NM-AZ_PBR_Final_RFP_Q A_041713.doc
DOC document 28 KB Posted
- Solicitation number
- FA8903-12-R-0050
About this file
Additional Q As
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NM-AZ_PBR_Final_RFP_Q As_041613.doc | DOC document | |
| NM-AZ_PBR_Final_RFP_Q As.doc | DOC document | |
| FA8903-12-R-0050_0001.pdf | ||
| QA_2Apr2013.docx | DOCX document | |
| QA_4Apr2013.docx | DOCX document | |
| NM-AZ_PBR_Atch_1_SOO_Revision_1_DRAFT_-_03_Apr_13.doc | DOC document | |
| QA_2Apr2013.docx | DOCX document | |
| Attachment_L-3_Past_Performance_Questionnaire.doc | DOC document | |
| Attachment_L-6_CLIN_MPS_IMS_Guidance_Template_and_SubCLIN_Structure_NM-AZ_PBR_19_Mar_13.doc | DOC document | |
| NM-AZ_PBR_Final_SECTION_M_Evaluation_Criteria_11_Mar_13.doc | DOC document | |
| Attachment_L-4_Subcontractor_Consent_Letter_Sample.doc | DOC document | |
| NM-AZ_PBR_Final_RFP_28_Mar_2013.pdf | ||
| RFP_FA8903-12-R-0050_Sched_B_-_Word_Doc.doc | DOC document | |
| Attachment_L-2_MilestonePaymentSchedule_with_price_19_Mar_13.xls | XLS spreadsheet | |
| Attachment_L-5_Client_Authorization_Letter_Sample_NM-AZ.doc | DOC document | |
| Attachment_L-1_MilestonePaymentSchedule_without_price.xls | XLS spreadsheet |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NM-AZ PBR Final RFP Question submitted 17 April 2013:
On 15 April, the Government stated:
The MPO for three (3) of the sites have been revised and the time lengthened in which the contractor will have to achieve the MPOs. Five (5) of the MMRP sites will remain at an MPO of SC, but they will now have 5 years to achieve the MPO. Three (3) of the MMRP sites will change to an MPO of RC, but they will now have 7 years to achieve the MPO; these 3 sites are the ones with the largest acreage and more munitions to address.
This is a summary of four of the MMRP sites:
Site CSE Ph II Acreage MPO
FI 857 0.8 Acres RC within 7years
ML 866 1350.4 Acres RC within 7 years
SR 867 449.2 Acres RC within 7 years
XU 853 204.5 Acres SC within 5 years
Simply put-would the Government consider changing MPO for XU 853 to RC within 7 years since it appears the intent was to address the larger sites?
Government Response: The prior changes to MPO for sites identified above were based on recommendations from the AFCEC MMRP QA Panel. The MPO will remain as stated.
Further, yesterday's Q&A stated additional soil sampling at Cannon AFB Site FL070 is part of the NM-AZ PBR. Previous Q&A had indicated North Wind would complete all outstanding field work. Would a one week extension be considered to adequately price this new requirement?
Government Response: No extensions will be granted.