12_Attachment_9A_EELV_Phase_2_Payment_Plan_SingleManifest.docx
DOCX document 54 KB Posted
- Attached to
- Evolved Expendable Launch Vehicle (EELV) Phase 2 Launch Service Procurement (LSP) Draft Request for Proposals (dRFP) Federal contract opportunity
- Solicitation number
- FA8811-19-R-0002
About this file
This document is a draft request for proposals for Evolved Expendable Launch Vehicle Phase 2 Launch Service Procurement. It seeks industry feedback on meeting National Security Space launch requirements through the draft RFP. Responses to the provided comments resolution matrix are due by December 21, 2018. The North American Industry Classification System code is 481212 and the small business size standard is 1,500 employees. The draft RFP and other documents are available in the unclassified bidder's library, and classified documents can be obtained from the listed point of contact. Feedback from small and small disadvantaged businesses is encouraged.
12 Attachment 9A EELV Phase 2 Payment Plan Single Manifest
View the file
Other files for this federal contract opportunity
Show all 41
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Evolved Expendable Launch Vehicle (EELV) Phase 2 Launch Service Procurement
FA8811-19-R-0002
Attachment 9a Single Manifest Payment Plan
3 December 2018
PRE-DECISIONAL
Single Manifest Payment Plan FA8811-19-R-0002
PRE-DECISIONAL
1. Basis of Payment The basis of payment for single manifest missions shall be the successful accomplishment of event milestones scheduled for a single manifest mission assigned throughout the period of performance of the contract. The milestones represent meaningful efforts or actions that are an integral and necessary part of performance. The basis for an event should be either specifically described events or a measurable criterion of performance. Included within this Payment Plan is what constitutes successful performance of each event. Once a single manifest mission is assigned, the Contractor shall fill in the payment amounts, which are listed here as a percentage of the total contract price for all applicable firm fixed price (FFP) Contract Line Item Numbers (CLINs) pertaining to the mission (CLINs YYX1, YYX2, and YYX7). NRO-only references appear in grey text.
1. milestone Success Criteria and Completion Evidence Each event milestone has associated measurable success criteria that serve to validate milestone accomplishment. All milestone success criteria must be met before the milestone payment will be authorized. When the Launch Vehicle Contractor (LVC) has successfully completed all applicable milestone success criteria, the LVC shall submit a Notice of Completion (NOC) for the milestone to the Procurement Contraction Officer (PCO). The NOC shall include supporting documentation to substantiate meeting the milestone success criteria as provided in the completion evidence defined herein.
1. Event Milestone Payments and Event Timing Completion of milestone and subsequent NOCs may be submitted non-successively (e.g., if milestone two is completed before milestone one, then the LVC may submit an NOC for milestone two before an NOC for milestone one). Additionally, the NOC may be for multiple milestones. In the event the LVC completes a milestone ahead of the milestone completion date, the LVC may include that milestone in the monthly NOC and the Government will consider, on a case-by-case basis, the early payment of the milestone.
The PCO will determine whether or not the LVC has successfully met each of the milestone success criteria based on inputs provided by the United States Government (USG) Team (for Air Force missions) and the Mission Team (for NRO missions).
For Air Force missions, the USG team consists of the Air Force Space and Missile Systems Center Launch Systems Enterprise Directorate (SMC/LE), and the Air Force Program Executive Officer for Space office personnel; and also includes The Aerospace Corporation, LE’s Systems Engineering and Integration (SE&I) Contractor, LE’s Systems Engineering and Technical Assistance (SETA) support Contractors, the NRO/Office of Space Launch (OSL) (as applicable), the SMC Independent Readiness Review Team, Defense Contract Management Agency, Defense Contract Management Agency, Defense Contract Audit Agency, 30th Space Wing (30 SW), 45th Space Wing (45 SW), and other organization as designated by the SMC/LE PCO.
For NRO missions, in addition to the USG Team listed above for Air Force Missions, the Mission Team consists of the OSL Mission Manager (OMM), the OSL Contracting Officer Technical Representative (COTR), and their support personnel (to include Government, Aerospace Corporation, and SETA personnel). At their discretion, the OMM and COTR may solicit inputs from SMC/LE to assist in their determination of the LVC’s satisfactory completion of the milestone success criteria. Written concurrence from both the OMM and COTR that the LVC has successfully met the milestone success criteria is required before the PCO will authorize payment of the milestone.
To the maximum extent possible within fifteen (15) business days after receipt of the LVC’s NOC, the PCO will provide written notification to the LVC specifying which milestones contained in the NOC are determined to be “met” (complete) and, if necessary, which are considered “not met” (incomplete). For milestones identified as incomplete, the PCO will: (1) specify in the notification, the issues(s) that led to the determination based upon the milestone success criteria and completion evidence provided herein, and (2) the corrective action(s) required to complete the milestone. The Government and LVC will ensure agreement and understanding of the corrective actions, and the LVC will make a good faith effort to quickly reconcile an incomplete milestones. When the LVC accomplishes the corrective actions, the LVC will submit an NOC addendum to the PCO for Government review. To the maximum extent possible within fifteen (15) business days after receipt of the LVC’s NOC addendum, the PCO will provide written notification to the LVC specifying whether the Government concurs that all corrective actions have been accomplished and the milestone has been “met” (completed).
For each milestone, the Estimated Completion Date is the estimated date that the LVC will complete the payment event and submit the associated NOC for payment of each milestone under this Plan. For each milestone, the value in the percentage “%” column of Table 1 indicates the percentage of the assigned mission value of all applicable FFP CLINs (CLINs YYX1, YYX2, and YYX7) that will be used to calculate the dollar amount to be paid to the LVC upon successful completion of the milestone. The Government reserves the right to withhold up to fifty percent (50%) of the total payment value for any unpaid milestone(s) in the event of a Government-approved Class 1 change required for the launch service that is not implemented or completed to meet the Government’s approval by the implementation deadlines specified in and in accordance with (IAW) Attachment 1 Performance Work Statement (PWS) section 3.2.4.3.
1. Event Milestone Schedule Criteria for payment of each event milestone appears in Table 1. In no event shall the LVC receive payments in excess of 90% of the total contract price until after acceptance of the launch service IAW Milestone 12 (Government Acceptance of Launch Service IAW contract clause Federal Acquisition Regulation [FAR] 52.212-04, Addendum to Contract Terms and Conditions – Commercial Items [January 2017]). Given that defects in service for the last Milestone 12, Acceptance of Launch Service, are not suitable for correction by re-performance, the PCO has determined that, pursuant to FAR 52.246-4(e), the appropriate relief for the Government in the event of Milestone 12 defect (e.g., mission failure) is to reduce the contract price by the amount of the full Milestone 10, Upper Stage Disposal, Final As-Built Configuration List (ABCL), and Final Fleet Insight ABCL: Milestone 11, Mission Orbital Parameter Accuracy Verification; and Milestone 12 payment, which appropriately reflects the reduced value of the services performed.
Table 1: Single Manifest Mission Payment Event Schedule
| Milestone # |
| Payment Event |
| Accomplishment Criteria |
| Est. Comp. Date |
| Total Payment ($) |
| % of FFP CLINs YYX1, YYX2, and YYX7 |
| 1 |
| Initial Payload Integration & Ops Plan; Initial Flight Critical Items List (FCIL); Updated Mission-Specific Integrated Master Schedule (IMS); Launch Service Provider Non-Recurring Design Validation (NRDV) work closure schedule; Procurement initiated of long lead hardware; and completed Mission Kickoff Review (MKR) |
| · First submission and Government acknowledgement of receipt of the following: Initial Payload Integration & Ops Plan IAW CDRL A023; and Initial FCIL IAW CDRL A035. |
· Submission and Government approval of the updated mission-specific IMS and baseline schedule for NRDV work closure IAW CDRL A038.
· Long lead hardware procurement or build initiated as required.
· MKR completed IAW PWS Appendix G.
| Authority to Proceed (ATP) + 1 month |
| To be filled in by Offeror on Mission Assignment |
| 10% |
| 2 |
| Initial Draft Mission Integration Schedule (MIS) (non-NRO missions); Initial Safety Assessment Report; and Initial As-Designed Configuration List (ADCL) |
| · Submission and Government acknowledgement of receipt of the following: Initial MIS IAW CDRL A009 (non-NRO missions); Initial Safety Assessment Report IAW CDRL A029; and Initial ADCL for the launch vehicle IAW CDRL A033. |
| ATP + 2 months |
| To be filled in by Offeror on Mission Assignment |
| 5% |
| 3 |
| Preliminary mission Interface Control Document (ICD); Initial Launch Vehicle Test & Verification Plan (LVT&VP); Updated MIS (non-NRO missions) |
| · Submission and Government acknowledgement of receipt of the following: Preliminary mission ICD IAW CDRL A025; initial LVT&VP IAW CDRL A037; and updated MIS IAW CDRL A009, as required (non-NRO missions). |
| ATP + 3 months |
| To be filled in by Offeror on Mission Assignment |
| 10% |
| 4 |
| Initial Verification Planning Matrix (VPM); Initial Flight Hardware Interface Checks (non-NRO missions); Updated FCIL; Updated ADCL; Updated Payload Integration & Ops Plan; Final LVT&VP and Final MIS (non-NRO missions) |
| · Submission and Government acknowledgement of receipt of the initial VPM IAW CDRL A027 and initial Flight Hardware Interface Checks IAW CDRL A024 (non-NRO missions). |
· Submission and Government approval of the following: updated FCIL IAW CDRL A035; updated ADCL IAW CDRL A033; updated Payload Integration & Ops Plan IAW CDRL A023; final LVT&VP IAW CDRL A037; and final MIS IAW CDRL A009 (non-NRO missions).
| ATP + 6 Months |
| To be filled in by Offeror on Mission Assignment |
| 10% |
| 5 |
| Preliminary Coupled Loads Analysis (CLA); Updated ADCL |
| · Submission and Government acknowledgement of receipt of the preliminary CLA complete and delivery of results IAW CDRL A039. |
· Submission and Government approval of the updated ADCL IAW CDRL A033.
| ATP + 8 Months |
| To be filled in by Offeror on Mission Assignment |
| 5% |
| 6 |
| Final ADCL; Baseline Mission ICD; Updated VPM; Final Payload Integration and Ops Plan; Final FCIL; Secondary Objectives Risk Analysis; Initial ABCL; Initial Fleet Insight ABCL; Completion of all NRDV Work Closure Plan tasks; Final Technical Rationale for all Class 1A changes; Mission Design Review completed; and Completed Flight Hardware Interface Checks (non-NRO missions), Final Facility Requirements Document (FRD) (non-NRO missions) |
| · Submission and Government approval of the following: Final ADCL IAW CDRL A033; updated baseline mission ICD IAW CDRL A025; updated VPM IAW CDRL A027; final Payload Integration & Ops Plan IAW CDRL A023; final FCIL IAW CDRL A035; and Secondary Objectives Risk Analysis (as applicable) IAW CDRL A030. |
· Submission and Government acknowledgement of receipt of the initial ABCL IAW CDRL A034.
· Submission and Government acknowledgement of receipt of the initial Fleet Insight ABCL IAW CDRL A020.
· Evidence demonstrating the completion of all NRDV Work Closure Plan tasks IAW CDRL A038.
· Final technical rationale for all Class 1A changes IAW PWS section 3.2.4.3.2 and CDRL A036.
· Mission Design Review completed IAW PWS Appendix G.
· Flight hardware Interface Checks completed IAW PWS paragraph 3.4.10 and CDRL A024 (non-NRO missions).
· Government approval of Final FRD IAW CDRL A017 (non-NRO missions).
| Launch (L) – 12 Months |
| To be filled in by Offeror on Mission Assignment |
| 20% |
| 7 |
| Launch countdown parameters and operational redline limits; Mission Assurance Data; Updated ABCL; Updated Fleet Insight ABCL; and completion of the Mission Verification Review |
| · Submission and Government acknowledgement of receipt of the launch countdown parameters and operational redline limits baseline IAW PWS section 3.2.6; and Mission Assurance Independent Assessment Data IAW CDRL A039 to include: intermediate unguided three Degrees of Freedom (3-DOF); Collision and Contamination Avoidance Maneuver Memo; acoustics, shock, and vibration environments; vibroacoustic modeling and analysis; engineering drawings; and transportation environments. |
· Submission and Government approval of the updated ABCL IAW CDRL A034.
· Submission and Government approval of the updated Fleet Insight ABCL IAW CDRL A020.
· Mission Verification Review completed IAW PWS Appendix G.
| L – 6 Months |
| To be filled in by Offeror on Mission Assignment |
| 10% |
| 8 |
| Verification Evidence Record; Updated ABCL; Updated Fleet Insight ABCL; Completion of Ground Operations Readiness Review |
| · Submission and Government acknowledgement of receipt of at least 30% of Verification Evidence Record IAW CDRL A028. |
· Submission and Government approval of updated ABCL IAW CDRL A034.
· Submission and Government approval of updated Fleet Insight ABCL IAW CDRL A020.
· Ground Operations Readiness Review completed IAW PWS Appendix G.
| L – 3 Months |
| To be filled in by Offeror on Mission Assignment |
| 5% |
| 9 |
| Verification Evidence Record; Updated ABCL; Updated Fleet Insight ABCL; Mission Assurance Data; Completion of Pre-Ship Review(s) and Independent Hardware Review(s); and Completion of Component and Subsystem Readiness Review |
| · Submission and Government acknowledgement of receipt of at least 60% of Verification Evidence Record IAW CDRL A028; Mission Assurance Independent Assessment Data IAW CDRL A039: controls tools input data; controls analysis outputs (except pad/launch drift analysis); acoustics, shock, and vibration testing; and interface environment. |
· Submission and Government approval of the updated ABCL IAW CDRL A034.
· Submission and Government approval of the updated Fleet Insight ABCL IAW CDRL A020.
· Completion of major launch vehicle pre-ship reviews and Government independent hardware review(s) IAW PWS sections 3.6.7.1 and 3.6.6, respectively.
· Completion of Component and Subsystem Readiness Review IAW PWS Appendix G.
| L- 2 Months |
| To be filled in by Offeror on Mission Assignment |
| 15% |
| 10 |
| Upper Stage Disposal; Final ABCL; and Updated Fleet Insight ABCL |
| · Submission and Government approval of compliance with upper stage disposal requirements IAW CDRL A044. |
· Submission and Government approval of final ABCL IAW CDRL A034.
· Submission and Government approval of updated Fleet Insight ABCL IAW CDRL A020.
| L + 2 Months |
| To be filled in by Offeror on Mission Assignment |
| 1.5% |
| 11 |
| Mission Orbital Parameter Accuracy Verification |
| · Submission and Government approval of final post-flight assessment report IAW CDRL A044; and IAW the Success Criteria outlined in Milestone 12 in this attachment. |
| L + 2 Months |
| To be filled in by Offeror on Mission Assignment |
| 3.5% |
| 12 |
| Government Acceptance of Launch Service |
| · Submission and Government approval of final post-flight assessment report IAW CDRL A044: and Government approval of the launch (launch has not been deemed “mission failure”) IAW PWS Appendix A and the Launch Service Acceptance Criteria (LSAC) outlined in contract Attachment 4. |
| L + 2 Months |
| To be filled in by Offeror on Mission Assignment |
| 5% |
* The dollar amount for each milestone is to be filled in by the Offeror upon Mission Assignment and is equal to the percentage listed in the last column multiplied by the value of the launch mission (CLINs YYX1, YYX2, and YYX7) prior to award of each milestone. No adjustment to the payment will occur after milestone award.
1. Event Milestone Descriptions Milestone 1: Initial Payload Integration & Ops Plan; Initial Flight Critical Items List (FCIL); Updated Mission-Specific Integrated Master Schedule (IMS); Launch Service Provider Non-Recurring Design Validation (NRDV) work closure schedule; Procurement initiated of long lead hardware; and Completed Mission Kickoff Review (MKR) Description:
1. Initial Payload Integration and Ops Plan. LVC’s initial Payload Integration and Ops Plan delivered, and the Government has acknowledged receipt IAW PWS paragraph 3.5.3.5 and CDRL A023.
2. Initial FCIL. LVC’s initial FCIL delivered, and the Government has acknowledged receipt IAW PWS paragraph 3.2.4.2.3 and CDRL A035.
3. Updated Mission-Specific IMS. LVC’s updated mission-specific IMS delivered, and the Government has acknowledged receipt IAW CDRL A008.
4. NRDV Work Closure Schedule. LVC’s baseline launch service provider NRDV work closure schedule and plan delivered and approved by the Government IAW CDRL A038.
5. Long Lead Hardware Procurement or Production Initiated. LVC has initiated procurement orders for or production of long lead hardware required for the mission.
6. Mission Kickoff Review. LVC has conducted the Mission Kickoff Review (MKR) IAW with PWS Appendix G with actions and action closure plans, and accepted by the Government.
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of initial Payload Integration and Ops Plan IAW PWS paragraph 3.5.3.5 and CDRL A023.
2. The LVC has delivered and the Government has acknowledged receipt of initial FCIL IAW PWS paragraph 3.2.4.2.3 and CDRL A035.
3. The LVC has delivered and the Government has acknowledged receipt of updated mission-specific IMS IAW CDRL A008.
4. The LVC has delivered and the Government has approved the baseline launch service provider NRDV work closure schedule and plan IAW CDRL A038.
5. The LVC has initiated procurement orders for or production of long lead hardware required for the mission.
6. The LVC has conducted the MKR IAW with PWS Appendix G with actions and action closure plans, and the Government has accepted.
Completion Evidence:
1. CDRL A023 initial draft Payload Integration and Ops Plan accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A035 initial FCIL accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL A008 updated mission-specific IMS accepted by the PCO, appropriate COR, or appropriate COTR.
4. CDRL A038 baseline launch service provider NRDV work closure schedule and plan accepted by the PCO, appropriate COR, or appropriate COTR.
5. Long lead hardware procurement or build initiated as required for the mission. Copies of signed, written procurement or build orders for all long lead hardware required for the mission received and accepted by the PCO, appropriate COR, or appropriate COTR
6. MKR meeting minutes documenting meeting completion, action items, and action item closure plans.
Milestone 2: First Submission MIS (non-NRO missions), First Submission Safety Assessment Report, and First Submission ADCL Description:
1. MIS. The LVC’s initial MIS delivered (non-NRO missions), and the Government has acknowledged receipt IAW PWS paragraph 3.4.2.1 and CDRL A009.
2. Safety Assessment Report. The LVC’s initial Safety Assessment Report delivered, and the Government has acknowledged receipt IAW PWS paragraph 3.1.10.1 and CDRL A029.
3. ADCL. LVC’s initial ADCL delivered, and the Government has acknowledged receipt IAW CDRL A033.
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of the initial MIS IAW PWS paragraph 3.4.2.1 and CDRL A009 (non-NRO missions).
2. The LVC has delivered and the Government has acknowledged receipt of the initial Safety Assessment Report IAW PWS paragraph 3.1.10.1 and CDRL A029.
3. The LVC has delivered and the Government has acknowledged receipt of the initial ADCL IAW CDRL A033.
Completion Evidence:
1. CDRL A009 initial MIS accepted by the PCO, appropriate COR, or appropriate COTR (non-NRO missions).
2. CDRL A029 initial Safety Assessment Report accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL A033 initial ADCL accepted by the PCO, appropriate COR, or appropriate COTR.
Milestone 3: Preliminary Interface Control Document (ICD); Initial Launch Vehicle Test & Verification Plan (LVT&VP); and updated Mission Integration Schedule (MIS) (non-NRO missions) Description:
1. ICD. LVC’s initial baseline mission ICD delivered, and the Government has acknowledged receipt IAW PWS paragraph 3.4.4 and CDRL A025.
2. LVT&VP. LVC’s initial LVT&VP delivered, and the Government has acknowledged receipt IAW PWS paragraph 3.2.5 and CDRL A037.
3. MIS. The LVC’s updated MIS delivered, and the Government has acknowledged receipt IAW PWS paragraph 3.4.2.1 and CDRL A009 (non-NRO missions).
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of the initial, first draft mission ICD IAW CDRL A025.
2. The LVC has delivered and the Government has acknowledged receipt of the initial LVT&VP IAW CDRL A037.
3. The LVC has delivered and the Government has acknowledge receipt of the updated MIS IAW PWS paragraph 3.4.2.1 and CDRL A009 (non-NRO missions).
Completion Evidence:
1. CDRL A025 initial, first draft baseline mission ICD accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A037 initial LVT&VP accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL A009 updated MIS accepted by the PCO, appropriate COR, or appropriate COTR (non-NRO missions).
Milestone 4: Initial Verification Planning Matrix (VPM); Initial Flight Hardware Interface Checks (non-NRO missions); updated FCIL; updated ADCL; updated Payload Integration and Ops Plan; Final LVT&VP; and Final MIS (non-NRO missions) Description:
1. VPM. LVC’s first draft VPM delivered, and the Government has acknowledged receipt IAW CDRL A027.
2. Flight Hardware Interface Checks. LVC’s initial Flight Hardware Interface Checks delivered (non-NRO missions), and the Government has acknowledged receipt IAW CDRL A024.
3. FCIL. The LVC has delivered, and the Government has approved the updated FCIL IAW PWS paragraph 3.2.4.2.3 and CDRL A035.
4. ADCL. The LVC has delivered, and the Government has approved the updated ADCL IAW CDRL A033.
5. Payload Integration and Ops Plan. The LVC has delivered, and the Government has approved the updated Payload Integration and Ops Plan IAW PWS paragraph 3.5.3.5 and CDRL A023.
6. LVT&VP. The LVC has delivered, and the Government has approved the final LVT&VP IAW CDRL A037.
7. MIS. The LVC’s has delivered and the Government has approved the final MIS IAW PWS paragraph 3.4.2.1 and CDRL A009 (non-NRO missions).
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of the first draft VPM IAW CDRL A027.
2. The LVC has delivered and the Government has acknowledged receipt of initial Flight hardware Interface Checks IAW CDRL A024 (non-NRO missions).
3. The LVC has delivered and the Government has approved the updated FCIL IAW PWS paragraph 3.2.4.2.3 and CDRL A035.
4. The LVC has delivered and the Government has approved the updated ADCL IAW CDRL A033.
5. The LVC has delivered and the Government has approved the updated Payload Integration and Ops Plan IAW PWS paragraph 3.5.3.5 and CDRL A023.
6. The LVC has delivered and the Government has approved the final LVT&VP IAW CDRL A037.
7. The LVC has delivered and the Government has approved the final MIS IAW PWS paragraph 3.4.2.1 and CDRL A009 (non-NRO missions).
Completion Evidence:
1. CDRL A027 first draft VPM accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A024 initial Flight Hardware Interface Checks accepted by the PCO, appropriate COR, or appropriate COTR (non-NRO missions).
3. CDRL A035 updated FCIL accepted by the PCO, appropriate COR, or appropriate COTR.
4. CDRL A033 updated ADCL accepted by the PCO, appropriate COR, or appropriate COTR.
5. CDRL A023 updated Payload Integration and Ops Plan accepted by the PCO, appropriate COR, or appropriate COTR.
6. CDRL A037 final LVT&VP accepted by the PCO, appropriate COR, or appropriate COTR.
7. CDRL A009 final MIS accepted by the PCO, appropriate COR, or appropriate COTR (non-NRO missions).
Milestone 5: Preliminary Coupled Loads Analysis (CLA) and Updated ADCL Description:
1. Preliminary CLA. The LVC has completed preliminary CLA, submitted the preliminary CLA data, and the Government has acknowledged receipt of the CLA data IAW CDRL A039.
2. Updated ADCL. The LVC has delivered, and Government has approved the updated ADCL IAW CDRL A033.
Success Criteria:
1. The LVC has completed preliminary CLA, submitted the preliminary CLA data, and the Government has acknowledged receipt of the CLA data IAW CDRL A039.
2. The LVC has delivered and the Government has approved the updated ADCL IAW CDRL A033.
Completion Evidence:
1. CDRL A039 preliminary CLA data accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A033 updated ADCL accepted by the PCO, appropriate COR, or appropriate COTR.
Milestone 6: Final ADCL; Updated Baseline Mission ICD; Updated VPM; Final Payload Integration & Ops Plan; Final FCIL; Approved Secondary Objectives Risk Analysis; Initial ABCL; Initial Flight Insight ABCL; NRDV Work Closure Plan Complete; Submission of Rationale for All Class 1A Changes; Mission Design Review Complete; Flight Hardware Interface Checks Complete (non-NRO missions); Facility Requirements Document (non-NRO missions) Description:
1. Final ADCL. LVC’s final ADCL delivered, and Government has approved IAW CDRL A033.
2. Updated Baseline Mission ICD. LVC’s updated baseline mission ICD delivered, and Government has approved IAW CDRL A025.
3. Updated VPM. LVC’s updated VPM submitted, and the Government has approved IAW CDRL A027.
4. Final Payload Integration and Ops Plan. LVC’s final Payload Integration and Ops Plan delivered, and the Government has approved IAW PWS paragraph 3.5.3.5 and CDRL A023.
5. Final FCIL. LVC’s final FCIL delivered, and the Government has approved IAW PWS paragraph 3.2.4.2.3 and CDRL A035.
6. Approved Secondary Objectives Risk Analysis (as applicable). The LVC has delivered and the Government has approved the final Secondary Objectives Risk Analysis IAW CDRL A030.
7. Initial ABCL. LVC’s initial ABCL delivered, and the Government has acknowledged receipt IAW CDRL A034.
8. Initial Fleet Insight ABCL. LVC’s initial Fleet Insight ABCL delivered, and the Government has acknowledged receipt IAW CDRL A020.
9. NRDV Work Closure Plan Complete. LVC’s launch service provider NRDV work is complete with Government-approved exceptions allowed, and all action items have been closed, with Government-approved exceptions allowed IAW the LVC’s Government-approved baseline NRDV work closure plan and schedule, CDRL A038.
10. Rationale for All Class 1A Changes. LVC has submitted technical rationale for all Class 1A changes, and the Government has approved IAW PWS paragraph 3.2.4.3.2 and CDRL A036.
11. Mission Design Review. LVC has conducted the Mission Design Review IAW with PWS Appendix G with actions and action closure plans, and accepted by the Government.
12. Flight Hardware Interface Checks (non-NRO missions). The LVC shall perform tests to verify the compatibility of the physical and electrical interfaces and clearances between the LV and the Payload IAW PWS paragraph 3.4.12 and CDRL A024. The LVC shall perform mechanical fit-checks of the adapter harness to the standard electrical interfaces panel for the SV. The testing shall verify that all physical interfaces meet mission ICD requirements. These tests shall be performed, with SV contractor/Launch Systems Integration contractor support, to satisfy all applicable requirements in the ICD, PWS, and CDRL A024 (non-NRO missions).
13. Facility Requirements Document. The LVC has delivered (non-NRO missions) and the Government has approved the final Facility Requirements Document submission IAW CDRL A017.
Success Criteria:
1. The LVC has delivered and the Government has approved final ADCL IAW CDRL A033.
2. The LVC has delivered and the Government has approved updated ICD IAW CDRL A025.
3. The LVC has delivered and the Government has approved updated VPM IAW CDRL A027.
4. The LVC has delivered and the Government has approved final Payload Integration and Ops Plan IAW PWS paragraph 3.5.3.5 and CDRL A023.
5. The LVC has delivered and the Government has approved final FCIL IAW PWS paragraph 3.2.4.2.3 and CDRL A035.
6. The LVC has delivered and the Government has approved final Secondary Objectives Risk Analysis (as applicable) IAW CDRL A030.
7. The LVC has delivered and the Government has acknowledged receipt of the initial ABCL IAW CDRL A034.
8. The LVC has delivered and the Government has acknowledged receipt of the initial Fleet Insight ABCL IAW CDRL A020.
9. The LVC has completed and the Government has approved (with allowed exceptions) the launch service provider NRDV work IAW CDRL A038.
10. The LVC has delivered and the Government has approved the technical rational for all Class 1A changes IAW PWS paragraph 3.2.4.3.2 and CDRL A036.
11. The LVC has conducted the Mission Design Review IAW with PWS Appendix G with actions and action closure plans, and the Government has accepted.
12. The LVC has performed Flight Hardware Interface Checks IAW PWS paragraph 3.4.10 and CDRL A024 (non-NRO missions).
a. The LVC has delivered a second submission of as-run interface check procedures, and the Government has accepted receipt.
13. The LVC has delivered and the Government has acknowledged receipt of the final Facility Requirements Document IAW CDRL A017 (non-NRO missions).
Completion Evidence:
1. CDRL A033 final ADCL accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A025 updated ICD accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL A027 updated VPM accepted by the PCO, appropriate COR, or appropriate COTR.
4. CDRL A023 final Payload Integration and Ops Plan accepted by the PCO, appropriate COR, or appropriate COTR.
5. CDRL A035 final FCIL accepted by the PCO, appropriate COR, or appropriate COTR.
6. CDRL A030 final Secondary Objectives Risk Analysis (as applicable) accepted by the PCO, appropriate COR, or appropriate COTR.
7. CDRL A034 initial ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
8. CDRL A020 initial Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
9. CDRL A038 baseline launch service provider NRDV work completion (with allowed exceptions) accepted by the PCO, appropriate COR, or appropriate COTR.
10. CDRL A036 Class 1A changes technical rationale accepted by the PCO, appropriate COR, or appropriate COTR
11. Mission Design Review meeting minutes documenting meeting completion, action items, and action item closure plans.
12. CDRL A024 Flight Hardware Interface Checks completion accepted by the PCO, appropriate COR, or appropriate COTR (non-NRO missions).
13. CDRL A017 final Facility Requirements Document accepted by the PCO, appropriate COR, or appropriate COTR (non-NRO missions).
Milestone 7: Launch Countdown Parameters and Operational Redline Limits; Mission Assurance Data; Updated ABCL; Updated Fleet Insight ABCL; Mission Verification Review Completion Description:
1. Launch Countdown Parameters and Operational Redline Limits. LVC’s Launch Countdown Parameters and Operational Redline Limits delivered, and Government has acknowledged receipt IAW PWS paragraph 3.2.6.
2. Mission Assurance Data. LVC’s Mission Assurance Independent Assessment Data delivered, and Government has acknowledged receipt IAW CDRL A039 to include: intermediate unguided 3-DOF; Collision and Contamination Avoidance Maneuver memo; acoustics, shock, and vibration environments; vibroacoustic modeling and analysis; engineering drawings; and transportation environments.
3. Updated ABCL. LVC’s updated ABCL delivered, and the Government has approved IAW CDRL A034.
4. Updated Fleet Insight ABCL. LVC’s updated Fleet Insight ABCL delivered, and the Government has approved IAW PWS CDRL A020.
5. Mission Verification Review Completion. LVC has conducted the Mission Verification Review IAW with PWS Appendix G with actions and action closure plans, and accepted by the Government.
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of Launch Countdown Parameters and Operational Redline Limits IAW PWS paragraph 3.2.6.
2. The LVC has delivered and the Government has acknowledged receipt of Mission Assurance Independent Assessment Data IAW CDRL A039 to include: intermediate unguided 3-DOF; Collision and Contamination Avoidance Maneuver memo; acoustics, shock, and vibration environments; vibroacoustic modeling and analysis; engineering drawings; and transportation environments.
3. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL A034.
4. The LVC has delivered and the Government has approved the updated Fleet Insight ABCL IAW CDRL A020.
5. The LVC has conducted the Mission Verification Review IAW with PWS Appendix G with actions and action closure plans, and the Government has accepted.
Completion Evidence:
1. Written acknowledgement of receipt of Launch Countdown Parameters and Operational Redline Limits by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A039 Mission Assurance Independent Assessment Data accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL A034 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
4. CDRL A020 updated Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
5. Mission Verification Review meeting minutes documenting meeting completion, action items, and action item closure plans.
Milestone 8: Verification Evidence Record; Updated ABCL; Updated Fleet Insight ABCL; and Ground Operations Readiness Review Completion Description:
1. Verification Evidence Record. LVC’s delivery of at least 30% of Verification Evidence Record, and Government has acknowledged receipt IAW CDRL A028.
2. Updated ABCL. LVC’s updated ABCL delivered, and the Government has approved IAW CDRL A034.
3. Updated Fleet Insight ABCL. LVC’s updated Fleet Insight ABCL delivered, and the Government has approved IAW CDRL A020.
4. Ground Operations Readiness Review. LVC has conducted the Ground Operations Readiness Review IAW with PWS Appendix G with actions and action closure plans, and accepted by the Government.
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of at least 30% of the Verification Evidence Record IAW CDRL A028.
2. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL A034.
3. The LVC has delivered and the Government has approved the updated Fleet Insight ABCL IAW CDRL A020.
4. The LVC has conducted the Ground Operations Readiness Review IAW with PWS Appendix G with actions and action closure plans, and the Government has accepted.
Completion Evidence:
1. CDRL A028 delivery of at least 30% Verification Evidence Record accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A034 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL A020 updated Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
4. Ground Operations Readiness Review meeting minutes documenting meeting completion, action items, and action item closure plans.
Milestone 9: Verification Evidence Record; Updated ABCL; Updated Fleet Insight ABCL; Mission Assurance Data; Completion of Pre-Ship Review(s) and Independent Hardware Review(s); Component and Subsystem Readiness Review Completion Description:
1. Verification Evidence Record. LVC’s delivery of at least 60% of Verification Evidence Record, and Government has acknowledged receipt IAW CDRL A028.
2. Updated ABCL. LVC’s updated ABCL delivered, and the Government has approved IAW CDRL A034.
3. Updated Fleet Insight ABCL. LVC’s updated Fleet Insight ABCL delivered, and the Government has approved IAW CDRL A020.
4. Mission Assurance Data. LVC’s Mission Assurance Data delivered, and Government has acknowledged receipt IAW and CDRL A039 to include: controls tools input data; controls analysis outputs (except pad/launch drift analysis); acoustics, shock, and vibration testing; and interface environments.
5. Pre-Ship Review(s) and Independent Hardware Review(s). The LVC shall conduct and complete pre-ship review(s) for the major launch vehicle elements prior to shipment to the launch site IAW PWS paragraph 3.6.7.1. The major launch vehicle elements shall include: core booster(s), upper stage, payload fairing, payload adapter, and solid rocket motors (as applicable).
6. Component and Subsystem Readiness Review. LVC has conducted the Component and Subsystem Readiness Review (MKR) IAW with PWS Appendix G with actions and action closure plans, and accepted by the Government.
Success Criteria:
1. The LVC has delivered and the Government has acknowledged receipt of at least 60% of the Verification Evidence Record IAW CDRL A028.
2. The LVC has delivered and the Government has approved the updated ABCL IAW CDRL A034.
3. The LVC has delivered and the Government has approved the updated Fleet Insight ABCL IAW CDRL A020.
4. The LVC has delivered and the Government has acknowledged receipt of Mission Assurance Data IAW CDRL A039 to include: controls tools input data; controls analysis outputs (except pad/launch drift analysis); acoustics, shock, and vibration testing; and interface environments.
5. The LVC has delivered and the Government has acknowledged receipt of the pre-ship reviews for the major launch vehicle elements prior to shipment to the launch site IAW PWS paragraph 3.6.7.1 to include: core booster(s), upper stage, payload fairing, payload adapter, and solid rocket motors (as applicable).
6. The LVC has conducted the Component and Subsystem Readiness Review IAW with PWS Appendix G with actions and action closure plans, and the Government has accepted.
Completion Evidence:
1. CDRL A028 delivery of at least 60% Verification Evidence Record accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A034 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL A020 updated Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
4. CDRL A039 Mission Assurance Data accepted by the PCO, appropriate COR, or appropriate COTR.
5. Delivery of the Pre-Ship Review(s) and Independent hardware Review(s) IAW PWS paragraphs 3.6.7.1 and 3.6.6 accepted by the PCO, appropriate COR, or appropriate COTR. Written acknowledgement by the Government that pre-ship reviews have been completed for the core booster(s), upper stage, payload fairing, payload adapter, and solid rocket motors (as applicable) IAW PWS paragraph 3.6.7.1.
6. Component and Subsystem Readiness Review meeting minutes documenting meeting completion, action items, and action item closure plans.
Milestone 10: Upper Stage Disposal; Final ABCL; Updated Fleet Insight ABCL Description:
1. Upper Stage Disposal. The LVC shall identify which upper stage disposal method was planned and flown (random atmospheric reentry, controlled atmospheric reentry, maneuvering to a storage orbit, direct retrieval) IAW CDRL A044. The LVC shall provide telemetry data confirming the depletion of upper stage propellant (by blowdown, depletion burn, or the release of compressed gases) IAW CDRL A044. The LVC shall provide the following information dependent upon which disposal method was flown:
a. Random atmospheric reentry: Value for risk of human casualty, state vector for end of mission upper stage disposal orbit, disposal orbit lifetime for upper stage based on as-flown end of mission, description of analysis that produced the upper stage disposal orbit lifetime value.
b. Controlled atmospheric reentry: Latitude and longitude of upper stage reentry impact location and comparison to Notice to Airmen and Mariners box.
c. Maneuvering to storage orbit: Orbital elements at end of mission for as flown upper stage.
d. Direct retrieval: Description of retrieval operation. Time after end of mission when upper stage will be removed.
2. Final ABCL. LVC’s final ABCL delivered, and the Government has approved IAW CDRL A034.
3. Updated Fleet Insight ABCL. LVC’s updated Fleet Insight ABCL delivered, and the Government has approved IAW CDRL A020.
4. The Launch Service Order has been accepted by the Government IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
Success Criteria:
1. The LVC identified which upper stage disposal method was flown IAW CDRL A044. The LVC provided telemetry data confirming the depletion of upper stage propellant (by blowdown, depletion burn, or the release of compressed gases) IAW CDRL A044. The Government accepted the Upper Stage disposal using the following criteria dependent upon which disposal method was flown:
a. Random atmospheric reentry: Risk of human casualty is less than 1 in 10,000. Disposal orbit lifetime is no longer than 25 years.
b. Controlled atmospheric reentry: Impact location is within the Notice to Airmen and Mariners box.
c. Maneuvering to storage orbit: End of mission disposal orbit is within one of the storage orbit regimes described in the USG Orbital Debris Mitigation Standard Practices (4-1b).
d. Direct retrieval: Upper stage is removed within the time defined in the Space Debris Assessment Report for this mission.
2. The LVC has delivered and the Government has approved the final ABCL IAW CDRL A034.
3. The LVC has delivered and the Government has approved the updated Fleet Insight ABCL IAW CDRL A020.
4. The Launch Service Order has been accepted by the PCO IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
Completion Evidence:
1. CDRL A044 Orbital Debris Compliance, via telemetry data confirming depletion of propellant and disposal approach, accepted by the PCO, appropriate COR, or appropriate COTR.
2. CDRL A034 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
3. CDRL A020 updated Fleet Insight ABCL accepted by the PCO, appropriate COR, or appropriate COTR.
4. No written determination by the SMC/LE Director deeming the Launch Service Order a “Mission Failure” IAW PWS Appendix A, and Attachment 4, LSAC. PCO’s written notification to the LVC that the mission launched has been accepted by the Government IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
Milestone 11: Mission Orbital Parameter Accuracy Verification Description:
1. Mission Orbital Parameter Accuracy Verification. The orbital parameter accuracy requirement is met IAW the mission ICD and CDRL A025.
2. The LVC had delivered the Final Post Flight Assessment Report IAW CDRL A044.
3. The Launch Service Order has been accepted by the Government IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
Success Criteria:
1. The orbital parameter accuracy requirement is met IAW the mission ICD and CDRL A025.
2. The LVC has delivered and the Government has approved the Final Post Flight Assessment Report IAW CDRL A044.
3. The Launch Service Order has been accepted by the PCO IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
Completion Evidence:
1. CDRL A044 final submission accepted by the PCO, appropriate COR, or appropriate COTR.
2. No written determination by the SMC/LE Director deeming the Launch Service Order a “Mission Failure” IAW PWS Appendix A, and Attachment 4, LSAC. PCO’s written notification to the LVC that the mission launched has been accepted by the Government IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
Milestone 12: Government Acceptance of Launch Service Description:
1. The LVC has delivered and the Government has approved the Final Post Flight Assessment Report IAW CDRL A044.
2. The Launch Service Order has been accepted by the Government IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
Success Criteria:
1. The LVC has delivered and the Government has approved the Final Post Flight Assessment Report IAW CDRL A044.
2. The mission has not been deemed a “Mission Failure” IAW PWS Appendix A, and Attachment 4, LSAC. The Launch Service Order has been accepted by the PCO IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
Completion Evidence:
1. CDRL A044 final submission accepted by the PCO, appropriate COR, or appropriate COTR.
2. No written determination by the SMC/LE Director deeming the Launch Service Order a “Mission Failure” IAW PWS Appendix A, and Attachment 4, LSAC. PCO’s written notification to the LVC that the mission launched has been accepted by the Government IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.
File details come from the government source that posted it. Updated .