FA8903-12-R-0031
Attachment 2
FA8903-12-R-0050
Attachment L-6
Contract Line Item Number (CLIN) Structures/
Milestone Payment Schedules (MPS)/Integrated Master Schedules (IMS) Guidance This guidance is being provided to communicate Air Force expectations for the development of CLIN/SubCLIN Structures and the correlation with the subsequent development of the MPS and the IMS. This guidance is not intended to remove Contractor flexibility. The examples provided are for illustrative purposes only and are not intended to be inclusive of all acceptable approaches.
When annual Congressional appropriations provide the basis for sourcing these contracts, special consideration must be given to ensure compliance with funding rules concerning period of availability, bona fide need and purpose as they relate to each year of funding applied. This will ensure milestones are developed that support fiscally responsible use of funds. To ensure compliance when establishing milestones, any contingent events that affect the beginning date of any milestone must be considered. Key to proper use of funds in this context is non-severability. A non-severable deliverable is defined as a deliverable item that represents a single end product or undertaking, entire in its nature, that cannot be feasibly subdivided into discrete elements or phases without losing its identity. Milestones must have a clear delineation of final deliverables, as distinct non-severable options to be fully funded in the fiscal year in which the award of the SubCLIN is made, even though the performance may extend into future fiscal years. There is no administrative reservation of funds whatsoever until a determination is made to exercise a separate and non-severable SubCLIN. Each non-severable SubCLIN will be funded in its entirety with funds current at the time the SubCLIN is exercised, and any need for prior year funds in the future will be clearly tied back to the specific non-severable SubCLIN and associated well-defined requirement(s) and associated deliverable(s).
CLIN AND SUBCLIN STRUCTURE:
SubCLINs provide a means for funding economically or programmatically viable stages by identifying the items or activities to be acquired as non-severable contract deliverables (performance objectives). SubCLINs shall provide a firm fixed price for separately identifiable contract deliverables (performance objectives). Each SubCLIN shall have its own performance objective expressly stated. SubCLINs should identify remediation objectives or activities that relate directly to, and are an integral part of, the CLIN. For example:
· Achieve [performance objective] for [site number(s)]
SubCLIN prices and completion dates must not exceed the value or completion date of the CLIN. SubCLINs cannot be partially exercised and must be fully funded when exercised in order to avoid violations of the Anti-Deficiency Act. The use of SubCLINs provides the Air Force with the flexibility to match options to be exercised with available funding as the amount of available program funding is sometimes unpredictable. The Air Force may restructure the SubCLINs with the Apparent Successful Offeror based upon the submitted MPS.
MILESTONE PAYMENT SCHEDULE:
The Contractor shall propose milestone payments as part of the MPS in its proposal. The Air Force intends to use the Contractor’s proposed MPS to restructure SubCLINs, if necessary, to align with projected available funding prior to award. The MPS shall also be included as part of the Project Management Plan (PMP). The MPS is not included in the contract and is not considered final with award of the contract. Changes made to the MPS prior to award are used to finalize the SubCLINs, therefore, award of the contract does not equate to final acceptance of the MPS. The MPS will be negotiated during development of the PMP and may require additional changes.
Milestone payments shall be based on the completion of a definable and measurable step considered integral and necessary to the achievement of the performance objective/SubCLIN. Completion of milestones shall demonstrate payment is appropriate. Milestone payments shall include the approval requirements in accordance with the performance standards in Table 1 of the Statement of Objectives (SOO) and the requirements of the regulatory structure. Terms of acceptance of milestone payments will be negotiated during development of the PMP.
A consolidation of completed milestone payments is to be submitted monthly, however milestone payments shall not represent a “progress” payment or a “monthly” payment for level of effort expended. In addition, milestone payments shall not include management or overhead type costs (program/project management, monthly reporting, mobilization/demobilization, etc.) that do not provide measurable project advancement. For any performance objective, a milestone payment shall be for completion of a definable and measurable point considered integral and necessary to completion of the performance objective. For example, if the performance objective is to achieve Remedy-in-Place (RIP) and the work required to achieve RIP includes Feasibility Study (FS), Proposed Plan (PP), Record of Decision (ROD), Remedial Design (RD), and Remedial Action (RA), then potential interim milestone payments could be:
· Air Force approval of Draft FS;
· Air Force and Regulator approval of Final FS;
· Air Force approval of Draft PP;
· Air Force and Regulator approval of Final PP;
· Air Force approval of Draft ROD;
· Air Force and Regulator approval of Final ROD;
· Air Force approval of Draft Remedial Action Work Plan (RAWP)/RD;
· Air Force and Regulator approval of Final RAWP/RD;
· Air Force approval of Remedial Action Completion Report (RACR);
· Air Force and Regulator approval of Final RACR signifying achievement of RIP.
Contractor proposed milestone payments for Air Force approval of draft documents require sufficient funds to remain associated with the final document to ensure completion of the performance objective. Milestone payments shall not exceed 80% of the total payment for that SubCLIN prior to achievement of the final deliverable (performance objective). The SubCLIN’s final deliverable may include the combination of the draft and final versions. The final SubCLIN milestone for each site must be a minimum of 20% of the total SubCLIN cost. Air Force acceptance of Contractor proposed draft milestones, or the proposed percentage of the milestone payment as compared to the total payment for that SubCLIN, is discretionary and negotiated on a case-by-case basis between the Air Force and selected Offeror. These negotiations may occur prior to award and/or during development of the PMP.
The Air Force will use performance indicators and performance models in addition to the PMP to establish and execute a Surveillance Plan. The Surveillance Plan will highlight key quality control activities or events. The Contracting Officer’s Representative (COR) will use the Surveillance Plan to determine when Air Force (COR and/or Contracting Officer (CO)) surveillance activities can be conducted to assess progress toward and/or completion of milestone payments.
INTEGRATED MASTER SCHEDULE:
The Contractor shall prepare and submit an activity-based IMS that is consistent with the MPS. The Contractor must include and identify all performance milestones at the appropriate level of detail and logically sequenced to support and manage achievement of the proposed performance objectives. The IMS shall identify completion of the performance objectives in the time designated and shall include identification of any critical path items. The IMS shall include incorporation of Air Force and Regulatory review periods for deliverables while meeting or exceeding any applicable agreements or regulatory schedule requirements.
Sites associated with each milestone/task must be noted in the schedules using the Site IDs and referencing all site aliases noted in Table 1 of the SOO. The schedule shall be provided in hardcopy and electronic format consistent/compatible with Air Force software, currently Microsoft( Project, Microsoft( Excel, and in Adobe Acrobat portable document file (.pdf). Updated and revised schedules shall be submitted with monthly status reports with changes clearly identified by the Contractor.
An example illustrating the progression of CLIN/SubCLIN Structure to MPS and IMS follows:
EXAMPLE CLIN/SUBCLIN STRUCTURE
(Air Force approval required prior to Contract Award)
CLIN/
SUBCLIN
| CLIN/SUBCLIN/MILESTONE PAYMENT DESCRIPTION |
| CLIN/ |
SUBCLIN AMOUNT
PROJECTED EXERCISE DATE OR RATIONALE
| 0001 |
| Project Management Plan (PMP) |
| $0 |
| 0001AA |
| Preliminary Project Management Plan in accordance with Table 1 of the SOO |
| $25,000 |
| At Award |
| 0001AB |
| Final Project Management Plan in accordance with Table 1 of the SOO |
| $25,000 |
| Approx 4.5 years from 0001AA or upon CO determination of bona fide need |
| 0002 |
| LF002 - LANDFILL NO. 2: Achieve RIP |
| $200,000 |
| At Award |
EXAMPLE MILESTONE PAYMENT SCHEDULE
(Negotiated between the Air Force and the selected Offeror and approved by the Air Force)
CLIN/
SUBCLIN
| CLIN/SUBCLIN/MILESTONE PAYMENT DESCRIPTION |
| CLIN/ |
SUBCLIN AMOUNT
| MILESTONE PAYMENT AMOUNT |
| MILESTONE PERCENT |
| 0001 |
| Project Management Plan (PMP) |
| $0 |
| 0001AA |
| Preliminary Project Management Plan in accordance with Table 1 of the SOO |
| $25,000 |
| $25,000 |
| 0001AB |
| Final Project Management Plan in accordance with Table 1 of the SOO |
| $25,000 |
| $25,000 |
| 0002 |
| LF002 - LANDFILL NO. 2 |
| $200,000 |
| 0002AA |
| Air Force Approval of Draft FS |
| 0002AB |
| Air Force and Regulatory Approval of Final FS |
| 0002AC |
| Air Force Approval of Draft ROD |
| 0002AD |
| Air Force and Regulatory Approval of Final ROD |
| 0002AE |
| Air Force Approval of Draft Remedial Action Work Plan/Remedial Design |
| 0002AF |
| Air Force and Regulatory Approval of Final Remedial Action Work Plan/Remedial Design |
| 0002AG |
| Air Force Approval of Draft RACR |
| 0002AH |
| Air Force and Regulatory Approval of Final RACR signifying achievement of RIP |
Note: Payment milestone ranges could be as low as 60%; but shall not exceed 80% of the total payment for the CLIN/SubCLIN prior to achievement of the final deliverable. In the example above, 80% of $200,000 = $160,000; therefore, RACR (draft + final) = $40,000 or 20% of the CLIN 0002. Air Force approval of the "Draft" is defined as Contractor resolution of Air Force comments on the Draft deliverable.
EXAMPLE Integrated Master Schedule (Air Force approval required as part of the PMP)
| Activity ID# |
| ACTIVITY DESCRIPTION |
| DURATION |
| START |
| FINISH |
| 0001 |
| Contract Award |
| 1 day |
| 1 OCT 10 |
| 1 OCT 10 |
| 0001AA0001 |
| Kick Off Meeting |
| 1 day |
| 15 OCT 10 |
| 15 OCT 10 |
| 0001AA0002 |
| Prepare Preliminary PMP |
| 30 days |
| 1 OCT 10 |
| 31 OCT 10 |
| 0001AA0003QA |
| Air Force Review of Draft Preliminary PMP |
| 30 days |
| 1 NOV 10 |
| 1 DEC 10 |
| 0001AA0004PM |
| Air Force Approval of Final Preliminary PMP |
| 1 day |
| 1 DEC 10 |
| 1 DEC 10 |
Note: Air Force surveillance activities precede all milestone payments.
| CLIN |
| SUBCLIN |
| CLIN/SUBCLIN DESCRIPTION |
| **PROJECTED DATE OF EXERCISE |
| CLIN/SUBCLIN AMOUNT |
Project Management Plan (PMP)
$0
| 0001AA |
| Preliminary Project Management Plan in accordance with Table 1 of the SOO |
| At Award |
| 0001AB |
| Final Project Management Plan in accordance with Table 1 of the SOO |
| Approx 4.5 years from 0001AA or upon CO determination of bona fide need |
Cannon Air Force Base
LF002 - LANDFILL NO. 2
| 0002AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0002AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0002AA or upon CO determination of bona fide need |
| 0002AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0002AB or upon CO determination of bona fide need |
| 0002AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0002AC or upon CO determination of bona fide need |
SW002 - Recovered tank no. 108
| 0003AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0003AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0003AA or upon CO determination of bona fide need |
| 0003AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0003AB or upon CO determination of bona fide need |
| 0003AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0003AC or upon CO determination of bona fide need |
LF003 - Landfill No. 3 -- LTM
| 0004AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0004AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0004AA or upon CO determination of bona fide need |
| 0004AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0004AB or upon CO determination of bona fide need |
| 0004AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0004AC or upon CO determination of bona fide need |
LF004 - Landfill No. 4 -- LTM
| 0005AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0005AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0005AA or upon CO determination of bona fide need |
| 0005AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0005AB or upon CO determination of bona fide need |
| 0005AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0005AC or upon CO determination of bona fide need |
SW004 - Recovered tank no. 121
| 0006AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0006AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0006AA or upon CO determination of bona fide need |
| 0006AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0006AB or upon CO determination of bona fide need |
| 0006AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0006AC or upon CO determination of bona fide need |
LF005 - Landfill No. 5, cell 3
| 0007AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0007AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0007AA or upon CO determination of bona fide need |
| 0007AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0007AB or upon CO determination of bona fide need |
| 0007AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0007AC or upon CO determination of bona fide need |
FT006 - Fire Training Area No. 1
| 0008AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0008AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0008AA or upon CO determination of bona fide need |
| 0008AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0008AB or upon CO determination of bona fide need |
| 0008AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0008AC or upon CO determination of bona fide need |
SW006 - POL tank no. 129
| 0009AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0009AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0009AA or upon CO determination of bona fide need |
| 0009AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0009AB or upon CO determination of bona fide need |
| 0009AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0009AC or upon CO determination of bona fide need |
SD012 - Stormwater collection point (South Playa)
| 0010AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0010AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0010AA or upon CO determination of bona fide need |
| 0010AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0010AB or upon CO determination of bona fide need |
| 0010AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0010AC or upon CO determination of bona fide need |
SD015 - AGE drainage ditch
| 0011AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0011AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0011AA or upon CO determination of bona fide need |
| 0011AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0011AB or upon CO determination of bona fide need |
| 0011AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0011AC or upon CO determination of bona fide need |
SD017 - Old entimology rinse area
| 0012AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0012AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0012AA or upon CO determination of bona fide need |
| 0012AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0012AB or upon CO determination of bona fide need |
| 0012AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0012AC or upon CO determination of bona fide need |
SD020 - NE stormwater drainage area
| 0013AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0013AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0013AA or upon CO determination of bona fide need |
| 0013AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0013AB or upon CO determination of bona fide need |
| 0013AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0013AC or upon CO determination of bona fide need |
SD022 - Storm water drainage & retention pond on GC
| 0014AA |
| Achieve approved RFI within three (3) years from NTP |
| At Award |
LF025 - Landfill 25, Concrete rubble pile -- LTM
| 0015AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0015AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0015AA or upon CO determination of bona fide need |
| 0015AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0015AB or upon CO determination of bona fide need |
| 0015AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0015AC or upon CO determination of bona fide need |
MY031 - AGE maintenance shop pad
| 0016AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0016AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0016AA or upon CO determination of bona fide need |
| 0016AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0016AB or upon CO determination of bona fide need |
| 0016AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0016AC or upon CO determination of bona fide need |
DP036 - MWR Body Shop
| 0017AA |
| Achieve RC within three (3) years from NTP |
| At Award |
FL070 - Oil/water separator and leach field 326
| 0018AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0018AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0018AA or upon CO determination of bona fide need |
| 0018AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0018AB or upon CO determination of bona fide need |
| 0018AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0018AC or upon CO determination of bona fide need |
TU071 - Recovered JP-4 fuel tank no. 390
| 0019AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0019AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0019AA or upon CO determination of bona fide need |
| 0019AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0019AB or upon CO determination of bona fide need |
| 0019AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0019AC or upon CO determination of bona fide need |
SI101 - Wastewater treatment system - lagoons 1&2
| 0020AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0020AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0020AA or upon CO determination of bona fide need |
| 0020AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0020AB or upon CO determination of bona fide need |
| 0020AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0020AC or upon CO determination of bona fide need |
WL102 - Wastewater treatment effluent discharge
| 0021AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0021AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0021AA or upon CO determination of bona fide need |
| 0021AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0021AB or upon CO determination of bona fide need |
| 0021AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0021AC or upon CO determination of bona fide need |
AT109 - Fire Training Area
| 0022AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
AT110 - Underground waste oil tank no. 2336 (FTA-4)
| 0023AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
SW111 - Unlined pit (used with SWMU 109) (FTA-4)
| 0024AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
SW112 - Oil/water separator no. 2336 (FTA-4)
| 0025AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
TU126 - Inactive underground storage tank 3
| 0026AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0026AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0026AA or upon CO determination of bona fide need |
| 0026AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0026AB or upon CO determination of bona fide need |
| 0026AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0026AC or upon CO determination of bona fide need |
SW127/128 - Oil/water separator near tank 4095 (#1)
| 0027AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0027AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0027AA or upon CO determination of bona fide need |
| 0027AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0027AB or upon CO determination of bona fide need |
| 0027AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0027AC or upon CO determination of bona fide need |
TA129 - Waste oil storage facility 244- formerly AOC I
| 0028AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0028AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0028AA or upon CO determination of bona fide need |
| 0028AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0028AB or upon CO determination of bona fide need |
| 0028AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0028AC or upon CO determination of bona fide need |
SS501 - Former AGE Dispatch Facility spills
| 0029AA |
| Achieve approved RFI within three (3) years from NTP |
| At Award |
TU502 - Former Gas Stations USTs
| 0030AA |
| Achieve approved RFI within three (3) years from NTP |
| At Award |
TU503 - Base Support/ Operations Generator Former UST
| 0031AA |
| Achieve approved RFI within three (3) years from NTP |
| At Award |
TU504 - Hospital Abandoned UST
| 0032AA |
| Achieve approved RFI within three (3) years from NTP |
| At Award |
TU505 - Flightline Generator USTs
| 0033AA |
| Achieve approved RFI within three (3) years from NTP |
| At Award |
SS507 - POL Yard Refueling Area
| 0034AA |
| Achieve approved RFI within three (3) years from NTP |
| At Award |
DA508 - Surface Disposal Area
| 0035AA |
| Achieve approved RFI within three (3) years from NTP |
| At Award |
TS835 - Former Skeet Range(VCA)
| 0036AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
Holloman AFB
SS013 - Sodium Arsenite Spill Area
| 0037AA |
| Achieve Site Closeout (SC) within two (2) years from NTP |
| At Award |
OT014 - Former Entemology Shop Area
| 0038AA |
| Achieve Site Closeout (SC) within two (2) years from NTP |
| At Award |
SS017 - BX Gas Station Fuel Spill
| 0039AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0039AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0039AA or upon CO determination of bona fide need |
| 0039AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0039AB or upon CO determination of bona fide need |
| 0039AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0039AC or upon CO determination of bona fide need |
SS018 - Chromic Acid Spill Site
| 0040AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0040AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0040AA or upon CO determination of bona fide need |
| 0040AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0040AB or upon CO determination of bona fide need |
| 0040AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0040AC or upon CO determination of bona fide need |
SD027 - PAD 9 Washrack Area - Rad Waste
| 0041AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
LF029 - Old Army Landfill
| 0042AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0042AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0042AA or upon CO determination of bona fide need |
| 0042AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0042AB or upon CO determination of bona fide need |
| 0042AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0042AC or upon CO determination of bona fide need |
DP030 - Grease Trap Disposal Pits
| 0043AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0043AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0043AA or upon CO determination of bona fide need |
| 0043AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0043AB or upon CO determination of bona fide need |
| 0043AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0043AC or upon CO determination of bona fide need |
OT032 - Former Primate Research Area
| 0044AA |
| Achieve Site Closeout (SC) within two (2) years from NTP |
| At Award |
SD033 - Cooking Grease Disposal Trench
| 0045AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0045AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0045AA or upon CO determination of bona fide need |
| 0045AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0045AB or upon CO determination of bona fide need |
| 0045AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0045AC or upon CO determination of bona fide need |
OT037 - Early Missile Testing Site
| 0046AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
OT038 - Test Sled Maintenance Area
| 0047AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
SS039 - Missile Fuel Spill Area
| 0048AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0048AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0048AA or upon CO determination of bona fide need |
| 0048AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0048AB or upon CO determination of bona fide need |
| 0048AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0048AC or upon CO determination of bona fide need |
RW042 - Radioactive Waste Disposal Area
| 0049AA |
| Achieve Site Closeout (SC) within two (2) years from NTP |
| At Award |
SS065 - Test Cell Surface Spill
| 0050AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
SS067 - Spill and Sand Blasting Residuals Area
| 0051AA |
| Achieve Site Closeout (SC) within two (2) years from NTP |
| At Award |
SS069 - Flightline Fuel Spill Area
| 0052AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
TU503 - Building 221
| 0053AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
TU506 - Building 901
| 0054AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
TU508 - Building 298
| 0055AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
TU515 - Building 889
| 0056AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
TU518 - UST 7003
| 0057AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
TU904 - Building 1194
| 0058AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0058AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0058AA or upon CO determination of bona fide need |
| 0058AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0058AB or upon CO determination of bona fide need |
| 0058AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0058AC or upon CO determination of bona fide need |
OD20K - 20,000 Pound Open Detonation Unit
| 0059AA |
| Achieve Response Complete (RC) within five (5) years from NTP |
| At Award |
OW967 - SWMU 20 (Within T-38 Site)
| 0060AA |
| Achieve Response Complete (RC) within seven (7) years from NTP |
| At Award |
OW968 - SWMU 19 (Within T-38 Site)
| 0061AA |
| Achieve Response Complete (RC) within seven (7) years from NTP |
| At Award |
SS059, SS524 - T-38 Test Cell (SWMU 229)
| 0062AA |
| Achieve Response Complete (RC) within seven (7) years from NTP |
| At Award |
TS851 - Former Skeet Range
| 0063AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
XU853 - Missle Test Stands Area
| 0064AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
XU854 - Able 51 Area
| 0065AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
FI857 - Former Bunker
| 0066AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
SR858 - Former Small Arms Range
| 0067AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
SR859 - Former Skeet Range
| 0068AA |
| Achieve an approved RI Report within three (3) years from NTP |
| At Award |
TS862 - Jeep Target Area Skeet Range
| 0069AA |
| Achieve an approved RI Report within three (3) years from NTP |
| At Award |
SR863 - 1000 Inch Range
| 0070AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
SR864 - Poorman Range
| 0071AA |
| Achieve an approved RI Report within three (3) years from NTP |
| At Award |
ML865 - Ballistics Rain Field
| 0072AA |
| Achieve an approved RI Report within three (3) years from NTP |
| At Award |
ML866 - Former Bombing Range
| 0073AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
SR867 - Possible Firing Range
| 0074AA |
| Achieve Site Closeout (SC) within three (3) years from NTP |
| At Award |
RR869 - Debris Field
| 0075AA |
| Achieve an approved RI Report within three (3) years from NTP |
| At Award |
Kirtland AFB
LF001 - Landfill No 1,
| 0076AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0076AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0076AA or upon CO determination of bona fide need |
| 0076AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0076AB or upon CO determination of bona fide need |
| 0076AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0076AC or upon CO determination of bona fide need |
LF002 - Landfill No 2
| 0077AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0077AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0077AA or upon CO determination of bona fide need |
| 0077AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0077AB or upon CO determination of bona fide need |
| 0077AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0077AC or upon CO determination of bona fide need |
LF008 - Landfill No. 4, 5, & 6
| 0078AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0078AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0078AA or upon CO determination of bona fide need |
| 0078AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0078AB or upon CO determination of bona fide need |
| 0078AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0078AC or upon CO determination of bona fide need |
WP026 - Base Sewage Lagoons and Golf Course Ponds
| 0079AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0079AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0079AA or upon CO determination of bona fide need |
| 0079AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0079AB or upon CO determination of bona fide need |
| 0079AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0079AC or upon CO determination of bona fide need |
ST-070 E - Oil Water Seperator, ST-219
| 0080AA |
| Achieve RIP within five (5) years from NTP |
| At Award |
ST105 - TCE and Nitrate Contaminated GW
| 0081AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0081AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0081AA or upon CO determination of bona fide need |
| 0081AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0081AB or upon CO determination of bona fide need |
| 0081AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0081AC or upon CO determination of bona fide need |
PL567 - SWMU UST 58
| 0082AA |
| Achieve Response Complete (RC) within five (5) years from NTP |
| At Award |
CG570 - EOD Hill
| 0083AA |
| Achieve approved RFI (including background study for Perchlorate) within three (3) years from NTP |
| At Award |
CW571 - ZIA Park
| 0084AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
OT572 - Bldg 5700-1
| 0085AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
OT573 - Asphalt Dump Area
| 0086AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
SS575 - Transient Alert Pad
| 0087AA |
| Achieve Site Closeout (SC) within five (5) years from NTP |
| At Award |
ML125 - Field Firing Range
| 0088AA |
| Achieve Response Complete (RC) within nine (9) years from NTP with an interim objective of achievement of approved Decision Document within four (4) years from NTP |
| At Award |
| 0088AB |
| Achievement of approved Decision Document |
| Approx. 2 years from 0088AA or upon CO determination of bona fide need |
TG100 - Bomb Target
| 0089AA |
| Achieve Response Complete (RC) within five (5) years from NTP |
| At Award |
AL120 - Proximity Fuze Range
| 0090AA |
| Achieve Response Complete (RC) within nine (9) years from NTP with an interim objective of achievement of approved Decision Document within four (4) years from NTP |
| At Award |
| 0090AB |
| Achievement of approved Decision Document |
| Approx. 2 years from 0090AA or upon CO determination of bona fide need |
AL120A - Proximity Fuze Range
| 0091AA |
| Achieve Response Complete (RC) within five (5) years from NTP |
| At Award |
AL120B - Proximity Fuze Range
| 0092AA |
| Achieve Response Complete (RC) within five (5) years from NTP |
| At Award |
PT123 - Tijeras Small Arms Range
| 0093AA |
| Achieve Response Complete (RC) within five (5) years from NTP |
| At Award |
DA130 - Arroyo Del Coyote Demolition Area
| 0094AA |
| Achieve Response Complete (RC) within five (5) years from NTP |
| At Award |
Luke AFB
RW002 - Low Level Radioactive Waste Burial Pit
| 0095AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0095AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0095AA or upon CO determination of bona fide need |
| 0095AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0095AB or upon CO determination of bona fide need |
| 0095AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0095AC or upon CO determination of bona fide need |
LF003 - Outboard Runway Landfill
| 0096AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0096AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0096AA or upon CO determination of bona fide need |
| 0096AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0096AB or upon CO determination of bona fide need |
| 0096AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0096AC or upon CO determination of bona fide need |
FT007 - North Fire Training Area
| 0097AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0097AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0097AA or upon CO determination of bona fide need |
| 0097AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0097AB or upon CO determination of bona fide need |
| 0097AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0097AC or upon CO determination of bona fide need |
FT007E - North Fire Training Area (Eastern - Not in EESOH-MIS)
| 0098AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0098AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0098AA or upon CO determination of bona fide need |
| 0098AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0098AB or upon CO determination of bona fide need |
| 0098AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0098AC or upon CO determination of bona fide need |
DP013 - Drainage Ditch Disposal Area
| 0099AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0099AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0099AA or upon CO determination of bona fide need |
| 0099AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0099AB or upon CO determination of bona fide need |
| 0099AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0099AC or upon CO determination of bona fide need |
LF014 - Old Salvage Yard Burial Site
| 0100AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0100AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0100AA or upon CO determination of bona fide need |
| 0100AC |
| Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP. |
| Approx. 2 years from 0100AB or upon CO determination of bona fide need |
| 0100AD |
| Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP. |
| Approx. 2 years from 0100AC or upon CO determination of bona fide need |
ST018 - Facility 993
| 0101AA |
| Develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP |
| 1Q FY14 |
| 0101AB |
| Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP. |