & specifications been previously accepted? If “Yes” list contract Yes No title and effective date of acceptance below.
Title: Date:
The basis for this checklist is Rule 62-552.700, F.A.C. The questions below are used to verify that the plans and specifications prepared for competitive bidding meet program requirements.
1. Is the project sponsor requesting construction funding at the next priority list meeting? Explain.
Yes No Comments:
2. Is the work described consistent with the planning documentation recommendations?
Yes No If "No" describe the inconsistency and how it was resolved:
3. Do the design documents include any ineligible items? Yes No N/A
If "Yes," briefly describe and list the ineligible items:
4. Has the ineligible work been noted as ineligible in the database? Yes N/A
5. Is the work described consistent with environmental mitigation as recommended in the Department's environmental information document? Yes Mitigation is not an issue
6. During the administrative review, has anything come to the reviewer's attention to indicate the documents are too incomplete to competitively bid the contract work or procure equipment/materials as appropriate? Yes No
7. Do the contract specifications include the requirements of the most current FDEP Supplementary Conditions, as appropriate? Yes No If No, Please explain:
8a. Has the construction permit been received? If No, then provide an explanation.
Form Revised 1-19-24 by GCA
8b. Has the Site Certification been received? If No, then provide an explanation. Yes No
a. Formal advertising and bid opening procedures? Yes
b. Method of bid evaluation; including bid item additives, deducts and contract award? Yes
c. Comprehensive (or individual) "or equal" c1 lause(s) for equipment and materials? Yes days.
Yes No
10. Are the following clearly specified?
9. The completion time for the contract is
DRINKING WATER PLANS & SPECIFICATIONS REVIEW CHECKLIST
No
Yes
11. Will the project sponsor use a pre-qualified list in acquiring goods and services? Yes
If “Yes,” is the pre-qualified list current and does it include enough qualified sources to ensure maximum open and free competition? Yes N/A
12. Are bonds (or equivalent) required for bids and contract performance and payment of suppliers, subcontractors and workmen? Yes
13. Are the procedures for issuing changes to the bidding and contract documents clearly stated?
14. Has the contract information been entered into the database? Yes
15. Is the acceptance letter included with this checklist? Yes
ACCEPTANCE:
Project Manager
Effective Date Program
Administrator
Form Revised 1-19-24 by GCA
| Project Sponsor: Bay County | |
| Project Number: DW0302J | |
| Contract Title: Water Treatment Plant Resiliency Project | |
| Contract: 1 | |
| Check Box1: Yes | |
| Check Box2: Off | |
| Check Box5: Yes | |
| Check Box6: Off | |
| Check Box7: Yes | |
| Check Box8: Off | |
| Check Box9: Off | |
| Check Box10: Yes | |
| Check Box11: Off | |
| Check Box12: Off | |
| Check Box13: Yes | |
| Check Box14: Yes | |
| Check Box15: Off | |
| Check Box16: Off | |
| Check Box17: Yes | |
| Check Box18: Yes | |
| Check Box19: Off | |
| Title: Water Treatment Plant Resiliency Project | |
| Comment on Authorization to Incur Construction Costs: This is an already approved loan agreement, this is the final project associated with the grant | |
| Description of Inconsistancy: | |
| Comment on Supplementary Conditions: | |
| Competion time for contract: 432 | |
| Date_es_:signer:date: 04/17/2026 | |
| Ineligible items: | |
| P: | |
| E: | |
| 2026-04-17T10:38:38-0400 | |
| Timothy L. Owens |
| 2026-04-17T11:36:48-0400 | |
| Eric V. Meyers |
| Check Box25: Off |
| Check Box26: Yes |
| Check Box27: Off |
| Check Box28: Yes |
| Check Box29: Yes |
| Check Box35: Yes |
| Check Box36: Yes |
| Check Box38: Yes |
| Date1_es_:signer:date: 12/2025 |
| Check Box20: Yes |
| Check Box21: Off |
| Text2: Environmental permit and ACOE permit has been received, the contractor once selected will have to provide any remaining permits |
| Text3: All work is contained within the existing county owned site. |
| Check Box4: Off |
| Check Box22: Yes |
| Check Box23: Yes |
| Check Box24: Yes |
| Check Box30: Yes |
| Text31: Installation of new filters and appurtenances for existing water treatment plant |