19ba3_Attach_1a_Project_Specs_Addendum_1.doc
DOC document 42 KB Posted
- Attached to
- Modernize C4 Restrooms/Break Area Federal contract opportunity
- Solicitation number
- FA875119BA003
About this file
Attachment 1a - Specifications Addendum
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 19ba3_Additional_Information_5.docx | DOCX document | |
| 221316_FL_-_Sanitary_Waste_and_Vent_Piping_RFI_5.pdf | ||
| 19ba3_Additional_Information_4.docx | DOCX document | |
| Solicitation_Amendment_2_FA875119BA0030002_SF_30.pdf | ||
| Solicitation_Amendment_FA875119BA0030001_SF_30.pdf | ||
| 19ba3_Additional_Information_3.docx | DOCX document | |
| 19ba3_Additional_Information_2.docx | DOCX document | |
| A_-_18841_Rome_AF_B-3_asbestos_lead.pdf | ||
| 19ba3_Additional_Information_1.docx | DOCX document | |
| 19ba3_Attach_2_Project_Drawings.pdf | ||
| Solicitation_-_FA875119BA003.pdf | ||
| 19ba3_Attach_3_AFRL_RI_Suppl_Rqmts.pdf | ||
| 19ba3_Attach_4_Wage_Decision.pdf | ||
| 19ba3_Attach_5_RRS_Visit_Authorization_Rqst.pdf | ||
| 19ba3_Attach_1_Project_Specifications.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project:
Modernize C4 Restrooms and Break Room B3
Agency: Department of the Air Force
Office: Air Force Materiel Command
Location: AFRL/RIK - Rome Date of Issue:
10 JUL 2019
TO ALL BIDDERS:
The following additions, deletions, and/or changes or clarifications to the drawings, specifications, and bidding documents for this project, shall become and are hereby made part of the Contract Documents. They change the original documents only in the manner and to the extent stated. Each bidder shall acknowledge receipt of this ADDENDUM in the appropriate location on the bid proposal form.
This ADDENDUM consists of one (1) pages, including this page. All requirements of the original Specifications and Drawings and previous Addendum, if applicable, shall remain in force except as noted by this ADDENDUM.
THE PURPOSE OF THIS ADDENDUM IS TO CHANGE THE FOLLOWING ITEMS:
SPECIFICATIONS ISSUED FEBRUARY 22, 2019:
Section 014000 – QUALITY REQUIREMENTS – DELETE this section in its entirety.
NOTE: Testing and inspecting services – including special inspections - are required exclusively by the Contractor to verify compliance with requirements specified or indicated. These testing and inspecting services do not relieve Contractor of any responsibility for compliance with the Contract Document requirements.
1.2
087100 - DOOR HARDWARE
a) Paragraph 3.4A - REPLACE the word “Owner” with “Contractor”.
1.3
SECTION 099123 – INTERIOR PAINTING
Paragraph 2.3A.1 – ADD “at Contractor’s expense” at beginning of sentence.
1.4
SECTION 221123 - INLINE, DOMESTIC-WATER PUMPS
a) Paragraph 3. 4A - REPLACE the word “Owner” with “Contractor”.
1.5
SECTION 223300 - ELECTRIC, DOMESTIC-WATER HEATER
a) Paragraph 3.3A - REPLACE the word “Owner” with “Contractor”.
1.6
SECTION 233416 - CENTRIFUGAL HVAC FANS
a) Paragraph 3.5A - REPLACE the word “Owner” with “Contractor”.
END OF ADDENDUM NO.1
FA875119BA003
ATACHMENT 1a PROJECT SPECIFICATIONS ADDENDUM 1